Q

What does the 100% rule in WBS creation mean?

A

completing all the work at lower level of hierarchy mean completing all the work at highest level (100% of the work)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a Work Breakdown Structure?

A

a HIERARCHICAL DECOMPOSITION of a task/goal into SMALLE SCALE tasks or goals