Balancing Authority A is currently reading a system frequency of 60.06Hz. Its Net Actual Interchange is +100MW and its Net Scheduled Interchange is +160MW. If Balancing Authority ‘s frequency bias setting is -100MW/0.1Hz, Balancing Authority A’s AGC should be pulsing its generators to ______.
Remain at current MW output level
The initial response to a frequency deviation is due to which of the following?
- Load/frequency response
- AGC
- Governor action
- Interchange schedules
1&3
Interconnection frequency is 59.80Hz. Your ACE is a large negative value and your AGC is pulsing your units down. What should you do?
Suspend AGC and investigate
To conform to the CPS requirements, a Balancing Authority must have a _____.
CPS greater than or equal to 100%
Balancing Authority A is currently reading a system frequency of 59.98Hz. Its Net Actual Interchange is +100MW and its Net Scheduled Interchange is +100MW. If Balancing Authority A’s frequency bias setting is 100MW/0.1Hz, what is ACE?
-20
A Balancing Authority is performing Overlap Regulation Service for another Balancing Authority. What will apply?
The Balancing Authority’s Frequency Bias Setting shall be modified to reflect the combined Frequency Bias Setting of both Balancing Areas.
A CPS1 violation is an indication that:
A BA’s ACE is hindering frequency
You are ready to restore power to a generator facility. Which of the following Transmission lines would be the best choice best choice to energize the facility?
- 25 mile, overhead transmission line
- 10 mile, overhead transmission line
- 25 mile, underground transmission cable
- 10 mile, underground transmission cable
10 mile, overhead transmission line
Who must have plans for operator controlled manual load shedding to respond to real-time emergencies?
Transmission Operators and Balancing Authorities
During a system emergency, the System Operator can direct other Transmission Operators and Balancing Authorities to violate which limit?
None. Equipment parameters should be maintained within their established limits
A severe lightning storm has hit your transmission system. Two 345kV lines have been damaged and unable to be re-energized. Two large generators of 500MW and 700MW have tripped offline. No additional generators are available to bring online. The parallel 230kV and 138kV lines are loaded at their emergency limits. What should a system operator do?
Shed load
Once a Balancing Authority inform the Reliability Coordinator of future or current Capacity and Energy Emergencies, it is the responsibility of the ____ to mitigate the emergency condition.
Reliability Coordinator and Balancing Authority
If a Balancing Authority is unable to purchase capacity or energy to meet its demand and reserve requirements on a day-ahead basis, which entity or entities, is it expected to notify?
Its Reliability Coordinator and Balancing Authorities
If a transmission Operator or Balancing Authority is unable to restore Real and/or Reactive Power Balance, they must request emergency assistance from the Reliability Coordinator. If Operating Reserves are not available, corrective action need to include:
implement manual load shedding
If a Balancing Authority or Reserve Sharing Group is experiencing conditions where all available resources are committed to meet firm load, firm transactions, and reserve commitments, what does the deficient entity need to request their Reliability Coordinator to issue?
Energy Emergency Alert Level 1