§ 830.120 Scope.

A

Establishes quality assurance requirements for contractors conducting activities, including providing items or services that affect, or may affect, nuclear safety of DOE nuclear facilities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Subpart A - Quality Assurance Requirements
§ 830.121 Quality Assurance Program (QAP)

What should contactors conducting activities work in accordance with?

A

Contractors conducting activities, including providing items or services, that affect, or may affect, the nuclear safety of DOE nuclear facilities must conduct work in accordance with the Quality Assurance criteria in § 830.122.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Subpart A - Quality Assurance Requirements
§ 830.121 Quality Assurance Program (QAP)

What must the contractor responsible for a DOE nuclear facility do (for QAP)

A

The contractor responsible for a DOE nuclear facility must:

(1) Submit a QAP to DOE for approval and regard the QAP as approved 90 days after submittal, unless it is approved or rejected by DOE at an earlier date.
(2) Modify the QAP as directed by DOE.
(3) Annually submit any changes to the DOE-approved QAP to DOE for approval. Justify in the submittal why the changes continue to satisfy the quality assurance requirements.
(4) Conduct work in accordance with the QAP.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Subpart A - Quality Assurance Requirements
§ 830.122 Quality assurance criteria

Criterion 1 - Management/Program.

A

1) Establish an organizational structure, functional responsibilities, levels of authority, and interfaces for those managing, performing, and assessing the work.
(2) Establish management processes, including planning, scheduling, and providing resources for the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Subpart A - Quality Assurance Requirements
§ 830.122 Quality assurance criteria

Criterion 2 - Management/Personnel Training and Qualification.

A

(1) Train and qualify personnel to be capable of performing their assigned work.
(2) Provide continuing training to personnel to maintain their job proficiency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Subpart A - Quality Assurance Requirements
§ 830.122 Quality assurance criteria

Criterion 3 - Management/Quality Improvement.

A

1) Establish and implement processes to detect and prevent quality problems.
(2) Identify, control, and correct items, services, and processes that do not meet established requirements.
(3) Identify the causes of problems and work to prevent recurrence as a part of correcting the problem.
(4) Review item characteristics, process implementation, and other quality-related information to identify items, services, and processes needing improvement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Subpart A - Quality Assurance Requirements
§ 830.122 Quality assurance criteria

Criterion 4 - Management/Documents and Records.

A

(1) Prepare, review, approve, issue, use, and revise documents to prescribe processes, specify requirements, or establish design.
(2) Specify, prepare, review, approve, and maintain records.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Subpart A - Quality Assurance Requirements
§ 830.122 Quality assurance criteria

Criterion 5 - Performance/Work Processes.

A

(1) Perform work consistent with technical standards, administrative controls, and other hazard controls adopted to meet regulatory or contract requirements, using approved instructions, procedures, or other appropriate means.
(2) Identify and control items to ensure their proper use.
(3) Maintain items to prevent their damage, loss, or deterioration.
(4) Calibrate and maintain equipment used for process monitoring or data collection.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Subpart A - Quality Assurance Requirements
§ 830.122 Quality assurance criteria

Criterion 6 - Performance/Design.

A

(1) Design items and processes using sound engineering/scientific principles and appropriate standards.
(2) Incorporate applicable requirements and design bases in design work and design changes.
(3) Identify and control design interfaces.
(4) Verify or validate the adequacy of design products using individuals or groups other than those who performed the work.
(5) Verify or validate work before approval and implementation of the design.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Subpart A - Quality Assurance Requirements
§ 830.122 Quality assurance criteria

Criterion 7 - Performance/Procurement.

A

(1) Procure items and services that meet established requirements and perform as specified.
(2) Evaluate and select prospective suppliers on the basis of specified criteria.

Establish and implement processes to ensure that approved suppliers continue to provide acceptable items and services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Subpart A - Quality Assurance Requirements
§ 830.122 Quality assurance criteria

Criterion 8 - Performance/Inspection and Acceptance Testing.

A

(1) Inspect and test specified items, services, and processes using established acceptance and performance criteria.
(2) Calibrate and maintain equipment used for inspections and tests.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Subpart A - Quality Assurance Requirements
§ 830.122 Quality assurance criteria

Criterion 9 - Assessment/Management Assessment.

A

Ensure managers assess their management processes and identify and correct problems that hinder the organization from achieving its objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Subpart A - Quality Assurance Requirements
§ 830.122 Quality assurance criteria

Criterion 10 - Assessment/Independent Assessment.

A

1) Plan and conduct independent assessments to measure item and service quality, to measure the adequacy of work performance, and to promote improvement.
(2) Establish sufficient authority, and freedom from line management, for the group performing independent assessments.
(3) Ensure persons who perform independent assessments are technically qualified and knowledgeable in the areas to be assessed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly