Test 1 Flashcards
What is a project
A project consists of a series of activities having the following characteristics:
- The project and end date
- It has well-defined objectives (what are we trying to achieve)
- It achieves a specific product or result
- It is unique and non-repetitive (temporary)
- Cost, time schedules and resources are consumed (resources, labour equipment, material)
Project vs Operation
Operation are ongoing and repetitive (mass production)
Projects are unique (single time)
Ultimate goal of a construction project
To complete the project successfully (profitably) within the project parameters
1. Time
2. Money
3. Quality
4 aspects of a project
- Scope of work; What is included? (What do you want)
- Time: Schedule, Start/Finish, Milestone dates, etc.
- Quality: Characteristics of products, testing and inspections according to specifications
- Cost: budget, Cost control, Payments, Cash flow
If you change one aspect of a project? With example
It affects another one. Example: Melamine counters to granite = SCOPE, new counters will take longer time = TIME, QUALITY is different therefore COST changes aswell.
In the PMI, Scope, Time, Cost and Quality are referred to as ? Other ? include
Areas of knowledge
-Integration management
-Human resources
-Communications
-Risk
-Procurement
Examples of a project
-Developing software
-Deigning transportation vehicle
-Construction of a new building or bridge
4 main phases in a project
- Feasibility
(Project formulation, feasibility studies, strategy design and approval)
-Planning and design
(Base design, cost and schedule, contract terms and conditions, detailed planning)
-Construction
(Manufacturing, delivery, civil works, installation, testing)
-Turnover and Close-Out
(Final testing, maintenance)
What are the intermediary steps between phases
1 to 2: Project GO decision
2 to 3: Major contracts let
3 to 4: Installation substantially complete
4: Full operations
Feasibility
A study to determine if a project is viable: Market study, population growth, incomes, environmental impact, preliminary budget, schedule
Planning and design
The project is designed, costs and schedule are determined. Contracts are given out: Preparation of Bid documents
Construction
Manufacturing and delivering the product, installation and testing, detailed schedule
Turnover and Close-Out
-Final testing and approvals
-Correction of deficiencies
-Contract and document close-out
-Turn-over of facilities to owner: As builts, guarantees
Planning
Determine the order in which the activities are to take place.
Determine what is to be done. Make a WBS. Make a list of activities. Determine durations for said activities.
Concurrent activities
Activities that can occur at the same time (do not depend on each other)