Time Flashcards

0
Q

What is the only non-planning process during the time management knowledge area?

A

Control schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

What are the 6 processes in the Time Management knowledge area? P99

A
  1. Define activities
  2. Sequence activities
  3. Estimate activity resources
  4. Estimate activity durations
  5. Develop schedule
  6. Control schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the activity list & what is it an output of?

A

List representing all the schedule activities & it’s used during “ define activities”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is float?

A

Slack meaning how much an activity can sip before it starts to affect the critical path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is early start?

A
  1. Earliest an activity can start when you factor in other dependencies
  2. The date the activity will start if everything goes according to plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is late start

A

What the latest is the activity could start without delaying the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is free float?

A

How much slack there is before a delay would affect early start date of subsequent dependent activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is negative float?

A

Occurs when an activities start date occurs before a preceding activities finish date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a dummy activity?

A

An activity on the network diagram that does not have time associated with it….included only to show a relationship and exists only on arrow diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is duration compression

A

Crashing and/ or fast tracking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is crashing?

A

Applying more resources to an activity to get it down quicker, this increases costs and risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is fast tracking

A

Performing activities in parallel that would normally be done in sequence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is heuristics?

A

Rules for which no formula exists, trial and error

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are mandatory dependencies?

A

Activities that must be followed in a sequence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are discretionary dependencies?

A

Expert judgement or best practices …not hard fact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are external dependencies?

A

Dependencies relying on factors outside the organization

18
Q

What is lag?

A

The delay between being done with an activity and the one that follows it

19
Q

What is project % reserve time?

A

Add X% to entire project schedule

20
Q

What is “project lump sum” reserve time?

A

Add X months calendar schedule to end of project

21
Q

What is “activity %”

A

Add X% to each activity

22
Q

What is “activity lump sum” reserve time

A

Add X to each activity

23
Q

What is variance analysis

A

Comparing planned verses actual schedule dates

24
Q

What is sequencing activities and what is its key output (108)

A
  1. Taking the activity list and organizing it in the order they must be performed
  2. Project schedule network diagrams
25
Q

What is “estimate activity resources” how is it done (tools) and what are the key outputs?

A
  1. Estimating what resources are needed to get an activity done
  2. Expert judgement, alternative analysis, published data, and bottom up estimating
  3. Activity resource requirements and resource breakdown structure
26
Q

What is “estimate activity durations” how do you do it and what are key outputs?….also, what goes into this?

A
  1. Estimating how long an activity will take
  2. Analogous, parametric, reserve analysis, 3 point
  3. Activity duration estimates
  4. Activity list, project scope statement, resource calendars, activity resources requirements
27
Q

What is develop schedule, what are the inputs, tools, and key outputs

A
  1. Develop the schedule
  2. Inputs: activity list and attributes, project scope statement, resources calendars, activity resources & duration requirements, project network diagrams
  3. Tools: critical path, resource leveling, schedule compression, apply lags and leads, what if analysis, scheduled network analysis
  4. Outputs: project schedule, schedule baseline
28
Q

What are the inputs, tools, and outputs of control schedule?

A
  1. Inputs: project schedule, PM plan, work performance indicators
  2. Tools: performance reviews, resource leveling, schedule compression, adjust leads and lags, what if analysis
  3. Outputs: work performance measurements, change requests
30
Q

What is activity duration estimates

A

Probable number of periods (weeks, hours, months, etc) with the probable range of results

31
Q

What is analogous estimating?

A

Top down/big picture expert judgement used when there is little information. Example: last year, this took 2 years, so this year it will take 2 years