As an agile project manager, what is your goal or objective when presented with issues or problems?
Find them early and fix them as early as possible. The further you get into a project, the more costly issues and problems can be.
The team is presented with a problem? As the agile project manager, do you solve the problem, does the product manager, or should you let the team solve the problem?
Allow the team to solve the problem. The team usually produces the best practical solutions.
What visual tool provides a way to display the root cause analysis of problems by helping the team to identify way a particular process failed during iteration? Done during the generate insight step of a retrospective to show reasons why something failed.
Fishbone diagram analysis
Can you list the 5 steps of the retrospective process?
- Set the stage
- Gather data
- Generate insights
- Decide what to do
- Close the retrospective
What is the process of adding more detail as greater amounts of information and more accurate estimates become available over time?
Progressive elaboration
What is the outcome of the Spring planning meeting?
The sprint backlog which will outline work to be done in the next Sprint
What is the first step an agile project manager should take when leading an agile project team?
Learn the team members needs
When do customers give feedback on a completed increment of the product?
Spring review meeting
What is the longest an iterations should last?
Four weeks. Iterations should be no more than this.
When does the team get feedback on the work that was completed during the iteration?
Iteration review meeting
What is a visual representation of the flow of information or materials required to product a product or service? Helps the team improve processes and remove waste.
Value stream mapping
What refers to adapting your implementation of agile to better fit your project environment? This isn’t recommended for teams new to agile.
Process tailoring
Whats a visual depiction of the product releases and the main components that will be included in each release? It’s a communication tool.
Product roadmap
What is a high level planning tool that is used to map out project priorities early in the planning process? Matrix of features and user stories.
Story map
First documents product for a project that describes project’s goal, purpose, composition, and approach. Authorization from sponsor for the project to proceed. Includes acceptance criteria.
Charter