1
Q

As an agile project manager, what is your goal or objective when presented with issues or problems?

A

Find them early and fix them as early as possible. The further you get into a project, the more costly issues and problems can be.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The team is presented with a problem? As the agile project manager, do you solve the problem, does the product manager, or should you let the team solve the problem?

A

Allow the team to solve the problem. The team usually produces the best practical solutions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What visual tool provides a way to display the root cause analysis of problems by helping the team to identify way a particular process failed during iteration? Done during the generate insight step of a retrospective to show reasons why something failed.

A

Fishbone diagram analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Can you list the 5 steps of the retrospective process?

A
  1. Set the stage
  2. Gather data
  3. Generate insights
  4. Decide what to do
  5. Close the retrospective
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the process of adding more detail as greater amounts of information and more accurate estimates become available over time?

A

Progressive elaboration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the outcome of the Spring planning meeting?

A

The sprint backlog which will outline work to be done in the next Sprint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the first step an agile project manager should take when leading an agile project team?

A

Learn the team members needs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When do customers give feedback on a completed increment of the product?

A

Spring review meeting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the longest an iterations should last?

A

Four weeks. Iterations should be no more than this.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When does the team get feedback on the work that was completed during the iteration?

A

Iteration review meeting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a visual representation of the flow of information or materials required to product a product or service? Helps the team improve processes and remove waste.

A

Value stream mapping

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What refers to adapting your implementation of agile to better fit your project environment? This isn’t recommended for teams new to agile.

A

Process tailoring

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Whats a visual depiction of the product releases and the main components that will be included in each release? It’s a communication tool.

A

Product roadmap

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a high level planning tool that is used to map out project priorities early in the planning process? Matrix of features and user stories.

A

Story map

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

First documents product for a project that describes project’s goal, purpose, composition, and approach. Authorization from sponsor for the project to proceed. Includes acceptance criteria.

A

Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Measures the frequency of defects found. Can be used to understand how well a process is working. D

A

Defect rates

17
Q

A graphical representation of the work completed toward the release of a product is?

A

Burnup chart

18
Q

A graphical representation of the work remaining versus the time left is?

A

Burndown chart

19
Q

Valuable tools for tracking and forecasting the delivery value. They’re graphs that depict the features that are in-progress, remaining, and completed over time.

A

Cumulative flow diagrams

20
Q

What is one of the key activities performed at release planning meetings?

A

Assigning user stories to sprints

21
Q

What is a product demonstration method used to show the functionality of the product and gain feedback?

A

Product Simulation