Strip / Pad / Piled Foundations Flashcards

1
Q

Describe the process of constructing a strip foundation?

A
  1. Dig trenches to a depth that reaches the required soil bearing strata.
  2. Erect and place temporary supports
  3. Pour concrete into the trenches.
  4. On top of these concrete trenches, the loadbearing walls of the building can be erected.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

For buildings with insulated ground floors what is the general minimum foundation depth that is sufficient against the possibility of damage from ground movement due to frost heave?

A

450mm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why are strip foundations not commonly used when you have to excavate deep into the ground to reach soil with a higher bearing strata?

A

It is very expensive thus pad foundations (less excavation required) are used.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does the width of a concrete strip foundation depend on?

A

The Bearing Capacity of the soil and the loads that will be acting on the foundations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is shear failure?

A

Shear is caused by two opposing forces of the wall and the ground acting on and tearing or shearing the concrete (footing).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Strip foundations on subsoils with poor bearing capacity need to be a lot wider than the wall they support. The alternative to widening the wall is adding…?

A

Steel reinforcement (means the foundation doesn’t need to widen as much).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

It is normal when using strip foundations to have a foundation depth of at least what?

A

0.9m minimum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What depth is ‘topsoil’ (the weak top surface of land that needs to be removed before construction can begin)

A

Typically between 100-300mm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Describe the process of constructing a pad foundation?

A

Pits are excavated down to the necessary level (the sides of the excavation are temporarily supported and isolated pads are cast in the bottom of the pits. The ground beams/foundation beams may be just below or at ground level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Describe the process of constructing a pile foundation?

A

Pits are excavated down to the necessary level, the sides of the excavation temporarily supported and isolated pads of concrete are cast in the bottom of the pits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What material is most used for temporary support for the sides of excavations in foundations?

A

Rough Sawn Timber

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Name the 4 different types of foundation (and describe them in your head)

A
  1. Strip
  2. Pad
  3. Pile
  4. Raft