Tender Returns and Analysis Flashcards

1
Q

What is a form of tender?

A

A FoT is formal acknowledgement that the tenderer understands and accepts the terms and conditions of the tender documents and any requirements that are stipulated. The contractor usually signs and returns it within their prepared tender submission.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What information is usually included within a Form of Tender?

A

Tender Sum
The date in which the price remains valid
Construction period (programme)
Confirmation of the tender being genuine and bona fide
Tenderer details and signature
Acceptance of Ts&Cs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Apart from contractors tender sum, what else might be requested that the contractor should provide?

A

Relevant experience
Project team
Programme
H&S information
Logistics plans
Social Value policy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Once tenders have been submitted, what should be examined for compliance with the invitation to tender and tender instructions?

A

Arithmatical errors
Pricng errors (elements/items not priced)
Pricing methods (e.g. evidence of front loading)
Compare contractors proposals (CPs) to the ERs (D&B only)
Check that form of tender is complete and signed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the process for opening tenders

A

A tender opening form should be used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is front loading

A

Suppliers may front-load costs (or prices in bids) in order to maximise their revenue early in a project by assigning overstated values to the preliminary elements of the work. For example, a contractor might front-load costs for preliminary construction work such as services diversions, demolition, setting out, groundworks, piling, and so on.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What happens if a tender is submitted late

A

Public Sector project - The documents should not be accepted.
Private Sector project - The matter should be discussed with the client to understand if they would like to accept, however the safest option is not to consider (because of fraud, collusion, bid rigging etc).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the danger of accepting a very low tender?

A

Contractor may be trying to ‘buy’ the project with a view to recovering costs with variations post contract.
Could indicate contractors poor financial situation/cashflow position and is eager to win work at any cost.
Areas of the project may not be priced accurately, creating potential for an adversarial relationship with client team post contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How do you deal with qualifications within a tender submission?

A

Procedures associated with qualifications should be outlined in the tender instructions.
If the qualifications are unauthorised, it might invalidate the tender (leading to DQ).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How would you deal with errors identified within the tender

A

As per JCT tendering practice note:

Alternative 1 - Tenderer should be given the details of the errors and afforded to opportunity to either confirm or withdraw from the tender
Alternative 2 - Tenderer should be given the opportunity to confirm their offer or amend it to correct genuine errors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What would you do if you believe the contractor submitting the tender was in financial difficulty?

A

As part of the evaluation process (normally in the PQQ), a financial check would be done on the contractor.
Consider a performance bond.
Consider a PCG
Raise your concern with the client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

On what grounds would you advise the client to re-tender the project?

A

Not enough tenders returned.
The tendering procedure is comprimised somehow
If the required cost level is not achieved and its believe by re-tendering the cost level could be achieved
Design changes significantly changed the overall design that was originally tendered

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How would you deal with front loading

A

Normally not a pricing error but a pricing method.
Request that the contractor remove the fornt loading form their tender, if they refuse, disqualify them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is included within a tender opening form

A

The tender price
Proposed programme in weeks
Key comments/exclusions
Alternative tender offers
Confirmation that all docs have been submitted or not

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do you review tenders?

A

Tender opening form
Check for errors and conflicts
Raise tender queries and conflicts in information
Normalise the tenders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are ways of normalising a tender

A

Use an average of the submitted costs
Use the highest price from the tender returns
Use the cost plan allowance for that particular item/element

17
Q

What could selecting the wrong contractor lead to?

A

A bad client / contractor relationship

b) A dissatisfied client
c) An insolvent contractor

18
Q

What are the employers requirements?

A

They provide a description of the client’s requirements, including; the specification for the building, the scope of services required from the contractor and an allocation of risk for unknown items.

19
Q

What are the contractors proposals?

A

The contractors response to the ERs

They are the key document for the client to consider at the tender review
Often includes plans, elevations, sections and typical details
Layout drawings and specification for materials and workmanship

20
Q

Why should you as a surveyor examine tenders?

A

Check tenderer has included everything, if not to ascertain whether they are still the lowest. - Component parts of tender will be used subsequently e.g. valuing variations- Errors in SOR, BOQ need to be identified and dealt with.

21
Q

What was the process of your tender analysis for WHBG?

A

Error check
PTQs
Normalisation
Scoring
Recommendation

22
Q

What would you do if a client asked you to change a tender score?

A

I would request the basis of this request as my recommendation should be a true reflection on my evaluation of the tender submissions. If I do not feel the request is justifiable I would refer the client to my TRR

23
Q

What if your client isn’t happy with tender recommendation?

A

Still recommend but explain why others weren’t selected

24
Q

What was done if there was any issues with the CPs?

A

ER’s should take precedence but any discrepency should be raised and dealt with in the PTQs

25
Q

What level of design risk would you expect the contractor to include for?

A

3-5% is what I have seen on some of my projects