Q

What is the LCO and Applicability for Technical Specification 3.1.3, Control Rod Operability?

A

LCO: Each Control Rod SHALL be OPERABLE.

Applicability: MODES 1 and 2.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the one hour, or less, actions associated with Technical Specification 3.1.3, Control Rod Operability?

A

Condition: One Withdrawn Control Rod Stuck.

Required Action: Verify stuck Control Rod separation criteria are met.

Completion Time: Immediately

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the LCO and Applicability for Technical Specification 3.1.4, Control Rod Scram Times?

A

LCO:
a. No more than 13 OPERABLE control rods shall be “slow” in accordance with Table 3.1.4-1; AND

b. No OPERABLE Control Rod that is “slow” shall occupy a location adjacent to another OPERABLE Control Rod that is “slow” or a withdrawn Control Rod that is stuck.

Applicability: MODES 1 and 2.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the one hour, or less, actions associated with Technical Specification 3.1.4, Control Rod Scram Times?

A

NONE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the LCO and Applicability for Technical Specification 3.1.5, Control Rod Scram Accumulators?

A

LCO: Each Control Rod Scram Accumulator shall be OPERABLE.

Applicability: MODES 1 and 2.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the one hour, or less, actions associated with Technical Specification 3.1.5, Control Rod Scram Accumulators?

A

Condition: Two or more control rod scram accumulators INOPERABLE with Reactor Steam Dome pressure greater than or equal to 600 psig.

Required Action(B.1): Restore charging water header pressure to greater than or equal to 1520 psig.

Completion Time(B.1): 20 minutes from discovery of Condition B concurrent with charging water header pressure < 1520 psig.

                       AND 

Required Action: (NOTE: Only applicable if the associated control rod scram time was within the limits of Table 3.1.4-1 during the last scram time Surveillance.)
–Declare the associated control rod scram time “slow.”

Completion Time: 1 hour

                        OR

Required Action: Declare the associated control rod INOPERABLE.

Completion Time: 1 hour

Condition: One or more control rod scram accumulators INOPERABLE with Reactor Steam Dome pressure < 600 psig.

Required Action(C.1): Verify all control rods associated with INOPERABLE accumulators are fully inserted.

Completion Time(C.1): Immediately upon discovery of charging water header pressure < 1520 psig.

                        AND

Required Action: Declare the associated control rod INOPERABLE.

Completion Time: 1 hour

Condition: Required action and associated completion time of required action B.1 or C.1 not met.

Required Action: (NOTE: Not applicable if all INOPERABLE control rod scram accumulators are associated with fully inserted control rods.)
–Place the reactor mode switch in the SHUTDOWN position.

Completion Time: Immediately

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the LCO and Applicability for Technical Specification 3.1.8, Scram Discharge Volume(SDV) Vent and Drain Valves?

A

LCO: Each SDV vent and drain valve shall be OPERABLE.

Applicability: MODES 1 and 2.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the one hour, or less, actions associated with Technical Specification 3.1.8, Scram Discharge Volume(SDV) Vent and Drain Valves?

A

NONE