Time Facts & Task Relationships Flashcards
Lag
Waiting time between activities (positive
time
Lead
Activities are moved closer together or
overlap (negative time).
Crashing
Adding resources to reduce the project
duration. Crashing adds costs to the project.
Fast Tracking
Allows project phases to overlap
to reduce the project duration. Fast-tracking adds
risk to the project.
Free Float
The amount of time an activity can be
delayed without delaying the next activity’s start
date.
Total Float
The amount of time an activity can be
delayed without delaying the project’s end date.
Finish-to-Start (FS)
This relationship means
Task A must complete before Task B can begin.
This is the most common relationship.
Start-to-start (SS)
This relationship means
Task A must start before Task B can start. This
relationship allows both activities to happen in
tandem.
Finish-to-finish (FF)
This relationship means
Task A must complete before Task B does.
Ideally, two tasks must finish at exactly the same
time, but this is not always the case.
Start-to-finish (SF)
This relationship is unusual
and is rarely used. It requires Task A to start so
that Task B may finish. It is also known as just-in time
(JIT) scheduling.