Tailoring & Adopting Prince2 Flashcards
1
Q
Explain which aspects of the project can be tailored…
A
- Processes may be combined or adapted
- Themes can be applied using techniques that are appropriate to the project
- Roles may be combined or split, provided that accountability is maintained and there are no conflicts of interest
- Management products may be combined or split into any number of documents or data sources
- Terminology may be changed to suit other standards or policies, provided it’s applied consistently
2
Q
Who is responsible for tailoring a project?
A
The project manager is responsible for identifying and documenting the level of tailoring for the project.
3
Q
How are tailoring decisions documented?
A
Tailoring affects how a project is managed and so it is documented as part of a the PID, which is reviews by the appropriate stakeholders and approved by the project board.