Time Flashcards
What is the only non-planning process during the time management knowledge area?
Control schedule
What are the 6 processes in the Time Management knowledge area? P99
- Define activities
- Sequence activities
- Estimate activity resources
- Estimate activity durations
- Develop schedule
- Control schedule
What is the activity list & what is it an output of?
List representing all the schedule activities & it’s used during “ define activities”
What is float?
Slack meaning how much an activity can sip before it starts to affect the critical path.
What is early start?
- Earliest an activity can start when you factor in other dependencies
- The date the activity will start if everything goes according to plan
What is late start
What the latest is the activity could start without delaying the project
What is free float?
How much slack there is before a delay would affect early start date of subsequent dependent activities
What is negative float?
Occurs when an activities start date occurs before a preceding activities finish date
What is a dummy activity?
An activity on the network diagram that does not have time associated with it….included only to show a relationship and exists only on arrow diagrams
What is duration compression
Crashing and/ or fast tracking
What is crashing?
Applying more resources to an activity to get it down quicker, this increases costs and risks
What is fast tracking
Performing activities in parallel that would normally be done in sequence
What is heuristics?
Rules for which no formula exists, trial and error
What are mandatory dependencies?
Activities that must be followed in a sequence
What are discretionary dependencies?
Expert judgement or best practices …not hard fact
What are external dependencies?
Dependencies relying on factors outside the organization
What is lag?
The delay between being done with an activity and the one that follows it
What is project % reserve time?
Add X% to entire project schedule
What is “project lump sum” reserve time?
Add X months calendar schedule to end of project
What is “activity %”
Add X% to each activity
What is “activity lump sum” reserve time
Add X to each activity
What is variance analysis
Comparing planned verses actual schedule dates
What is sequencing activities and what is its key output (108)
- Taking the activity list and organizing it in the order they must be performed
- Project schedule network diagrams
What is “estimate activity resources” how is it done (tools) and what are the key outputs?
- Estimating what resources are needed to get an activity done
- Expert judgement, alternative analysis, published data, and bottom up estimating
- Activity resource requirements and resource breakdown structure