Sedimentation Flashcards
1
Q
Solid flux
A
- batch solid flux = product of settling velocity and biomass concentration X
- continuous solid flux = sum of batch solid flux and underflow (or bulk) flux
- proper operation requires that:
> incoming flux G’ of solids are removed via the underflow (= Gb (flux due to settling) + Gu (flux due to drain))
> incoming flux G’ (horizontal line) has to be situated below the (Gb + Gu) curve
2
Q
Settling Zones
A
Picture
3
Q
Settler Design: Sludge Loading/Thickening Criterion
A
- the sludge loading rate of a settler has to be such that a settler is able to:
> treat a sufficient amount of suspended solids = remove the incoming solids via the underflow
> deliver a sludge at a certain (pre-defined high) sludge concentration) - to determine the area needed, the limiting solids Gmin (approximately based of field experiments) of the clarifier is taken from G
- equation
- Yoshlokas graphic mehtod:
> for a selected value of XR and starting from the point (XR,0) a tangent is drawn to the batch solid flux curve
> the intersection with the ordinate = Gmin - both Xr and X are control variable to be chosen properly during the dimensioning of activated sludge tanks
- recycle ration can be approximated by: r = Qr/Q = Cx/Cx,r - Cx where Cx,r is the total ss conversion to organic SS needed (Cx,r = 1000/SVI)
4
Q
Settler Design: Hydraulic Loading/Effluent Criterion
A
- high clarification degree
- no solids dragged away with the overflow
q0 = Qc/A = Qc*(1-w)/A
5
Q
Secondary Parameters of Settler Design
A
– for the hydraulic stability of the water volume
– to eliminate dead zones
> rectangular tanks (primary settling) L/H = 20 – 35
> circular tanks (secondary settling) diameter/H = 15 – 25
– sludge retention times in the clarifiers should be limited from 2 to 6 h to avoid denitrification (if there are still organic components and nitrates in the water) or P-release (if there are still organic components in the water that could induce P-release in anaerobic conditions (= first phase of “P-removal”)