Study Terms Flashcards
What are the 5 types of construction?
- Type I - fire resistive: Concrete or protected steel. Typically found in high-rise buildings.
- Type II - Non-combustible: Reinforced masonry with metal framing at roof. Typically found in mid-rise office buildings.
- Type III - Combustible: Also called “ordinary” using brick, block or light gauge steel framing walls with wood framing at roof. typically found in low-rise schools. hotels and offices.
- Type IV - Heavy Timber: Also called “Mill” Construction, wood must be nominally 8” or larger. Typically found in warehouse buildings.
- Type V - Wood Frame: used on apartment buildings and single-family homes. Typically found in apartment buildings and single-family homes.
A-305
Contractors qualification statement
A101
Standard form f agreement between the owner and the contractor where the basis for payment is a stipulated sum
A101
Standard form of agreement between owner and contractor where the basis for payment is stipulated sum
A201
General conditions of the contract for construction
A305
Contractors Qualification statement
A701
Instructions to bidders
Accessory occupancy
what determines an accessory use area
- Area can’t exceed 10% of total floor area allowed by height and area table.
- It does not need to be separated from the main area by a fire separation.
- Example: A small office inside a factory.
Addenda
Statements or drawings that modify basic contract documents after the latter have been issued to bidders, but prior to taking bids.
Addition to the contract sum
An amount added to the contract sum either by an accepted additive alternate or by a change order.
Arbitration
An Alternative to litigation or litigating a dispute in which one or more arbitrators hear the evidence and render a decision.
What is architect’s primary duty?
To protect the Health Safety and Welfare of the public
B101
Standard form of agreement between architect and the owner.
What 2 documents make up the B101
(Agreement between owner and Architect)
B101=B102 + B201
- B102 - Cannot stand alone and must be paired with something else. (standard form of agreement between owner and architect w/o a predefined scope of architects services.
- B201 - Standard form of architects services design & Construction Contract.
Basic Services
The architectural services normally required for a building project usually consisting of:
- Schematic design
- design development
- construction documents
- bidding and negotiation
- construction contract administration.
Bid Bond
A surety bond guaranteeing that the bidder will sign a contract if offered in accordance with his or her proposal
Bidding documents
- invitation to bid
- bid form
- contract documents
- instructions to bidders
Bonus and penalty clause
A provision in the construction contract for payment of a bonus to the contractor for completing the project prior to a specific date and for a charge (penalty) against the contractor for failing to complete the project by the date.
Bridging
what building code topics are typically addressed in the programming phase?
- Allowable floor area
- Parking requirements
C401
Standard form of agreement between Architect and consultant
Cash Allowance
An amount included in the contract sum to cover the cost of certain items not specified in detail. Hardware and other finish items are often handled in this manner.
Certificate of occupancy
A document issued by the governing authority stating that a building complies with applicable laws and permitting occupancy for its designated use.
Certificate of payment
A Statement by the architect informing the owner of the amount due to the contractor for work completed and or materials properly stored.
G702
Certificate of substantial completion
A document prepared by the architect stating that the work is substantially complete, thereby establishing the date of substantial completion. It generally fixes the time within which the contractor must complete the unfinished work listed.
change in services
(of the architect)
Professional services rendered by the architect upon the owner’s request, in addition to the basic services identified in the owner-architect agreement also called extra services.
change order
a written order to the contractor prepared by the architect and signed by the owner, contractor, and architect who authorizes a change in the work, the contract sum or the contract time.
Clerk of Works
the owner’s job site representative.
CM Advisor
Administers the contract and the work as the owners representative and don’t have financial responsibility
Advise owner about budget and contractibility during the design phase.
CM Advisor
Acts only as a constructibility consultant and cost management consultant to the owner during the design and construction process, but will not build the building.
CM Agent
Hired by the owner first, the CM manages the entire project on behalf of the owner.
CM Agent
(CM-A)
the CM As Agent provides Early consulting and may act on behalf of the owner in assembling and coordinating the construction trades prior to and during construction.
CM-Agents typically provide their services for a fixed fee.
CM Contractor
Hired by the owner @ 30% of design completion.
Advise owner Prior to construction and then build project
Assume a vendor relationship with the owner and have financial responsibility, topically using a fixed price, cost + fee w/ GMP
CM-Contractor
(CM-C)
The constructibility and cost advisor role of the contractor during the projects design phase and then transitions at a predetermined moment to the traditional role of a design-bid-build contractor for the project.
Typically includes a G.M.P Which is a commitment by the CM-C to build the project for a specific price based on an early design.
What is a code?
A code is an organized body of law designed to protect the health, safety and welfare of the public
Common path of egress travel
A portion of exit access that occupants must travel before two separate and distinct paths of egress travel to 2 exists become available.
Completion Bond
A bond obtained by the contractor or owner which guarantees that the project will be completed free of liens.
Comprehensive services
The architect’s Basic services expanded to include certain additional services such as programming, land use studies, etc.
Construction Change Directive
A document signed by the owner and the architect which authorizes a change in the work, the contract sum or the contract time. Used when there is not complete agreement on the terms of a change order.
For a CCD, the contractor does not have to agree.
for a change order, the contractor does have to be in agreement.
Contract Documents
- Working drawings
- specifications
- addenda
- general conditions of the contract
- supplementary conditions
- ower-contractor agreement
Contract Documents
- owner-contractor agreement
- general conditions of the contract
- supplementary conditions of the contract
- drawings
- specifications
- addenda issued prior to contract
- Any other documents specifically listed in the agreement
- modifications issued after execution of the contract
Contract sum
The total amount payable by the owner to the contractor as stated in the owner-contractor agreement, for performing the work under the contract documents.
Cost plus fee contract
An agreement under which the contractor or the architect is reimbursed for his or her costs and in addition is paid a fee for his or her services.
Cost plus fee method
Critical Path Method
(CPM)
A project management procedure in which all events and operations are charted in a way that establishes the optimum sequence and duration of operations.
Davis-Bacon act
A federal law that requires the department of labor to set prevailing wages for government-financed construction projects.
How many days does the contractor have to notify the architect of an issue between the drawings and the project site?
21 days
Which delivery method involves hiring someone with constructibility and const expertise to work with the architect during the design phase?
Construction Management
what 2 elements deplete the ozone layer?
- Chlorine
- Bromine
Direct personal expense
(DPE)
Salaries and wages Attributable to a specific project, plus benefits such as employee taxes, insurance, sick leave, holidays, vacations, pensions and similar contributions and benefits.
What happens if there is a discrepancy between the drawings and the specifications?
Drawings and specifications are complimentary.
if there is a conflict, the architect should be notified, review the conflict, and issue a written clarification.
Division 00
Procurement and contracting requirements
- requirements for bidding and contracting
- The agreement (contract)
- bonds and certificates
- general conditions of the contract
- supplementary conditions
- Addenda
- Modifications
Division 1
the general requirements division of the specifications that established the contractor, architect, and owner during construction.
Division 1
General Requirements
- A Summary of the work
- How pricing and payments will be handled
- Alternates
- Value analysis, special execution requirements.
- contract modification procedures
- unit prices, final cleaning protection of work
- construction progress documentation
- submittal procedures
- Quality control, temp. facilities @ job site, product substitution procedures, owner furnished items
Division 2
Existing conditions
- Site Remediation
- site decontamination
- subsurface investigation
- surveying and selective demolition
- other items related to existing conditions on a job site.
Division 3
Concrete
All Aspects of concrete including:
- Forms
- Reinforcement
- Cast-n-place concrete
- pre-cast concrete
- cementitious decks and underlayment
- grouts
- concrete restoration and cleaning
Division 4
Masonry
All Aspects of masonry including:
- Brick
- Concrete block
- Stone
- Terracotta
- Simulated masonry
- Glass block
- Masonry Restoration and cleaning.
Division 5
Metals
Includes all types of structural steel and other structural metals, ornamental metals, metal fabrications (metal stairs, ornamental ironwork, handrails, grating, metal castings, stair treads and nosings), expansion joint covers, metal restoration and cleaning
light gauge metal framing is in division 9
Division 6
woods, plastics, and composites
Typical structural wood framing, rough carpentry, finish carpentry, Architectural Woodwork. It also includes structural plastics, plastic fabrications, wood and plastic restoration and cleaning, newer plastic woods and other specialty composite materials
Casework is in division 12, furnishings.
Division 7
Thermal and moisture protection
includes Damp proofing, waterproofing, insulation, vapor retarders, air barriers, shingles, roof tiles, siding, membrane roofing, flashing, joint sealers, fire and smoke protection, and roofing specialties such as roof hatches, smoke vents, roof pavers, scuppers and gravel stops
Due Care
(Standard of care)
the requirement that a professional exercise reasonable ability and judgment in a specific circumstance. the absence of which constitutes negligence.
What are the 3 parts of an egress system?
- Exit Access
- Exit
- Exit Discharge