Tendering Flashcards
- What is tendering?
- Tendering is a method of obtaining the resources necessary to carry out the required work
- What are the main tendering options?
a) Open tendering
b) Selective tendering – single or two stage
c) Nomination / negotiation
d) Serial
e) Joint ventures
- What is open tendering?
- Indiscriminate request for tenders
- Advert placed in local paper/technical press inviting contractors to apply for tender docs
- Gives characteristics of the work
- Deposit usually required to discourage frivolous applications
- What are the advantages of open tendering?
a) No charge of favouritism
b) Gives opportunities for capable firms you might not have put on a list
c) Should secure max benefit from competition
- What are the disadvantages of open tendering?
a) Danger lowest tender is inexperienced or has made lots of errors
b) No guarantee the lowest is capable or financially stable
c) Total cost of tendering is increased
- What is selective tendering?
- Restricts the number of tenderers by pre-selecting a limited number of contractors to tender for the work
- What are the two types of selective tendering?
- Single stage
- Two stage
- What is single stage tendering? And what should be provided by the Contractor during pre-selection (PQQ)?
- A structured process of receiving competitive tenders from a number of pre selected capable contractors, who provide a lump sum for the works
- Contractors pre-selected on say NJCC basis:
1. Established skill
2. Integrity
3. Responsibility
4. Proven competence and character
5. Size of work - No more than 6 on list. If pre-selection is done beforehand then tenders can be selected on price alone.
- Good contractors have the following: Recent experience, necessary skills, good management and organisational structure, spare capacity, good financial standing.
- What are the advantages of single stage tendering?
- Ensures only capable and approved firms submit tenders
- Tends to reduce the aggregate cost of tendering
- Client gets a lump sum for the whole works
What is two stage tendering?
- Separates the processes involved with selecting a contractor from the processes for determining the price for the works
- Used when it is desired to obtain the benefits of competition and have the advantage of bringing a contractor into the planning of the project and gain an earlier commencement
- What is the purpose of the first stage (two stage)
- To select a suitable contractor by means of limited competition
- What is the purpose of the second stage (two stage)?
A negotiation process with the selected contractor on the basis of the first stage
- What do tenderers return as part of the first stage?
a) Detailed build up of prices for the preliminaries items
b) Percentage additions for profit and overheads
c) A construction programme
d) Proposed sub letting of the works
- Are there any precautions you should take before entering the 2nd stage process?
- Define procedure for either party to withdraw should 2nd stage negotiations prove abortive, what payments become due.
- Are there any precautions you should take before entering the 2nd stage process?
- Define procedure for either party to withdraw should 2nd stage negotiations prove abortive, what payments become due.
- What are the advantages of two stage tendering?
a) Early involvement of the contractor
b) Encourages collaborative working
c) Potential for earlier start on site
d) Greater client involvement in selecting the supply chain
e) Contractor can help identify and manage risk
- What are the disadvantages of two stage tendering?
a) Cost certainty may not be achieved before construction starts
b) Additional pre-construction fees for the contractor
c) Contractor could take advantage of second stage negotiation – increase costs
d) Potential for parties to not agree contract sum – risk – cost of retendering
- Why should you use 2 stage tendering?
- Building is complex
- Magnitude of work is unknown at time of contractor selection
- Early completion is required
- Design team would like to make use of contractors expertise on buildability issues.
- What is negotiation / nomination?
- Where the client has a preference for a particular firm
- When might negotiation/nominaion be used?
- Possibly when the contractor has done satisfactory work for him before
- How does negotiation/nomination work?
- There is no competition – likely to lead to a higher price
- BUT client may think it is worth it for a quicker or better quality job
- The contract sum is arrived at by a process of negotiation
- One party usually prices a schedule of rates / bill which is used as a basis
- What is serial tendering
- Effectively strategic partnering
- Contractors are asked to bid for a project on the basis that if they build this one satisfactorily, others of a similar type will follow and the same bill rates will be used
- What is a framework agreement?
- A list of contractors selected by the client after a formal tendering procedure to work over a long period of time
- The contractor may have to wait his turn for a contract or tender repeatedly with the same group of contractors
- What is a joint venture?
- Used on large complex projects when 2 or more companies take on a joint and several liability for design and execution of the project.
- Would normally be backed up with PCG, Performance Bonds.
- What is OJEU?
- Official Journal of the European Union
- What is OJEU for?
- Public sector tendering
- All contracts from the public sector above a certain financial threshold have to be advertised on OJEU
- What could selecting the wrong contractor lead to?
a) A bad client / contractor relationship
b) A dissatisfied client
c) An insolvent contractor
- What is NJCC?
- National Joint Consultative Council for Building
- They published highly regarded codes of procedures relating to tendering practices
- Disbanded and taken over by the Construction Industry Board (CIB)
- BUT many clients still adhere to the original codes and JCT’s practice note includes a substantial amount of their material
- How would you put together a set of tender documents?
- In accordance with JCT practice note 6. Include:
i. ITT (Invitation to tender letter)
ii. Instruction to tenderers: Date and time for return, to whom, site visits, programme, visit to architect to see drawings, errors, discrepancies, NJCC alternative 1,2. Scoring matrix (quality/ price), confirmation of receipt
iii. Conditions of proposed contract
iv. Prelims, Pricing doc (SOR, BOQ)
v. Specification
vi. Drawings
vii. ERs
viii. CPs
ix. Pre-construction H&S information
x. Form of tender
xi. Submission of bona fide tender
xii. Return envelope
- What information would the instructions to tenders contain?
a) Date for return
b) Address to return to
c) Site visit details
d) Programme length
e) Confirmation of receipt of documents
f) How tender should be submitted
- What is the form of tender?
- A pre printed formal statement in which the tenderer fills in the blank spaces
- He provides his name, address and the sum of money for which he offers to carry out the works
- What are the employer’s requirements?
- Sets out the client’s requirements e.g. function, size, accommodation, quality
- Level of detail depends on how much design has been done prior to tender
- Normally includes current state of planning permission
- Should detail the level of design, structure and spec info to be provided by the tenderers