Setpoints Flashcards
Nominal steam flow
15 x10^6 lbm/hr
ECCS initiation setpoints
-HPCS: -50”, 1.68#
-LPCS: -129”, 1.68#
-LPCI: -129”, 1.68#
ADS auto-initiation logic
-Low RPV level (-129”)
-Confirm low RPV level (+13”)
-105 second time delay (starts at Level 1)
-LPCS or LPCI available (LPCS >145#, LPCI >125#)
Vessel pressure limits
-Normal Operating: 1020#
-LCO limit (3.4.12): 1035#
-Design limit: 1250#
-Safety limit: 1325#
Vessel heatup and cooldown rates
-Admin: 80F/hr
-Tech Spec (3.4.11): 100F/hr
Safety Limits and actions if violated
-Steam dome press <686# or core flow <10%, THERMAL POWER shall be LE 25% RTP
-Steam dome press GE 686# and core flow GE 10%, MCPR shall be GE 1.07
-RPV level shall be > TAF
-Steam dome press shall be LE 1325#
-If violated: w/in 2 hrs, restore and insert all insertable rods
MSIV & MSL Drain isolation signals
-MSL low press: 831#
-Low cond vac: 21.6” Hg
-RPV low level: -129”
-High steam flow: 140%
-High MS Tunnel temp/diff temp
EDG Auto Starts
-DG-1: UV SM-7, RPV -129”, DW 1.68#
-DG-2: UV SM-8, RPV -129”, DW 1.68#
-DG-3: UV SM-4, RPV -50”, DW 1.68#
-EDG req to be at rated speed/voltage in 15 sec (typically 7-10), can be fully loaded in 30 sec (loads auto sequenced)
FAZ signals (CTMT Vent & Purge isolation signals)
(Fog, Agua, Zoomies)
F- High Drywell Pressure (1.68#)
A- Low RPV Water Level (-50”)
Z- High RB Exh Plenum Rad Level (13 mr/hr)
Reactor Scram conditions (RPS)
Pressure:
-DW high press (1.68#)
-RPV high press (1060#)
APRM:
-Upscale STP
-Upscale neutron flux Hi
-Fixed flux
-APRM INOP
Manual:
-Mode Switch to Shutdown
-Manual pushbuttons
Level:
-RPV low level (+13”)
-SDV high level (95%)
IRM:
-Neutron flux Hi (120/125)
-INOP
Valves:
-MSIV closure (<90% open)
-Turbine TV closure (<95% open)
-Turbine GV trip header low press (1252# @ >30%)
SRM:
-SRM Flux Hi (WITH SHORTING LINKS REMOVED)
OPRM:
-Period, Amplitude, Rate