Topic 7 - Capital Budgeting Decision Flashcards

1
Q

NPV decision rule (for a single stand alone project)

A

if NPV > 0, then accept
if NPV < 0. then reject

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Maximum Estimation Error

A

the difference between the IRR and the true cost of capital, the maximum estimation error that can exist without altering the initial position

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

IRR decision rule

A

the internal rate of return is the discount rate at which the NPV is 0. we calculate is using trial and error, then interpolation.

if IRR > 0 reject
if IRR < 0 accept

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Interpolation Formula

A

IRR = rlow +
(NPV low / NPV low - NPV high) x (rhigh-rlow)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Limitations of IRR

A
  • Delayed investment
  • Sometimes there is no IRR
  • Sometimes there are multiple IRR’s
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

NPV or IRR?

A

When they provide conflicting answers, then we follow the NPV rule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Delayed investment impact on IRR rule

A

When the benefits of an investment occur before the costs, the NPV and the IRR will conflict in this scenario.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Multiple IRR’s impact on IRR rule

A

This is a situation where the cash flow is unconventional as it switches between positive and negative, creating multiple crossover points ie IRRs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

No IRR, impact on IRR rule

A

In some cases we have no IRR at all, in this case we can’t apply this rule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Payback Period

A

the amount of time it takes to recover or pay back the initial investment

if PB period < specified time scale, then accept
if PB period > specified time scale, then reject

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

PB period formula

A

PB = Years before cost recovery + Remaining cost / CF during the year

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Limitation of the Payback Rule

A
  • it ignores the project’s cost of capital and time value of money
  • it ignores cash flows after the PB period
  • it relies on AD HOC decision criterion ie. what is the right amount of time to require for the PB period?
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Comparison of IRR and NPV

A

BOTH
- account for time value of money

Investment Size
- NPV takes this into account
- IRR fails to measure wealth changes

Additivity
- NPV is possible
- IRR isnt possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Profitability Index + formula

A

when resources are limited, the profitability index provides a tool for identifying the optimal combination of projects to undertake

PI = NPV / resource consumed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Pitfalls of Profitability Index

A
  • it doesn’t optimize the available resources
  • with multiple resource constraints, the PI breaks down completely
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What rule should be used with resource constraints?

A

Profitability Index - rank projects based on PI highest to lowest

17
Q

What rule should be used with mutually exclusive projects?

A

NPV rule - select the one with the highest NPV

18
Q

What rules should be used for a single stand alone project?

A

NPV
IRR
Payback period

19
Q

Break-even analysis

A

the point at which a businesses revenues cover its costs exactly i.e. NPV = 0
the IRR is the break even point

20
Q

Sensitivity Analysis

A