SectionFormat - Multiple-Choice Flashcards
All of the following are in ACTION SUBMITTALS /
INFORMATIONAL SUBMITTALS except:
A. Product Data
B. Shop Drawings
C. Samples
D. Certifications
E. Test and Evaluation Reports
F. Manufacturers’ Instructions
G. Manufacturer Reports
H. Qualification Statements
D. Certifications
Certifications are in QUALITY ASSURANCE
Certificates are in ACTION SUBMITTALS / INFORMATIONAL SUBMITTALS
ACTION SUBMITTALS /
INFORMATIONAL SUBMITTALS
- Product Data
- Shop Drawings
- Samples
- Certificates
- Delegated Design Submittals
- Test and Evaluation Reports
- Manufacturers’ Instructions
- Source Quality Control Submittals
- Field [OR] Site Quality Control Submittals
- Manufacturer Reports
- Sustainable Design Submittals
- Special Procedure Submittals
- Qualification Statements
QUALITY ASSURANCE
- Regulatory Agency Sustainability Approvals
- Qualifications
- Manufacturers
- Suppliers
- Fabricators
- Installers / Applicators / Erectors
- Testing Agencies
- Licensed Professionals
- Certifications
- Sustainability Standards Certifications
- Preconstruction Testing
- Field [OR] Site Samples
- Mock-ups
All of the following are in QUALITY ASSURANCE except:
A. Regulatory Agency Sustainability Approvals
B. Qualifications
C. Certifications
D. Sustainability Standards Certifications
E. Preconstruction Testing
F. Field [OR] Site Samples
G. Mock-ups
H. Regulatory Requirements
H. Regulatory Requirements.
[SYSTEMS] / [ASSEMBLIES] /
[MANUFACTURED UNITS] / [EQUIPMENT] /
[COMPONENTS] / [PRODUCT TYPES] /
[MATERIALS] / [USER-DEFINED HEADING]
Description
- Regulatory Requirements
- Sustainability Characteristics
QUALITY ASSURANCE
- Regulatory Agency Sustainability Approvals
- Qualifications
- Manufacturers
- Suppliers
- Fabricators
- Installers / Applicators / Erectors
- Testing Agencies
- Licensed Professionals
- Certifications
- Sustainability Standards Certifications
- Preconstruction Testing
- Field [OR] Site Samples
- Mock-ups
All of the following are in MAINTENANCE MATERIAL SUBMITTALS except (pick all that apply):
A. Spare Parts
B. Product Options
C. Extra Stock Materials
D. Tools
E. Operation and Maintenance Data
B. Product Options
E. Operation and Maintenance Data
MAINTENANCE MATERIAL
SUBMITTALS
- Spare Parts
- Extra Stock Materials
- Tools
CLOSEOUT SUBMITTALS
- Maintenance Contracts
- Operation and Maintenance Data
- Bonds
- Warranty Documentation
- Record Documentation
- Sustainable Design Closeout Documentation
- Software
All of the following are in CLOSEOUT SUBMITTALS except (pick all that apply):
A. Maintenance Contracts
B. Operation and Maintenance Data
C. Bonds
D. Field [OR] Site Samples
E. Warranty Documentation
F. Mock-ups
G. Record Documentation
H. Sustainable Design Closeout Documentation
I. Software
D. Field [OR] Site Samples
F. Mock-ups
CLOSEOUT SUBMITTALS
- Maintenance Contracts
- Operation and Maintenance Data
- Bonds
- Warranty Documentation
- Record Documentation
- Sustainable Design Closeout Documentation
- Software
All of the following are in PRICE AND PAYMENT PROCEDURES except:
A. Allowances
B. Unit Prices
C. Stipulated Sum
D. Alternates [OR] Alternatives
E. Measurement and Payment
C. Stipulated Sum
All of the following are in SOURCE QUALITY CONTROL except:
A. Tests and Inspections
B. Evaluation and Assessment
C. Non-Conforming Work
D. Manufacturer Services
E. Coordination of Other Tests and Inspections
B. Evaluation and Assessment
EXAMINATION
- Verification of Conditions
- Preinstallation Testing
- Evaluation and Assessment
All of the following are in [SYSTEMS] / [ASSEMBLIES] / [MANUFACTURED UNITS] / [EQUIPMENT] / [COMPONENTS] / [PRODUCT TYPES] / [MATERIALS] / USER-DEFINED HEADING except:
A. Manufacturers
B. Description
C. Performance / Design Criteria
D. Operation
E. Materials
F. Assembly [OR] Fabrication
G. Mixes
H. Finishes
I. Demonstration
I. Demonstration.
All of the following are in DELIVERY, STORAGE, AND HANDLING except:
A. Delivery and Acceptance Requirements
B. Storage and Handling Requirements
C. Demolition / Removal
D. Packaging Waste Management
C. Demolition / Removal
All of the following are in ERECTION / INSTALLATION / APPLICATION
/ [USER-DEFINED PROCESS] except:
A. Surface Preparation
B. Special Techniques
C. Interface with Other Work
D. Systems Integration
E. Tolerances
A. Surface Preparation
All of the following are in FIELD [OR] SITE QUALITY CONTROL except:
A. Field [OR] Site Tests and Inspections
B. Non-Conforming Work
C. Manufacturer Services
D. Coordination of Other Tests and Inspections
D. Coordination of Other Tests and Inspections