What is a result of an AMSAC actuation?
A. Trip of both main feed water pumps.
B. Auxiliary feed water conservation signal.
C. Auxiliary feed water feed reg valves go to their throttled position.
D.
B. Auxiliary feed water conservation signal.
What will cause an SI
A. 500 psig.
B. 100 psid.
C. 500 psid.
D. 1 psid.
A. 500 psig.
List 10 loads on the CCW misc. header.
Post accident sample heat exchangers Recip. charging pump SFP HX Waste gas compressor seal water HX. RCP Seal water HX Letdown HX Excess letdown HX Reactor support coolers Main steam penetration coolers BAE Evaporator condenser BAE Distillate coolers BAE Vent condenser RCP Thermal barrier RCP Motor upper bearing oil cooler RCP Motor Lower bearing oil cooler CEQ fan motor cooler
What does a # sign after a step number in a EOP mean?
It is a continuous action step
What inputs into rod control
T-ave and T-ref
What must you have in order to close the first MG set out put breaker?
Both MG set out put breakers must be racked in and open.
With a phase “B” and no other casualties what affect on NESW system?
No affect on NESW pumps already running phase “A”
What two things does the reactor protection system protect against?
Over pressure and departure from nucleate boiling.
What happens to CCW on a phase B.
RCP loads isolate
Delayed neutrons have less kinetic energy than?
Prompt neutrons
What is the moderator used for?
To slow down the neutrons, scattering
When can you move control rods?
When both RX trip breakers are racked.
What is the normal power supply to the control and power cabinets.
260ac from the output of the MG sets through a step down transformer to 120vac
If the south NESW pump is In service and you loose bus 21B what will happen?
The north NESW pump would start on low header pressure.
After which event are neutrons added?
Fast fission.