SREC Flashcards

1
Q

You say you have experience advising on property portfolios and strategic projects - can you explain how?

A

Portfolio review & scoring matrix - family portfolio, retail disposals

Telecoms providers - supporting non-cognate professionals eg. access requirements

Project management - prioritisation system (Landlord contact example)

Reducing costs - e.g. Solihull site blocker example

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How do you go about understanding clients’ core business strategies?

A

Meetings - be curious - understand goals, targets, challenges

How is the team/business performing against their goals/targets?

What challenges are arising? What is preventing progress? How are they currently approach such hurdles?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How have you helped clients reduce costs?

A

Solihull blocked site example

Access had been planned, contractor arrived and the neighbouring site (car garage/depot) had cars blocking access

The Landlord had approved access prior but was on holiday and advised he couldn’t deal with the issue until he returned - as such, the upgrade would have to be aborted

This would cost upwards of £5,000

I also noticed a renewal was on the horizon, and through previous meetings with the client, I knew timely renewals were of upmost importance, and that new ‘code’ renewals meant these were getting delayed

I advised the client that enforcing access rights in a situation like this could damage the relationship with the landlord, making the upcoming renewal a challenge

I suggested a one-off payment to appease the Landlord and have the situation resolved

Contractors were able to get on site, saving £5,000+ in abort fees, and potentially saving time & lawyer’s fees on the renewal further down the line

Renewal completed in a timely manner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How have you helped clients meet their strategic goals?

A

Best example would be my project supporting a telecoms client meet their 5G upgrade targets (Network Operator Access example)

I supported a team with a target of 60 upgrades per month

A number of these at any given time would be considered ‘blocked’ i.e. a landlord isn’t providing access - could be anything from outstanding renewal/rent review, outstanding rental payments, landlord has their own works, landlord unable to be contacted, landlord has changed etc
My role was to remove the blocker

This meant building a relationship with the landlord to come to a solution, or leaning on rights within the lease

Set up a system to contact all sites one month in advance, this was to confirm correct details, process and advise of plans to attend site

Sites that threw up issues were prioritised, or pushed back a month and replaced with a new site

This means we had sites ongoing to ensure target of 60 was achievable

I was on the project for 3 months and we were able to hit the target each month, including hitting 75 in the final month (end of financial year)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are some analysis techniques to analyse strategic real estate data?

A

SWOT analysis

PESTLE analysis

Scoring Matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When else might a Strategic Real Estate consultant be required?
When might Strategic advise be provided to a client?

A

Managing occupational requirements (if they need less or more space)

Portfolio reviews

Cost reduction exercise

Their current office is no longer fit for purpose

Location change

To comply with sustainability initiatives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the role of a Strategic Real Estate Consultant?

A

Working with senior management to ensure an organisation’s assets are delivering against its business strategy and objectives (both current and future).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why is Strategic Real Estate important?

A

Property is usually the second highest business expense behind staff.

The SRE consultant often works closely with wider professionals, and advising non-cognate professionals (often at senior level) such as an organisation’s board members.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Tell me about your involvement with the provision of strategic consultancy advice to clients.

A

One example is my review of a family portfolio (portfolio analysis example)

Family portfolio who weren’t property professionals, had their own careers etc

They wanted to reduce the size of their portfolio and in particular their exposure to secondary retail assets

We had a meeting to define ‘secondary’/the type of assets they wanted to dispose of

We concluded that the most important elements were the property’s location/marketability to occupants, the current tenant covenant and the years remaining on the lease.

I produced a matrix analysing each property by this criteria

Out of 9 retail properties, identified 3 that met the criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Tell me about your Network Operator Access Example?

A

I worked with a telecoms operator client to help them achieve 5G update targets

I supported a team with a target of 60 upgrades per month

A number of these at any given time would be considered ‘blocked’ i.e. a landlord isn’t providing access - could be anything from outstanding renewal/rent review, outstanding rental payments, landlord has their own works, landlord unable to be contacted, landlord has changed etc
My role was to remove the blocker

This meant building a relationship with the landlord to come to a solution, or leaning on rights within the lease

Set up a system to contact all sites one month in advance, this was to confirm correct details, process and advise of plans to attend site

Sites that threw up issues were prioritised, or pushed back a month and replaced with a new site

This means we had sites ongoing to ensure target of 60 was achievable

I was on the project for 3 months and we were able to hit the target each month, including hitting 75 in the final month (end of financial year)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What was the advice you provided?
(Network Operator Access Example)

A

The team weren’t property professionals - they were engineers/project managers

I was able to advise when we could and couldn’t rely on the lease terms to get on site

I also set up a spreadsheet tracker marking each site as ‘on track’, ‘blocked but resolvable’ and ‘delay’ - this enabled client to forecast numbers, and swap in new sites to replace the blocked/delayed sites

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What lease terms would you refer to?

A

Generally under Rights schedule

Would often advise right of access at all times and for all purposes

Rights without charge to inspect, maintain, repair, renew, replace, add to, alter, substitute, upgrade

Sometime would specify 24hr or 48hr notice

Sometimes would specify approval required from the Landlord (NTBUWoD)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What was their key objective for the strategy?
(Network Operator Access Example)

A

Key objective was to reach 60 upgrades per month

Also very important to avoid abort costs as these could be £5,000, £10,000 or even higher

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How was your advice presented to the client?
(Network Operator Access Example)

A

I produced a spreadsheet that highlighted which sites were on track/blocked but resolvable/delayed

The tracker was accessible by all stakeholders and client

Contractors would mark when equipment/MEWP/cherry pickers had been booked, where they were at in the process, if timelines were being met

That way everyone had oversight over each site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Tell me about your Landlord contact example?

A

One landlord for the network operator that had over 300 sites (operate canals and rivers around the UK)

Generally rural sites with access required through third parties e.g. farms, businesses, pubs

The client looked after a team who worked on outages for masts. Outages are big important issue for network operators - really important to fix quickly

They identified that this landlord hadn’t been updating access contacts for some years, and were having issues attending sites that had suffered outages

Came to Cluttons to resolve over 300 sites ASAP

I advised that in my experience, this can often take time to resolve, contacts can be hard to establish, difficult to reach etc

Therefore we should prioritise sites - P1, P2, P3

P1 was sites that needed to be attended immediately (outages, new equipment required etc)

P2 was sites where access was required in the coming months

P3 was all remaining sites

We were able to get the client onto all P1 sites (20 or so) within 2 weeks

And updated details for all remaining sites within 2 months

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What was the client’s key objective?
(Landlord Contact Example)

A

The overall goal was to update details for all the sites

But the key objective was to get the client onto the P1 sites ASAP

17
Q

What goals did you help you client meet?
(Landlord Contact Example)

A

Resolve outages within 2 weeks

18
Q

How did you present your advice to the client?
(Landlord Contact Example)

A

I would call/email the stakeholders at the end of each day advising what progress had been made on the P1 sites
We would update the system on P2 and P3 sites which would then inform the stakeholders
We had a spreadsheet to track progress

19
Q

Tell me about your portfolio analysis example?

A

This was strategic advice to a family portfolio who weren’t property professionals, had their own careers etc

They wanted to reduce the size of their portfolio and in particular their exposure to secondary retail assets

We had a meeting to define ‘secondary’/the type of assets they wanted to dispose of

We concluded that the most important elements were the property’s location/marketability to occupants, the current tenant covenant and the years remaining on the lease.

I produced a matrix analysing each property by this criteria

Out of 9 retail properties, identified 3 that met the criteria to be disposed of

20
Q

What properties met the criteria?
(Portfolio Analysis example)

A

The property they received an offer on was in Ealing. They had two properties there and one was close to the tube station and benefitted from 3 flats above, all let. This one was further away from the station and had a local tenant with just a couple of years remaining on the lease. Agent advised the unit close to the station always lets well, the other not so much. They received an offer from the neighbouring Landlord and accepted

One in Epping - on the ‘High Street’ but away from the main pitch, short lease term, local covenant

High Wycombe - there’s a number of different pitches in Wycombe as well as shopping centres, speaking with agents helped understand what was considered prime (dominated by Eden centre, streets around there do well, short stretch of the high street does well, rest not so much – we were situated on a road between the high street and the eden centre)

21
Q

What about the other properties?
What about properties that passed the test?
(Portfolio Analysis example)

A

One in Balham - national occupier, new lease

One in Oxted - local covenant (restaurant), but close to the station, restaurant very popular

One in Guildford - end of the ‘prime pitch’ - good tenant/covenant, long lease term

22
Q

What was the client’s key objective/goals/strategy?
(Portfolio analysis example)

A

Key objective was to reduce the size of their portfolio and in particular their exposure to secondary/weaker retail assets

23
Q

How did you present your advice to the client?
(Portfolio analysis example)

A

Provided a matrix ranking each property on the criteria we agreed

Three properties were identified as not meeting the necessary criteria

24
Q

Tell me about your Telecoms site blocker example (Solihull)?

A

Access had been planned (5G upgrade), contractor arrived and the neighbouring site (car garage/depot) had cars blocking access

The Landlord had approved access prior but was on holiday and advised he couldn’t deal with the issue until he returned - as such, the upgrade would have to be aborted

This would cost upwards of £5,000

I also noticed a renewal was on the horizon, and through previous meetings with the client, I knew timely renewals were of upmost importance, and that new ‘code’ renewals meant these were getting delayed

I advised the client that enforcing access rights in a situation like this could damage the relationship with the landlord, making the upcoming renewal a challenge

I suggested a one-off payment to appease the Landlord and have the situation resolved

Contractors were able to get on site, saving £5,000+ in abort fees, and potentially saving time & lawyer’s fees on the renewal further down the line

Renewal completed in a timely manner

25
Q

What strategic objective did you help your client meet?
(Telecoms site blocker Solihull)

A

Reducing abort fees - saving £x000’s

Maintaining positive relationship with the Landlord

Aiding future renewal - helping renewal goals/targets

26
Q

How did you determine how much to offer the Landlord?
How much did this save your client? What was the cost benefit?
(Telecoms site blocker Solihull)

A

I arranged a call with my client and determined the abort costs for the project would be upwards of £5,000
I spoke with my supervisor who advised one-off payments had been agreed in similar situations in the past for between £500-£2,500
We agreed we would start at £1,000 and go upwards if need be, up to a cap of £2,500
Speed an important factor - equipment being delivered to site