What is the triangular formula? 
Basically the average.
(X+y+z)=w
What is and how to use a control chart?
It identifies production issues and causes a variance in quality
What does it mean if a customer is unwilling to accept the deliverable due to function?
It usually means performance baselines are not define such as quality metrics
If a stakeholder can’t accept a deliverable, what should be done first?
Update the issues log and asses if there’s any other way to get around it
If a project schedule is trending behind, what is the next step to take and why? (SPI<1)
Issue a change request
Without enough time you can’t even allocate more resources to it.
What’s the point of a minimum viable product?
The objective is for the customer to start seeing value.
It’s not a finished deliverable.
What is CV=EV-AC?
Cost variance =
earned value - actual cost
What is SV=EV-PV?
Schedule variance =
Earned value - Planned value
What phase is a resource management plan created?
The planning phase
When do you start creating the business case?
In the initiating phase
Once you have prelim scope, few restrictions, & some assumptions.
SPI > 1
Ahead of schedule
SPI < 1
Behind schedule
CPI > 1
Under budget
CPI < 1
Over budget
Where can you find the communication and stakeholder engagement plans?
Project management plan