Explain which aspects of the project can be tailored…

A
  • Processes may be combined or adapted
  • Themes can be applied using techniques that are appropriate to the project
  • Roles may be combined or split, provided that accountability is maintained and there are no conflicts of interest
  • Management products may be combined or split into any number of documents or data sources
  • Terminology may be changed to suit other standards or policies, provided it’s applied consistently
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who is responsible for tailoring a project?

A

The project manager is responsible for identifying and documenting the level of tailoring for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How are tailoring decisions documented?

A

Tailoring affects how a project is managed and so it is documented as part of a the PID, which is reviews by the appropriate stakeholders and approved by the project board.