Site Utilities and Plumbing Flashcards

1
Q

Utilities are piped below ground up to _ feet from the building

A

5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

If cast iron fittings are used, they must be _ lined

A

cement-mortar

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Fire hydrants will be _, depending on freezing conditions, and installed with _.

A

wet or dry barrel, protective posts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Common materials include cast iron soil pipe, clay, concrete, or plastic up to _ inches in diameter.

A

15

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Manholes are installed in sewer and drain piping to permit _ of the pipes.

A

inspection and maintenance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Straight runs of pipe will have manholes about _ feet apart.

A

500

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Manholes more than _ feet deep will include a permanent ladder and be eccentric in shape.

A

12

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Storm drain piping will carry only surface run-off water and underground seepage water by means of _.

A

gravity flow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A single conductor, #_ AWG (American Wire

Gauge) wire with type TW insulation, is installed alongside plastic pipe to aid in locating the gas pipe.

A

14

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Gas steel pipe will be _ except at control valves, and coated as specified at the factory.

A

welded

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Gas pipe joints are coated in the field with _.

A

factory supplied materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Plastic pipe must be below ground, _ pounds per square inch gauge (psig) or less, and restricted to temperatures as specified in the contract.

A

100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Excavated material must be at least _ feet away from the edge of the trench.

A

2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Trenching more than _ feet deep may require bracing support, depending on the type of soil and
amount of moisture.

A

5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Ladders are required in trenches over _ feet deep, within _ feet of workers, and must extend _ feet above the ground surface.

A

4, 25, 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The trench bed width is limited by specifications and extends from the bottom of the trench to _ foot above the pipe.

A

1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Depressions called _ must be dug in the trench bottom to accommodate the _ of the pipe and to provide space for making the joint.

A

bell holes, bell joints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

The backfill material is specified by the contract. It gives the maximum rock size permitted, thickness
of each layer, compaction density, and _.

A

moisture content

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Bell ends must face _hill.

A

up

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Water lines must be _ feet horizontally from sewage lines, or at least _ feet if the water pipe is _ foot above the sewage line.

A

10, 6, 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Thrust blocks or tie rods are required at all bends of _ degrees or greater and at all caps, plugs, tees, and fire hydrants.

A

22-½

22
Q

Concrete thrust blocks should harden _ days prior to applying water pressure.

A

5

23
Q

Sewer lines that cross over water lines should be encased in _ inches of concrete for _ feet on each side of the water line.

A

4, 10

24
Q

Force mains must always cross _ feet beneath water lines.

A

2

25
Q

There are three methods of testing for leakage in sanitary sewer lines: ,,_.

A

exfiltration, infiltration,

and the air test

26
Q

When the trench has been backfilled to at least the _ (midpoint) of the pipe and the joints are still exposed, the pipe line must be tested for leakage by _.

A

spring line, exfiltration

27
Q

Each pipe section between manholes is then tested by _ it at the lower end. The pipe is then filled with water and a _-foot head imposed on the upper end.

A

plugging, 2

28
Q

The amount of water required to maintain it’s head during a _-hour period is measured.

A

2

29
Q

The leakage must not exceed _ gallons per inch diameter, per _ feet of pipe, per hour.

A

0.2, 100

30
Q

If the water table is above the top of the pipe, then the pipe must be tested by _.

A

infiltration

31
Q

The Infiltration method measures for leakage by a _ (or dam) at the lower end.

A

V-notch weir

32
Q

The third method used to test for sanitary sewer leakage, but one that is seldom used in Corps contracts, is a _ of vitrified clay pipe line (3 to _ inches).

A

low-pressure air test, 18

33
Q

The sewer section is plugged at each end and pressurized with air to _ pounds per square inch gauge (psig) and the time noted for the pressure to drop to _ psig.

A

3.5, 2.5

34
Q

This method can be used to locate a leak quickly and accurately by moving a pair of _ through the pipe and pressurizing the section between the _.

A

inflatable plugs, plugs.

35
Q

A _ test is conducted when the trench has been backfilled _ feet above the top of the sewer pipe.

A

Displacement, 2

36
Q

Each section between manholes is examined by _ into one end and observing the straightness of the pipe from the other end.

A

shining a light

37
Q

Flexible sewer pipe, such as single-wall plastic, is inspected for _ after the trench is completely backfilled.

A

deflection

38
Q

A plug of hard material having a diameter of _% of the actual inside diameter of the pipe is pulled through the
sewer section from one manhole to the other.

A

95%

39
Q

If the plug will not pass freely through the pipe, then the sewer section is not satisfactory because the overburden has deformed the pipe more than _% of its diameter

A

5%

40
Q

When watertight joints are required, a test is performed on each type of joint in the system before the pipe is installed. Two lengths of pipe are joined, and the joint is subjected to _
psi (pounds per square inch) hydro-static pressure for _ hours.

A

10, 24

41
Q

The contractor is required to apply a pressure test and a leakage test to the water piping, usually at _ psi or _ times the working pressure.

A
  1. one-and-a-half
42
Q

n the pressure test, the water pressure is held for _ hour(s), and the exposed joints and
piping are examined for leaks.

A

1

43
Q

In the leakage test, the pressure is held for _ hour(s) and the leakage is measured by
recording the amount of water added to the system to maintain the pressure.

A

2

44
Q

Pipe made of concrete or asbestos cement, or which is cement-lined or has mortar joints, should be filled with water _ before the test to permit these materials to absorb water.

A

several hours

45
Q

The hydro-static pressure test for water piping that supplies fire protection systems must be at least _ psi and _ psi in excess of the maximum static pressure.

A

200, 50

46
Q

Fire hydrants must be tested as specified in _.

A

NFPA 24

47
Q

Natural gas system mains and service lines must be tested with air at _ psi or _% of the operating pressure, whichever is greater.

A

75 psi, 150%

48
Q

Natural gas tests must continue for at least _ hours between the times of initial and final readings of temperature and pressure.

A

24

49
Q

The sterilizing dosage of chlorine must be at least _ parts per million (ppm).

A

50

50
Q

Chlorine compounds must be _ in water

before they are fed into plastic pipelines.

A

Dissolved

51
Q

85 of 208

A

1