Tech Specs Flashcards

1
Q

8.1.1 Boration Sys Operating (Shutdown)

A

M 1-3. Two paths. One Boric acid tank, pump, and charging pump. The other a CCP via RWST to RCS. Can’t be same path.

M4. Need 1 OR Other. Stop Core Alts if NOT met. Enter 8.0.3

M 5-6. Need 1 OR other flow path. IF NEITHER, IMMED suspend core alts and pos reactivity additions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Basis for Liquid and Gas Storage TRM

A

Limit exposure due to liquid tank failure to less than 10CFR20 limits.

Gas Tank Based on failure which limits exposure to less than .5 REM at site boundary.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

TRM Refueling Requirements

A

Direct Comms Between CR and Refueling at ALL Times. RNO Immed Suspend core alts.

Shall be Sub Crit for at least 120 hours. (M3)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly