Technical competencies Flashcards
• What are the differences between JCT and NEC Contracts?
o Price
JCT is a fixed price lump sum
NEC has lump sum, target price, cost reimbursement, managing contract
o Provisional sums
JCT allows
NEC doesn’t
o Cost scrutiny
JCT allows cost scrutiny via contract sum analysis/tender negotiations
NEC open book procedure. Defined cost and disallowed cost.
o Ground risk
JCT – with contractor
NEC – unforeseeable costs reimburst
o Programme
JCT – only requires master programme
NEC – contractor to supply programme at regular intervals.
o Extention of time/ loss and expense
JCT – relevant event/matter
NEC – compensation event, time and money considered together
o Design risk
JCT – defines specific duties dependant on form of contract
NEC – contractor simply designs sections stated in Works Information
o Employers Requirements/ Works Information
• NEC – What are defined costs and disallowed costs
o Defined costs - Cost actually incurred by contractor
o Disallowed costs – determined by PM to be not justified, should not have been paid to subies, incurred by not following works information/early warning.
• What are the NEC suit of contracts?
o Engineering & construction contract
o Engineering & construction sub contract
o Engineering & construction short contract
o Professional services contract
o Professional services sub contract
o Term service contract
o Design, build & operate contract
o Framework contract
o Supply contract
o Alliance contract
o Dispute resolution service contract
• Can you name some NEC ECC standard contract forms?
o Option A, Priced contract w/ Activity Schedule
o - Option B, Priced contract w/ BoQ
o - Option C, Target contract w/ Activity Schedule
o - Option D, Target contract w/ BoQ
o - Option E, Cost reimbursable
o - Option F, Management contract
• How does NEC manage change, risk and programme
o Requires an early warning notice as soon as pm/contractor becomes aware of issue to programme, cost, quality
o Programme has to be revised at defined intervals throughout the project
o Compensation event – contractor claims for time and cost, must be within 8 weeks of becoming aware.
• What are the advantages/disadvantages of NEC?
o Advantages: Simpler language Emphasis on cohesion Shares risk Active programming o Disadvantages: Administration heavy Needs time to understand
• What is necessary to form a contract?
o Offer o Acceptance (or counter offer) o Consideration o Intention (to be legally bound) o Capacity (to make agreement) (e.g. power of attorney on behalf of a company)
• How is contract executed?
o Under hand, signed by both parties, 6 year limitation period. Means that a party must bring about any claim for breach of contract within 6 years of the breach taking place. Any later and the claim will be time-barred.
o Under Seal (as a deed), signed and witnessed, 12 year limitation period. Valuable consideration not required,
• What are common contract documents?
o The Contract (with any amendments) o Preliminaries o Contract sum analysis/Pricing Schedule o Drawings o Specification o Planning conditions/agreements o Contractors Proposals
• Why use standard forms of contract?
o They are cheaper than getting a bespoke contract drawn up
o - Offer a level of familiarity between the parties
o - Tried and tested contracts in court, therefore you should be able to predict the outcome in the courts.
• What should be considered when determining the type of procurement to use?
o Need to consider key criteria for the client
Are they wanting to share risk or allocate it to one party
Do they need cost certainty
Need programme certainty
o Is there time to fully design
o Is there a focus on aesthetics and building performance
o How complex is the project
o What types of contract do the client and market have experience of using
o Should be made on the basis of characteristics of the project, the client and their requirements.
• What are the main forms of procurement?
Traditional
Design and Build
Construction Management
Management contracting
• What standard forms of contract do you know that are offered by JCT?
o Standard Building Contract with/without quantities
o Intermediate building contract 2011/2016
o - Minor works Building contract 2011/2016
o - Major Projects building contract 2011/2016
o - Design and build contract 2011/2016
o - Management Building contract 2011/2016
o - Construction management contract 2011/2016
o - Prime cost building contract 2011/2016
Features of traditional contract?
Suitable for complex projects High quality Accuracy design possible but needs to be good. Time and cost variable Risks high if poor design
Features of Design and Build contract
Suitable for simple projects
Time and cost certainty
Dependant on strength of employers requirements
High risk if client make changes
Features of Construction Management contract
Needs experienced client
Fast track projects
Often complex buildings with high quality
Brief and ERs developed during the project life
Cost certainty not clear
Contractor and design team appointed at the same time
Contractor contracted to client as is the construction manager
Risks transfer to CM
Features of management contract
Needs experienced client
Fast track projects
Often complex buildings with high quality
Brief and ERs developed during the project life
Cost certainty not clear
Contractor and design team appointed at the same time
Management contractor contracted to client who contracts with other contractors for works packages.
Risks transfer to contractor
What are Belbin’s 9 team roles?
Plant: creative, solves difficult problems. ignores detail.
Resource Investigator: explores options, develops opportunities. Over optimistic
Co-ordinator: Good chairperson, delegates well. Can be seen as manipulative, delegates personnel work.
Shaper: Challenging, thrives on pressure. Can hurt others feelings.
Monitor Evaluator: Sober, strategic, sees options. Lacks drive and ability to inspire others.
Teamworker: Co-operative, listens, builds. Indecisive in crunch
Implementer: Disciplined, reliable, turns ideas into actions. Inflexible.
Completer Finisher: Painstaking, corrects errors. Worries.
Specialist: Provides knowledge and skills in rare supply. Dwells on technicalities, overlooks big picture.
• What is meant by solo and team leaders?
o Solo leader – sole point of management, has ardent followers, takes responsibility for all elements of work. Decisions can be made quickly. E.g sub-contractor, known scope of work.
o Team Leader – Limits their role and declines to rule absolutely, seeks talent to overcome their shortcomings. Delegates and does not interfere. E.g project manager on complex project.
• What are the types of insurance used in construction contracts?
o Employers Liability - protects against liabilities to employers for injuries or illness.
o Public Liability - protects against liabilities for injury to third parties (non-employees) or their property.
o Professional Indemnity - against claims for loss or damages arising from professional negligence or negligent advice.
o Contractors All Risk insurance - physical damage to works and site materials that you were contracted to undertake.
• Define risk in terms of a project?
o Uncertain event or circumstance that if it occurs affects the project outcomes, programme, finance.
o Include threats and opportunities
o Different to issues which are current events actively impacting project
• Define risk analysis?
o The process to identify and quantify risks in terms of probability and impact.
• What is risk management?
o Risk management is a proactive exercise designed to:
Identify risks
Assess risks
Manage risks
• What is the risk management process?
o 5 steps:
- Identify risks
- Assess the probability and impact
- Respond – mitigate, ignore, transfer
- Record – monitor risk responses
- Feedback – record outcome for future projects
• What are the 5 categories of risk?
- Political and business – becomes public knowledge and effects ongoing business
- Benefit Risk – project fails to deliver performance benefit expected e.g. planning reduce building size = loss of rent
- Consequential risk – occurs due to other risks
- Project risks – affect time, cost, quality
- Programme risks – impact on the overall programme