Floating should be followed by trowling when?
A smooth hard, dense surface is desired
Methods for placing concrete under water include?
Tremie
Plastic shrinkage cracks occur when?
Water evaporates from the surface faster than it appears on the surface during the bleeding process
Chemical process by which cement reacts with water is called?
Hydration
Slump is used to measure the consistency of?
Concrete
Type 1 cement is
A general purpose cement suitable for all uses where the special properties of others are not required such as sulfate attack from soil or water or temperature rise due to heat generated by hydration
Type V cement is used principally where?
Where soils or ground waters have a high sulfate content
A concrete slab is being placed with a vibratory screed. What is the maximum slump according to UBC?
A) 1’’
B) 2’’
C) 4’’
D) 3’’
D) 3’’
According to OSHA air can be used for cleaning purposes if reduced to less than?
OSHA 1926.302
30 PSI
What does not affect pressure on a concrete form?
Air Entrainment
What are ganged forms?
Forms that are placed by a crane
What is the minimum distance from rebar to the ground in concrete wall?
1 1/2 inches
Which is not an approved fastener for tilt up walls?
Floor strip and dowel
According to OSHA portable tanks used for storage of flammable liquids shall be placed at least how far from any building?
A) 25’
B) 10’
C) 15’
D) 20’
D) 20’
According to OSHA a scaffold plank less than 10’ in length may extend over and support a maximum distance of____.
A) 12’
B) 10’
C) 13’
D) 11’
A) 12’