Standard variance Flashcards
Direct material cost variance
SC - AC
SC = SP x SQ (rate times actual production ignore planned production)
AC = AP X AQ
- Price variance = (SP - AP) * AQ
- Usage variance : (SQ - AQ) * SP
Direct labour cost variance
SC - AC
SC = SR x SH (rate times actual production ignore planned production)
AC = AR X AH
- Rate variance = (SR - AR) * AH
- Usage variance : (SH - AH) * SR
Adverse vs Favourable
Adverse - negative value (AC > SC)
Favourable - positive value (AC < SC)
Fixed overheads
Budget - Actual
Basic Cost standard (Not ideal to use)
All results are compared with a base year. Doesn’t consider changes in methods of production, price levels or other relevant factors, thus it isn’t ideal to use.
Ideal Cost standard (Difficult to achieve)
They represent perfect performance where minimum costs must be at the lowest level with maximum efficiency. Doesn’t consider macroeconomic conditions and has an adverse effect on employee motivation.
Currently attainable standard cost (Most ideal)
Difficult to achieve but possible takes several factors into consideration such as macroeconomic conditions