The Raise Flashcards
1
Q
Elevation of starter blocks
A
6953
2
Q
Elevation after S1 phase
A
7265
3
Q
Number of lifts in S1
A
78
4
Q
Amount of RCC placed in S1
A
299,029 CY
5
Q
Amount of CVC placed in S1
A
14,033 cy
6
Q
Amount of form work placed in S1
A
679,488 sf
7
Q
When will KBJV be using the telebelt
A
May 1-May 27
8
Q
What time will RCC placements happen during the first month?
A
Night only