Time Flashcards

0
Q

What is the only non-planning process during the time management knowledge area?

A

Control schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

What are the 6 processes in the Time Management knowledge area? P99

A
  1. Define activities
  2. Sequence activities
  3. Estimate activity resources
  4. Estimate activity durations
  5. Develop schedule
  6. Control schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the activity list & what is it an output of?

A

List representing all the schedule activities & it’s used during “ define activities”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is float?

A

Slack meaning how much an activity can sip before it starts to affect the critical path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is early start?

A
  1. Earliest an activity can start when you factor in other dependencies
  2. The date the activity will start if everything goes according to plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is late start

A

What the latest is the activity could start without delaying the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is free float?

A

How much slack there is before a delay would affect early start date of subsequent dependent activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is negative float?

A

Occurs when an activities start date occurs before a preceding activities finish date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a dummy activity?

A

An activity on the network diagram that does not have time associated with it….included only to show a relationship and exists only on arrow diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is duration compression

A

Crashing and/ or fast tracking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is crashing?

A

Applying more resources to an activity to get it down quicker, this increases costs and risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is fast tracking

A

Performing activities in parallel that would normally be done in sequence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is heuristics?

A

Rules for which no formula exists, trial and error

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are mandatory dependencies?

A

Activities that must be followed in a sequence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are discretionary dependencies?

A

Expert judgement or best practices …not hard fact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are external dependencies?

A

Dependencies relying on factors outside the organization

18
Q

What is lag?

A

The delay between being done with an activity and the one that follows it

19
Q

What is project % reserve time?

A

Add X% to entire project schedule

20
Q

What is “project lump sum” reserve time?

A

Add X months calendar schedule to end of project

21
Q

What is “activity %”

A

Add X% to each activity

22
Q

What is “activity lump sum” reserve time

A

Add X to each activity

23
Q

What is variance analysis

A

Comparing planned verses actual schedule dates

24
Q

What is sequencing activities and what is its key output (108)

A
  1. Taking the activity list and organizing it in the order they must be performed
  2. Project schedule network diagrams
25
Q

What is “estimate activity resources” how is it done (tools) and what are the key outputs?

A
  1. Estimating what resources are needed to get an activity done
  2. Expert judgement, alternative analysis, published data, and bottom up estimating
  3. Activity resource requirements and resource breakdown structure
26
What is "estimate activity durations" how do you do it and what are key outputs?....also, what goes into this?
1. Estimating how long an activity will take 2. Analogous, parametric, reserve analysis, 3 point 3. Activity duration estimates 4. Activity list, project scope statement, resource calendars, activity resources requirements
27
What is develop schedule, what are the inputs, tools, and key outputs
1. Develop the schedule 2. Inputs: activity list and attributes, project scope statement, resources calendars, activity resources & duration requirements, project network diagrams 3. Tools: critical path, resource leveling, schedule compression, apply lags and leads, what if analysis, scheduled network analysis 4. Outputs: project schedule, schedule baseline
28
What are the inputs, tools, and outputs of control schedule?
1. Inputs: project schedule, PM plan, work performance indicators 2. Tools: performance reviews, resource leveling, schedule compression, adjust leads and lags, what if analysis 3. Outputs: work performance measurements, change requests
30
What is activity duration estimates
Probable number of periods (weeks, hours, months, etc) with the probable range of results
31
What is analogous estimating?
Top down/big picture expert judgement used when there is little information. Example: last year, this took 2 years, so this year it will take 2 years