SWP Flashcards

1
Q

Where do you find the requirements for issuing SWP?

A

Life critical standards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Identify activities that do not require a SWP?

A

Activities specified on the TXO exempt job list.

Work on non Dow Property

Emergency Response

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Identify activities that require a Safe Work Permit if you are not an Authorized Procedure User

A
  1. CSE
  2. Criticel Crane Lifts
  3. Hot LEO
  4. Electrical Work
  5. High Energy Hot Work in a flammable area
    6.6. Excavation
  6. Hot Tap
  7. Hydro blasting
  8. Pressure Washing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Identify activities that always require a Safe Work Permit.

A

Identify activities that always require a Safe Work Permit.
1. CSE
2. Critical lifts
3. Excavation
4. Rope Access
5. High Energy in a flamble Area
6. Hot LEO
7. Hydro-blasting
8. When requested

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is required for exempt activities in process areas?

A

Approval from SWP Issuer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Identify 3 exempt job communication expectations.

A
  1. Job Scope
  2. Where work is happening
  3. Who is working
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Describe what the SWP “View Entire Standard” is and its use. Demonstrate how to navigate. Note that s “View Entire Standard” view is available for all Life Critical Standards. Print the SWP Standard d attach to the IPT package.

A

Link to view the entire standard

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Where do you find exempt jobs / work authorization information?

A

Permit Room
EDMS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who is required to authorize individuals to issue Safe Work Permit for the Facility?

A

Production Leader or Ops leader

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Who is required to authorize individuals to be an Authorized Operating Procedure User for the Facility

A

Production Leader

Ops Leader

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Can an Authorized SWP Issuer issue a SWP to himself or herself?

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Identify things the SWP must include.

A
  1. Scope
  2. location
  3. Name / Signatures (Acceptence)
  4. Hazards
  5. RTM#
  6. Environmental conditions
  7. Ergonomic concerns
  8. If other workers are in the area
  9. PPE requirements
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Identify the requirements a SWP Issuer must complete other than the documentation.

A
  1. Job walk - Everyone
  2. Confirm each Reciever understands permit requirements
  3. Determine if additional site inspection are needed
  4. Permit close out expectations
  5. Signature of SWP Issuer / Reciever
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the 3 responsibilities of the Facility / Work Group Leadership (FWGL)?

A

1 Authorize SWP Issuers
2. Approve/Document activies that dont require a SWP
3 Establish, Maintan and Communicate boundaries the group has operational control of.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

If work is being done in or near an area owned by another work group such that the operations and/or zards of the adjacent area may have an impact on the permitted work, or such that the permitted work ay have an impact on the adjacent area, what must the SWP Issuer do?

A
  1. Co Sign
  2. Print copy of SWP
  3. Notify other group when work is complete
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What must the SWP Receiver do prior to starting the permitted work?

A
  1. List all workers
  2. Review Hazords / Safegaurds
  3. Confirm all workers understand scope
  4. SWP Caseout expectations
17
Q

What is the maximum duration of a SWP?

A

24 hours

18
Q

Identify the requirements an Extended Duration SWP must meet by the standard.

A
  1. FWGL Approval
  2. NO CSE
  3. Conduct onsite inspection
  4. No Scope Change
  5. decord duration
  6. Same Reciever
  7. 50% Crew doesnt Change
  8. Wotk stoppage Not GT 24h
  9. Does not exceed 7 Days
19
Q

Where must a copy of the SWP be maintained?

A
  1. Work site
  2. designated location
20
Q

Identify conditions when a SWP issuers and/or SWP Receiver must stop the permitted work and notify one another.

A
  1. Scope changes
  2. Crew Change
  3. Emergency
    1 SWP Expires
  4. Work is complete
21
Q

While permitted work is progressing, what must a SWP Issuer do?

A
  1. Complete Inspections if needed
  2. Manage any changes
22
Q

What must a SWP Receiver do if they are unable to perform his/her responsibilities?

A
  1. Reassign SWP
  2. Confirm new receiver has signed all related documents CB
23
Q

What does the signature of a SWP Issuer indicate when closing out the SWP?

A
  1. Status was reviewed
  2. On site closeout is complete
  3. SWP is closed