Service water Flashcards

1
Q
Which system's principle purpose is the dissipation of decay heat?
A. Service Water System
B. Component Cooling Water System
C. Ultimate Heat Sink
D. Shutdown Cooling System
A

C’f Ultimate Heat Sink

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which of the following describes the rated design for the Service Water Pumps?
A. 8000 gpm and 120 feet TDH (Total Developed Head).
B. 8000 gpm and 140 feet TDH (Total Developed Head).
C. 7800 gpm and 120 feet TDH (Total Developed Head).
D. 7800 gpm and 140 feet TDH (Total Developed Head).

A

B. 8000 gpm and 140 feet TDH (Total Developed Head)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which of the following service water controls does the operator have the capability of
manipulating from remote panel, C-33?
A. P-7A/B/C, Service Water Pump start/stop handswitches.
B. CV-1359, Non-critical service water header isolation valve.
C. CV-0847, Containment Air Cooler service water supply.
D. CV-0857, Critical headers cross connection.

A

C~ CV-0847, Containment Air Cooler service water supply

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Service water pumps P-7A & 78 are running with service water header pressures at 76
psig. Due to an electrical fault, the closing coil fuses for Service Water Pump P-7C
have deenergized.
Assuming all bulbs are good, what Control Room indication could be used to confirm
the above condition?
A. The AMBER light will NOT illuminate when placing P-7C in standby.
B. P-7C would trip if it was in service.
C. The GREEN light above the handswitch is ON.
D. The AMBER light remains ON if P-7C is taken out of standby.

A

A. The AMBER light will NOT illuminate when placing P-7C in standby

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Service Water Pumps, P-7B and P-7C are in service with P-7A in Standby. Service
Water pump discharge pressure is 75 psig.
Which of the following would cause P-7A to automatically start?
A. The air line to CV-1359, Non-Critical Service Water Header Isolation Valve is
severed.
B. The Secondary Side Auxiliary Operator commences chlorinating the Service Water
Bay, causing Service Water pump discharge pressure to fall to 56 psig.
C. CV-1319, SW Pump Cross-Tie, is inadvertently CLOSED.
D.The Control Operator stops the P-7B Service Water Pump; Critical SW Header
pressures lower to 36 psig.

A

D.The Control Operator stops the P-7B Service Water Pump; Critical SW Header
pressures lower to 36 psig.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Non-critical Service Water has been isolated for maintenance and the containment air
cooler high capacity valves are closed to help raise containment temperature.
• It is day 40 of an extended plant outage.
• Service Water Pumps P-7A and P-7B are in-service.
• Service Water Pump P-7C is in standby.
• Service water header pressure is 80 psig.
To prevent P-7B from being run at significantly reduced flows, the CRS directs the
NCO to secure P-7B. When Service Water Pump P-7B is secured header pressure
lowers to 45 psig, Service Water P-7C starts, and header pressure returns to 80 psig.
Should Service Water Pump P-7C have started and why?
A. Yes, a standby pump starts at 40 psig discharge pressure on either of the other
pumps
B. Yes, a standby pump starts at 45 psig header pressure
C. No, the standby pump should not start when a pump is manually secured
D. No, the standby pump should not start until header pressure reaches 40 psig

A

A. Yes, a standby pump starts at 40 psig discharge pressure on either of the other
pumps

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The Plant is in mode 1 with Service Water Pumps P-7A and P-7C in service. Service
Water Pump P-7B is in Standby. Service Water pump discharge pressure is 75 psig.
Which of the following would cause P-7B to automatically start?
A. CV-1318 SW Pump Cross-Tie is inadvertently CLOSED.
B. The air line to CV-1359, Non-Critical Service Water Header Isolation Valve, is
severed.
C. P-7C discharge pressure switch PS-1320 is inadvertently isolated.
D. P-7A Service Water Basket Strainer F-2 dIP is >5 psid and increasing.

A

C. P-7C discharge pressure switch PS-1320 is inadvertently isolated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The plant is on day 30 of a refueling outage. Due to main generator maintenance the
Non-critical Service Water header has been isolated.
• Service Water Pumps P-7A and P-7C are in-service.
• Service Water Pump P-7B is in standby.
• Service water header pressure is above 80 psig.
Due to the low flow conditions the CRS directs the operator to secure P-7C. When
Service Water Pump P-7C is secured critical service water header pressure lowers to
45 psig. Service Water Pump P-7B did not start.
Is this the correct service water pump response and why?
A. No, P-7B should have started at 40 psig discharge pressure on either of the other
pumps.
B. No, P-7B should have started at 45 psig header pressure.
C. Yes, P-7B should not start since P-7C was manually secured.
D. Yes, P-7B should not start until header pressure reaches 40 psig.

A

A. No, P-7B should have started at 40 psig discharge pressure on either of the other
pumps

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The air line to CV-0870, Service Water inlet valve to Containment Air Cooler #3, has
completely broken off resulting in a total loss of operating air to the valve. CV-0870
will:
A. open or remain open.
B. close or remain closed.
C. stay as is due to nitrogen backup.
D. stay as is due to internal valve design.

A

A. open or remain open.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The air line to CV-0869, Service Water Inlet to Containment Air Cooler #4 Valve has
completely broken off. As a result of this, the valve will:
A. Open or remain open.
B. Close or remain closed.
C. Stay as is, due to nitrogen backup.
D. Stay as is, due to internal valve design.

A

B. Close or remain closed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The plant is at normal full power operations with all four Containment Air Cooler (CAC)
High Capacity Outlet valves open. Service Water Pump discharge pressure is 82 psig.
All Service Water Pumps are inservice. Which one of the following actions will lower
Service Water Pump discharge pressure?
A. Secure the “B” CAC fans
B. Close one CAC High Capacity Outlet valve.
C. Secure the “A” CAC fans.
D.Secure one Service Water pump.

A

D.Secure one Service Water pump

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which one of the following describes the position of the Containment Air Cooler
Service Water inlet and outlet valves for a complete loss of Instrument Air and why?
A. VHX-4 inlet and outlet are closed; VHX-1, 2, 3 inlet and outlet are open. This
provides maximum cooling on a loss of instrument air.
B. VHX-4 inlet and outlet are closed; VHX-1, 2, 3 inlet and outlet are open. VHX-4
isolates because it is not safety-related. VHX-1, 2, 3 valves have nitrogen backup.
C. VHX-4 inlet is closed; VHX-1, 2, 3 inlet and outlet and VHX-4 outlet are open.
VHX-4 inlet closes because it is not safety-related. VHX-1, 2, 3 and VHX-4 outlet
have nitrogen backup.
D. VHX-4 inlet is closed; VHX-1, 2, 3 inlet and outlet and VHX-4 outlet are open. This
provides maximum cooling on a loss of instrument air

A

D. VHX-4 inlet is closed; VHX-1, 2, 3 inlet and outlet and VHX-4 outlet are open. This
provides maximum cooling on a loss of instrument air

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Annunciator EK-1129, “SERVICE WATER PUMP BAY LO-LEVEL” alarm initiates and
bay level is lowering.
Which of the following describes the effect on the Service Water System?
A. Temperatures on components cooled by service water will start to lower.
B. The dp on the service water pump basket strainers will start to rise.
C. The critical service water header pressures will start to lower.
D. The service water booster pump P-25, will automatically start.

A

C. The critical service water header pressures will start to lower

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Annunciator EK-1129, “SERVICE WATER PUMP BAY LO-LEVEL” alarm initiates and
bay level is lowering.
Which of the following describes the effect on the Service Water System?
A. Temperatures on components cooled by service water will start to lower.
B. The dp on the service water pump basket strainers will start to rise.
C. The critical service water header pressures will start to lower.
D. The screenwash system will automatically start.

A

C. The critical service water header pressures will start to lower.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The Service Water System Break Detector alerts the operators to the potential of:
A. Flooding in the Turbine Building.
B. Flooding in the Containment Building.
C. Exceeding the service water pumps motor amps.
D. Exceeding the service water design flow rates

A

B~ Flooding in the Containment Building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

If the Turbine Bldg. were to experience a loss of Non-Critical Service water due to a
piping system malfunction, which annunciators would alert the control room operators
that a reactor trip was required?
A. EK-0260 H2 Cooler Hi Temp, and EK-1165 Non-Critical Serv Water Lo Press.
B. EK-0259 Exciter Cooler Hi Temp, and EK-1165 Non-Critical Serv Water Lo Press.
C. EK-0156/62 Condensate Pump Hi Temp, and EK-0259 Exciter Cooler Hi Temp.
D. EK-0259 Exciter Cooler Hi Temp, and EK-0260 H2 Cooler Hi Temp.

A

Not Sure, to be added

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Given the following conditions:
• The plant is operating at 100% power.
• Service Water Pump P-7B is tagged out for maintenance.
• P-7A is in service with running amps = 80 amps.
• P-7C is in service with running amps = 83 amps.
• All systems are functioning normally for plant conditions.
A problem develops with the Service Water System. The NCO then notes the following
indications:
• CRITICAL SERV WATER HEADER “A” LO PRESSURE
• P-7A Service Water Pump amps indicates 94 amps.
• P-7C Service Water Pump amps indicates 83 amps.
NO operator actions have been taken. Which one of the following accounts for the
above conditions?
A. A break between P-7A and CV-0845.
B. A loss of instrument air to CV-0844.
C. A loss of instrument air to CV-1359.
D. A partially plugged discharge basket strainerfor P-7A.

A

A. A break between P-7A and CV-0845.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

The Non-critical service water header isolation valve, CV-1359, has experienced a
malfunction causing the valve to close. Which annunciators would alert the control
room operators that a reactor trip was required?
A. EK-0259 Exciter Cooler Hi Temp and EK-0156/62 Condensate Pump Hi Temp
B. EK-1124 Traveling Screen Hi dP and EK-1 129 Service Water Pump Bay Lo Level
C. EK-1165 Non-Critical Serv Water Lo Press and EK-0260 H2 Cooler Hi Temp
D. EK-1165 Non-Critical Serv Water Lo Press and 0259 Exciter Cooler Hi Temp

A

D. EK-1165 Non-Critical Serv Water Lo Press and 0259 Exciter Cooler Hi Temp

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Annunciator EK-1165, “NON-CRITICAL SERVICE WATER La-PRESSURE” alarm
initiated.
What redundant indication, if any, is available in the Control Room to validate this
alarm?
A. The non-critical service water pressure indicator.
B. Temperature indications on components cooled by non-critical service water.
C. The non-critical service water pressure recorder.
D. None, there is no way to verify/validate this alarm in the Control Room

A

B. Temperature indications on components cooled by non-critical service water

20
Q

The plant operating at 100% power. No planned evolutions are underway.
Service Water Pumps P-7A and P-7B are in service
Service Water Pump P-7C is in standby
Which of the following alarm combinations will require an IMMEDIATE reactor trip?
A. EK-1165, Non-critical Serv Water Lo Pressure (PRESSURE = 44psig) and
EK-1137, Service Water Pump P-7B Overload/trip
B. EK-1165, Non-critical Serv Water Lo Pressure (PRESSURE = 44psig) and
EK-0259, “Exciter Cooler Hi Temp”
C. EK-1131, Service Water Pump P-7A Overload/trip and EK-1137, Service Water
Pump P-7B Overload/trip
D. EK-1164, “Critical SERV Header “A” Lo Pressure (PRESSURE = 44psig) and
EK-1163, “Critical SERV Header “B” Lo Pressure (PRESSURE = 44psig)

A

B. EK-1165, Non-critical Serv Water Lo Pressure (PRESSURE = 44psig) and
EK-0259, “Exciter Cooler Hi Temp”

21
Q

Which of the following undesirable consequences would result from supplying the
engineered safeguards pumps seal cooling from both the CCW system and the
Service Water System simultaneously?
A. A reduced pressure would cause insufficient cooling flow to the pump seals.
B. Pumping the contents of the Component Cooling Water System directly to the lake.
C. The Component Cooling Water System would be diluted by the Service Water
System.
D. An overpressure condition would exist causing damage to the pump seals.

A

B. Pumping the contents of the Component Cooling Water System directly to the lake.

22
Q

CV-0826, CCW Hx (E-54B) Outlet valve has been coupled to the manual handwheel to
perform flow adjustments. During this evolution the plant receives an SIAS due to
containment high pressure.
Five minutes into the event SIRWT level drops to 2411 initiating RAS.
Given these conditions, describe the consequences of coupling/placing CV-0826 in
manual handwheel. CCW Hx Service Water Outlet CV-0826 .
A. fails to full open position.
B. opens to a preset “hardstop” to provide maximum cooling for containment spray
and safety injection recirculation flow.
C.fails AS IS because the motor is not copuled when in manual handwheel.
D. closes to prevent a CCW pump runout condition from occurring.

A

C.fails AS IS because the motor is not copuled when in manual handwheel

23
Q

During the daily surveillance of Lake Michigan temperature, the temperature was
recorded as 86° F.
In addition to being in Mode 3 in 6 hours, what additional action is required?
A. Mode 5 in 30 hours.
B. Mode 5 in 36 hours.
C. Mode 4 in 31 hours.
D. Mode 5 in 37 hours.

A

B. Mode 5 in 36 hours.

24
Q

Given the following:
• Plant is in Mode 1, today is 10/13, time is 0800.
• Service Water Pump P-7A has been inoperable for 72 hours (LCO 3.7.8.A.1)
a. When is the plant required to be in Mode 3 (time and date)?
b. When is the plant required to be in Mode 5 (time and date)?
Tech Spec 3.7.8

A

Tech Spec 3.7.8

25
Q

Given the following conditions:
Plant is in Mode 1.
Service Water Bay level is 567’8”.
Service Water temperature is 83°F.
Service Water Critical pressures are at 68 psig.
“A” & “C” Service Water pumps are inservice.
“B” Service Water pump in OFF because its standby feature is broken.
Which one of the following describes the Technical Specification implications, if any, of
this condition?
A. None, both the Service Water system and Ultimate Heat sink are OPERABLE.
B. Restore the Service Water train associated with P-7B to OPERABLE within 72
hours.
C. Place the plant in MODE 3 within 6 hours and Mode 5 within 36 hours.
D. Shutdown in accordance with LCO 3.0.3.

A

C. Place the plant in MODE 3 within 6 hours and Mode 5 within 36 hours

26
Q

Given the following conditions:
- The plant is in MODE 5.
- PCS is at 623’ with S/G nozzle dams installed.
- The Shutdown Cooling System is controlling PCS temperature at 103°F.
- T-91, Utility Water Storage Tank, batch release is in progress
- The batch release calculation assumed two Service Water Pumps in operation.
- Main Condenser East and West Waterboxes are open for installation of a
modification.
- Service Water Pumps P-7A and P-7B are in service.
- Service Water Pump P-7C is tagged out for bearing replacement.
- Both Cooling Tower Pumps P-39A/B are available, but not in service.
- The Canal Sample Pump is in service.
The Secondary AO reports that the basket strainer on P-7A discharge appears to be
clogging as indicated by differential pressure trending steadily upward. A crew brief is
held to discuss removing P-7A from service to disassemble and clean the basket
strainer.
For the above plant conditions, what are the implications of the proposed maintenance
on the SW pump basket strainer?
A. Plant will have Required Actions per LCO 3.4.8 PCS Loops - MODE 5, Loops not
filled. Terminate the batch release before stopping P-7A
B. Plant will have Required Actions per LCO 3.4.8 PCS Loops - MODE 5, Loops not
filled. Establish 15 minute periodic sampling of batch release flow
C. Plant will have Required Actions per LCO 3.7.8 Service Water System. Terminate
the batch release before stopping P-7A
D. Plant will have Required Actions per LCO 3.7.8 Service Water System. Start a
Dilution Water Pump before stopping P-7A

A

A. Plant will have Required Actions per LCO 3.4.8 PCS Loops - MODE 5, Loops not
filled. Terminate the batch release before stopping P-7A
Correct - The Service Water LCO does not apply below MODE 4. The batch
release requires that the dilution flow requirements be met. Securing a Service
water pump would violate these requirements and require that the batch be
secured while the release calculations are updated. In Mode 5 with the loops not
filled two SDC trains are required to be operable. To be operable each train
needs to have a separate SW pump. With only one pump operable only one train
could be considered operable.

27
Q

SRO ONLY
The plant is operating at 100%. An extended drought has caused increased lake
temperatures and lowering of the lake level at the intake bay. At 1600 lake level was
recorded at 567.75 ft with a lake temperature of 820F.
What actions are required in accordance with the Palisades Technical Specifications?
A. Technical Specifications requirements are met plant may continue with normal full
power operations.
B. Declare UHS inoperable due to exceeding max allowed lake temperature and be in
Mode 3 in 6 hours only.
C. Declare UHS inoperable due to exceeding min allowed lake level and be in Mode 3
in 6 hours and in Mode 4 in 30 hours.
D. Declare UHS inoperable due to exceeding min allowed lake level and be in Mode 3
in 6 hours and in Mode 5 in 36 hours.

A

D. Declare UHS inoperable due to exceeding min allowed lake level and be in Mode 3
in 6 hours and in Mode 5 in 36 hours
D. Correct: With lake level below minimum of 568.25 ft, UHS is inoperable and plant is required to be in
Mode 3 in 6 hours and in Mode 5 in 36 hours lAW TS 3.7.9

28
Q

The Plant is operating at 100%.
During the daily surveillance of Lake Michigan temperature, the temperature was
recorded as Br F. The Shift Manager immediately declared the Ultimate Heat Sink
inoperable.
What actions are required in accordance with the Palisades Technical Specifications?
A. Be in Mode 3 in 6 hours only.
B. Be in Mode 4 in 24 hours only.
C. Be in Mode 3 in 6 hours and in Mode 4 in 30 hours.
D. Be in Mode 3 in 6 hours and in Mode 5 in 36 hours.

A

D. Be in Mode 3 in 6 hours and in Mode 5 in 36 hours.D. Correct: With UHS temperature above 85 degrees F, required to be in Mode 3 in 6 hours and in Mode
5 in 36 hours lAW TS 3.7.9.

29
Q

(SRO ONLY) Refer to the following valve description list:
• CV-1359, Non-Critical Service Water Isolation
• CV-0824, Containment Air Cooler Return
• CV-0847, Containment Air Cooler Supply
In order to provide 100% of the required service water system post-accident cooling
capability with only ONE (1) service water pump operating, which of the following
describes the minimum requirement for meeting 100% of SWS post accident cooling
CV-1359 CV-0824 CV-0847
A. OP INOP OP
B. INOP OP OP
C. OP INOP INOP
D. OP OP OP

A

A. OP INOP OP

30
Q

All of the following are automatic actions that occur in the Service Water System
(SWS) after receipt of an Safety Injection Actuation Signal, EXCEPT:
A. All three SWS pumps receive a start signal
B. Non-critical header isolation valve closes
C. VHX-1 Containment Air Cooler High Capacity Outlet Valve opens
D. VHX-4 Containment Air Cooler High Capacity Outlet Valve closes.

A

D. VHX-4 Containment Air Cooler High Capacity Outlet Valve closes

31
Q

Plant conditions resulting from an Excessive Feedwater Event caused a Reactor trip.
SIAS actuated on Pressurizer Low Pressure. Offsite Power is available.
Which of the following conditions SHOULD NOT occur?
A. All service water pumps start.
B. CV-1359, Non-Critical Header Isolation Valve isolates.
C.High capacity service water outlet valves on the CCW heat exchanger open to the
hard stop position.
D. Containment air cooler #4 high capacity service water outlet valve opens.

A

C.High capacity service water outlet valves on the CCW heat exchanger open to the
hard stop position.

32
Q

Describe the automatic response of the Service Water System to a RAS.

A

·CCW Heat Exchanger high capacity SW outlet CVs open to a hard stop position
·CCW Heat Exchanger Outlet SW TCVs close

33
Q

Given the following plant conditions:
• During power operations a Large Break Loss of Coolant Accident (LOCA) has
occurred.
• A Safety Injection has occurred as designed.
• A Containment High Pressure (CHP) also occurred as designed.
• 30 minutes later the Safety Injection & Refueling Water Tank level is at 1.8%.
What is the excited response of the highlighted valves (CV-0823 SW OUTLET A CCW
HX and CV-0826 SW OUTLET B CCW HX) and what is the reason for that response?
A. Failed AS IS to provide a gradual cooling of the containment sump fluid.
B. Modulating to provide a gradual cooling of the containment sump fluid.
C. Opened to a preset hardstop to provide maximum cooling for containment spray
and safety injection recirculation flow.
D. Closed to a preset hardstop to ensure maximum cooling water flow is maintained
for the Containment Air Coolers

A

C. Opened to a preset hardstop to provide maximum cooling for containment spray
and safety injection recirculation flow

34
Q

Which one of the following conditions will result in CV-1359, Non-Critical Service Water
Isolation, going CLOSED? (Consider each condition separately.)
A. A fuel element failure results in Containment radiation reaching 12R1Hr.
B. A steam line break results in Containment pressure rising to 4.8 psig.
C. Service Water Bay level lowers to 572 feet.
D. A turbine trip occurs.

A

B. A steam line break results in Containment pressure rising to 4.8 psig

35
Q

When a Safety Injection Actuation signal is generated, CV-0869, Containment Air
Cooler #4 Service Water Inlet, goes closed. Why does this valve close?
A. To ensure there is adequate Service Water to the other three coolers during a loss
of Bus 10.
B. To ensure there is adequate Service Water to the other three coolers during a loss
of Bus 1C.
C. To isolate Containment Air Cooler #4 since it is not rated for use in accident
conditions.
O. To minimize the potential for vapor binding of the SW piping inside containment.

A

B. To ensure there is adequate Service Water to the other three coolers during a loss
of Bus 1C.

36
Q

Which one of the following conditions will result in CV-1359, Non-Critical Service Water
Isolation, automatically closing? (Consider each condition separately.)
A. A fuel element failure results in Containment radiation reaching 12R1Hr.
B. A steam line break results in Containment pressure rising to 4.8 psig.
C. Service Water Bay level lowers to 568 feet.
D. Anticipated Transient Without a Scram (ATWS) occurs.

A

B. A steam line break results in Containment pressure rising to 4.8 psig.

37
Q

When a Safety Injection Actuation signal is generated the Service Water inlet isolation
valve CV-0869, for Containment Air Cooler #4 goes closed. Why does this valve
close?
A. To ensure there is adequate Service Water to the other three coolers during a loss
of Bus 10
B. To ensure there is adequate Service Water to the other three coolers during a loss
of Bus 1C
C. To isolate Containment Air Cooler #4 since it is not rated for use in accident
conditions
D. To minimize the potential for vapor binding of the SW piping inside containment

A

B. To ensure there is adequate Service Water to the other three coolers during a loss
of Bus 1C B) Correct - This train doesn’t rely on SW. It isolates and raises flow to the other
coolers

38
Q

Given the following plant conditions:
During power operations a Large Break Loss of Coolant Accident (LOCA) has
occurred.
A Safety Injection has occurred as designed.
A Containment High Pressure (CHP) also occurred as designed.
30 minutes later the Safety Injection & Refueling Water Tank level is at 1.8%.
(Refer to the attached drawing.)
What is the expected response of the highlighted valves (CV-0823 and CV-0826) and
what is the reason for that response?
A. Failed AS IS to provide a gradual cooling of the containment sump fluid.
B. Modulating to provide a gradual cooling of the containment sump fluid
C.Opened to a preset hardstop to provide maximum cooling for containment spray
and safety injection recirculation flow
D. Closed to a preset hardstop to ensure maximum cooling water flow is maintained
for the Containment Air Coolers

A

C.Opened to a preset hardstop to provide maximum cooling for containment spray
and safety injection recirculation flow c. CORRECT - Provides maximum service water flow and cooling to the CCW
Hxs.

39
Q

Which ONE of the following statements describes why the following occurs on a
Recirculation Actuation Signal?
- Component Cooling Water (CCW) Heat Exchanger (Hx) High Capacity Outlets,
CV-0823 and CV-0826, automatically open to hardstop position, and
- CCW Hx Outlet Temperature Control Valves automatically close.
A. To ensure LPSI pumps have sufficient cooling
B. To prevent CCW pump runout
C. To ensure the Shutdown Cooling Hxs have sufficient cooling
D. To ensure the Charging Pumps have sufficient cooling

A

C. To ensure the Shutdown Cooling Hxs have sufficient cooling Per lesson plan, this is to ensure critical CCW loads have sufficient cooling. Chg
Pumps are not a critical load. LPSI Pumps are tripped by RAS. Runout is not
technically sound.

40
Q

Which ONE of the following statements describes why the following occurs on a
Recirculation Actuation Signal?
- Component Cooling Water (CCW) Heat Exchanger (Hx) High Capacity Outlets,
CV-0823 and CV-0826, automatically open to hardstop position, and
- CCW Hx Outlet Temperature Control Valves automatically close.
A. To ensure LPSI pumps have sufficient cooling
B. To prevent CCW pump runout
C. To ensure the Shutdown Cooling Hxs have sufficient cooling
D. To ensure the Charging Pumps have sufficient cooling

A

C. To ensure the Shutdown Cooling Hxs have sufficient cooling

41
Q

The Plant is operating at 100%.
During the daily surveillance of Lake Michigan temperature, the temperature was
recorded as sr F. The Shift Manager immediately declared the Ultimate Heat Sink
inoperable.
What actions are required in accordance with the Palisades Technical Specifications?
A. Be in Mode 3 in 6 hours only.
B. Be in Mode 4 in 24 hours only.
C. Be in Mode 3 in 6 hours and in Mode 4 in 30 hours.
D. Be in Mode 3 in 6 hours and in Mode 5 in 36 hours.

A

D. Be in Mode 3 in 6 hours and in Mode 5 in 36 hours.

42
Q

Service water pumps P-7A & 7B are running with service water header pressures at 76
psig. Due to an electrical fault, the closing coil fuses for Service Water Pump P-7C
have deenergized.
Assuming all bulbs are good, what Control Room indication could be used to confirm
the above condition?
A. The AMBER light will not illimuninate when placing P-7C in Standby
B. P-7C would trip if it was in service
C. The GREEN light above the handswitch is ON.
D. THe AMBER light remains ON if P-7C is taken out of standby..

A

A. The AMBER light will no illimuninate when placing P-7C in Standby

43
Q

CV-0826, CCW Hx (E-54B) Outlet valve has been coupled to the manual handwheel to
perform flow adjustments. During this evolution the plant receives an SIAS due to
containment high pressure.
Five minutes into the event SIRWT level drops to 24” initiating RAS.
Given these conditions, describe the consequences of coupling/placing CV-0826 in
manual handwheel. CCW Hx Service Water Outlet CV-0826 .
A. fails to full open position.
B. opens to a preset “hardstop” to provide maximum cooling for containment spray
and safety injection recirculation flow.
C.fails AS IS because the motor is not copuled when in manual handwheel.
D. closes to prevent a CCW pump runout condition from occurring.

A

C.fails AS IS because the motor is not copuled when in manual handwheel.

44
Q

The plant is on day 30 of a refueling outage. Due to main generator maintenance the
Non-critical Service Water header has been isolated.
• Service Water Pumps P-7A and P-7C are in-service.
• Service Water Pump P-7B is in standby.
• Service water header pressure is above 80 psig.
Due to the low flow conditions the CRS directs the operator to secure P-7C. When
Service Water Pump P-7C is secured critical service water header pressure lowers to
45 psig. Service Water Pump P-7B did not start.
Is this the correct service water pump response and why?
A. No, P-7B should have started at 40 psig discharge pressure on either of the other
pumps.
B. No, P-7B should have started at 45 psig header pressure.
C. Yes, P-7B should not start since P-7C was manually secured.
D. Yes, P-7B should not start until header pressure reaches 40 psig.

A

A. No, P-7B should have started at 40 psig discharge pressure on either of the other
pumps.

45
Q

Which one of the following describes the position of the Containment Air Cooler
Service Water inlet and outlet valves for a complete loss of Instrument Air and why?
A. VHX-4 inlet and outlet are closed; VHX-1, 2, 3 inlet and outlet are open. This
provides maximum cooling on a loss of instrument air.
B. VHX-4 inlet and outlet are closed; VHX-1, 2, 3 inlet and outlet are open. VHX-4
isolates because it is not safety-related. VHX-1, 2, 3 valves have nitrogen backup.
C. VHX-4 inlet is closed; VHX-1, 2, 3 inlet and outlet and VHX-4 outlet are open.
VHX-4 inlet closes because it is not safety-related. VHX-1, 2, 3 and VHX-4 outlet
have nitrogen backup.
D. VHX-4 inlet is closed; VHX-1, 2, 3 inlet and outlet and VHX-4 outlet are open. This
provides maximum cooling on a loss of instrument air.

A

Will have to look this up. will change later.

46
Q

Given the following plant conditions:
During power operations a Large Break Loss of Coolant Accident (LOCA) has
occurred.
A Safety Injection has occurred as designed.
A Containment High Pressure (CHP) also occurred as designed.
30 minutes later the Safety Injection & Refueling Water Tank level is at 1.8%.
What is the expected response of CCW HX E-54A SW Outlet CV-0823 and CCW HX
E-54B SW OutletCV-0826, and what is the reason for that response?
A. Failed AS IS to provide gradual cooling of the containment sump fluid.
B. Modulating to provide a gradual cooling of the containment sump fluid
C. Opened to a preset hardstop to provide maximum cooling for containment spray and safety injection recirculation flow.
D. Closed to preset hardstop to ensure maximum cooling water flow is maintained for Containment Air Coolers.

A

C. Opened to a preset hardstop to provide maximum cooling for containment spray and safety injection recirculation flow

47
Q

Which one of the following conditions will result in CV-1359, Non-Critical Service Water
Isolation, automatically closing? (Consider each condition separately.)
A. A fuel element failure results in Containment radiation reaching 12R/Hr.
B. A steam line break results in Containment pressure rising to 4.8 psig.
C. Service Water Bay level lowers to 568 feet.
D. Anticipated Transient Without a Scram (ATWS) occurs

A

B. A steam line break results in Containment pressure rising to 4.8 psig.