Sept 2023 25 Q&A Flashcards
- Explain the concept of “time at large” in construction contracts.
• Time at large means that the main contractor has not fulfilled their obligation to meet practical completion, and no certificate of non-completion has been issued. It implies no set completion date and the obligation to complete within a reasonable time.
- Define frustration in contract law.
• Frustration occurs when events or circumstances beyond the control of both parties change the contractual obligations, making it impossible or illegal to fulfill them.
- How does a contract under deed differ from a contract underhand?
• A contract under deed is signed by the parties and a witness, traditionally authenticated by a seal. A contract underhand is only signed by the parties, with no witnesses or seal.
- What steps would you take if the client advised that liquidated damages were to be £100,000 per week?
• Verify whether the liquidated damages are based on a genuine pre-estimate of financial loss. Explain that they should be substantiated and cannot be punitive.
- What is the purpose of liquidated damages in a contract?
• Liquidated damages serve as a genuine pre-estimate of the likely loss incurred by the employer if the completion date is not met.
- What documents must be in place for liquidated damages to be deducted?
• A non-completion certificate, a payless notice, and other documentation or notices stipulated within the contract.
- Can liquidated damages be deducted even if the employer suffered no loss or damage?
• Yes, liquidated damages can be deducted at the value stated in the contract, regardless of whether the employer suffered damages.
- Explain the concept of the “defects liability period” in construction contracts.
• The defects liability period is a duration, typically 52 weeks after completion, during which the contractor is responsible for rectifying any defects arising from materials or workmanship not in accordance with the contract.
- When is a bespoke contract typically used in construction projects?
• Bespoke contracts are used for major projects with unique obligations, often requiring specialist advisors to draft specific contract conditions.
- What are the advantages of using standard forms of contracts over bespoke contracts in construction projects?
• Standard forms offer clarity, consistency, allocation of risk, time savings, established case law, and reduced preparation time.
- What are the disadvantages of using standard forms of contracts compared to bespoke contracts in construction?
• Standard forms may not always allocate risk appropriately, may not suit the project’s needs, and can lead to disputes if not tailored correctly.
- In what situations would you use a bespoke contract instead of a standard form in construction?
• Bespoke contracts are used for complex projects with unique requirements or when specialist advisors can draft specific contract conditions.
- What is a “retention of title” clause in a construction contract?
• A retention of title clause allows a subcontractor or supplier to retain ownership of materials until they are paid for by the main contractor.
- What are collateral warranties in construction contracts, and why are they used?
• Collateral warranties create contractual relationships between the main parties of a contract and external third parties who have a financial interest in the project. They are used to provide third parties with contractual rights.