Section L: Execution and Control Flashcards

1
Q

production activity control (PAC)

A

production activity control (PAC)

Includes scheduling, implementation, and capacity control. PAC, along with purchasing, are execution activities. PAC transforms the in-house manufacturing requirements of the material requirements plan into finished goods and services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What’s the end part of Material Requirements Planning?

A

The end of the material requirements planning process involves the material planner providing the production coordinator with planned orders to be released after verifying that capacity is available using capacity requirements planning (CRP).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What’s the first step of the Production Coordinator?

A

The production coordinator starts by scheduling the start and finish dates of these orders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Operations sequencing is used to dispatch jobs according to their current priority level based on certain rules. What are those methods?

A

Operations sequencing is used to dispatch jobs according to their current priority level based on certain rules, including the following methods:

  • First come, first served (FCFS)
  • Earliest job due date (EDD)
  • Earliest operation due date (ODD)
  • Shortest process time (SPT)
  • Critical ratio
  • Slack time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How does Capacity control differ based on whether intermittent or flow process types are being used?

A

Capacity control differs depending on whether intermittent or flow process types are being used.

For intermittent processes (work center or batch), capacity control uses input/output control to monitor and control inputs to and outputs from work centers in order to control backlogs (queues) and thus WIP inventory levels.

In flow (line or continuous) process types, capacity control uses flow control to adjust the rate of the process as needed. Lean may also use flow control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

theory of constraints (TOC)

A

theory of constraints (TOC)

A holistic management philosophy developed by Dr. Eliyahu M. Goldratt, based on the principle that complex systems exhibit inherent simplicity.

Even a very complex system comprising thousands of people and pieces of equipment can have, at any given time, only a very, very small number of variables—perhaps only one, known as a constraint—that actually limit the ability to generate more of the system’s goal.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How did TOC differ from conventional thinking?

A

Conventional thinking at the time was additive, meaning that, due to process complexity, streamlining any part of a system where improvements could be found would be beneficial to total system output.

However, according to TOC, real gains in efficiency can be made only by finding the part of the system that constrains total output—the weakest link—and making efficiency improvements to that area and only that area.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

constraint

A

constraint

Any element or factor that prevents a system from achieving a higher level of performance with respect to its goal. Constraints can be physical, such as a machine center or lack of material, but they can also be managerial, such as a policy or procedure.

A constraint is a limit on throughput, or the rate of production, not on inventory or production.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

bottleneck

A

bottleneck

A facility, function, department, or resource whose capacity is less than the demand placed upon it. For example, a bottleneck machine or work center exists where jobs are processed at a slower rate than they are demanded.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Throughput

A

Throughput

The rate at which the system generates “goal units.” Because throughput is a rate, it is always expressed for a given time period—such as per month, week, day, or even minute. If the goal units are money, throughput is an amount of money per time period. In that case, throughput is calculated as revenues received minus totally variable costs divided by units of the chosen time period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Cycle time

A

Cycle time

1) In industrial engineering, the time between the completion of two discrete units of production. For example, the cycle time of motors assembled at a rate of 120 per hour is 30 seconds.
2) In materials management, the length of time from when material enters a production facility until it exits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the 3 types of constraints?

A

The 3 different types of constraints:

  • physical constraints
  • capacity-constrained resources (CCR)
  • behavior-based constraints (sometimes called “non-constraints”)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Physical constraints

A

Physical constraints are related to resources (equipment, labor, materials), or they are market constraints.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

capacity-constrained resource (CCR)

A

capacity-constrained resource (CCR)

A resource that is not a constraint but will become a constraint unless scheduled carefully. Any resource that, if its capacity is not carefully managed, is likely to compromise the throughput of the organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Behavior-based constraints

A

Behavior-based constraints are generated by persons and management policies.

This can include administrative or other unnecessary steps that take time away from performing necessary process steps at a bottleneck area. It could be personnel that do not know they are working at a bottleneck work center and unnecessarily delay the process, or it could be a management decision not to spend time on improvement because of past failures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Principles of Bottleneck Management

How should inputs be provided to a bottleneck area?

A

The rate at which a bottleneck can process work is the rate at which its inputs should be provided to avoid increasing WIP inventory before it. Work centers that depend on the output of the bottleneck should be scheduled to work at the rate set by the bottleneck.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Principles of Bottleneck Management

The capacity of the production depends on the capacity of what?

A

The capacity of the production process depends on the capacity of the bottleneck, so breakdowns or slowdowns in this area directly reduce system throughput.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Principles of Bottleneck Management

Why is a setup at a bottleneck work center an opportunity cost?

A

Priority and capacity are interrelated, meaning that priority (demand) for different types of units promotes more setups, but each new setup at a bottleneck work center is an opportunity cost because it takes time away from processing, thus reducing utilization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Principles of Bottleneck Management

How should output from a bottleneck area be provided?

A

Output from bottleneck areas should be provided to the next work center(s) in smaller lots than a full batch size (in a split lot). The amount to move might be the amount finished each day or even more often, depending on materials handling costs. This smaller lot is called a split lot or a transfer batch.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Principles of Bottleneck Management

How should capacity constrained resources be scheduled?

A

The goal should be to maximize the total throughput of the plant, in other words, to maximize the revenue the plant produces by balancing the flow of units produced to maximize the amount of demand that can be satisfied. This means scheduling capacity-constrained resources to avoid bottlenecks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

split lot

A

split lot as follows: A manufacturing order quantity that has been divided into two or more smaller quantities, usually after the order has been released. The quantities of a split lot may be worked on in parallel, or a portion of the original quantity may be sent ahead to a subsequent operation to be worked on while work on the remainder of the quantity is being completed at the current operation. The purpose of splitting a lot is to reduce the lead time of the order.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Principles of non-Bottleneck Management

What is the principle of improving nonbottleneck capacity?

A

Nonbottleneck capacity improvements do not improve total capacity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Principles of non-Bottleneck Management

How to determine the rate of nonbottleneck areas?

A

Nonbottleneck areas set their maximum utilization not based on their potential but on the rate determined at the bottleneck. This means that nonbottleneck areas may be idle at times. However, when they are run, they should still be run using proper efficiency, quality, and cost principles (it runs at full speed when running).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Principles of non-Bottleneck Management

Does 100% utilization in a nonbottleneck area make sense?

A

Using a nonbottleneck area 100 percent of the time does not result in 100 percent utilization, since it would simply build up more and more WIP inventory and eventually need to be stopped.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Drum-buffer-rope (DBR)

A

Drum-buffer-rope (DBR)

The theory of constraints method for scheduling and managing operations that have an internal constraint or capacity-constrained resource.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Drum schedule

A

Drum schedule

The detailed production schedule for a resource that sets the pace for the entire system.

The drum schedule must reconcile the customer requirements with the system’s constraint(s).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Buffer

A

Buffer

In the theory of constraints, buffers can be time or material and support throughput and/or due date performance.

Buffers can be maintained at the constraint, convergent points (with a constraint part), divergent points, and shipping points.

The buffer, or time buffer, is an amount of inventory maintained before the constraint to ensure that the constraint never stops due to a lack of inputs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

time buffer

A

The Dictionary defines a time buffer as “protection against uncertainty that takes the form of time.”

The duration of the time buffer will be based on the amount of variability in production or purchasing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

The rope metaphor.

A

The rope is like a demand-pull signal, only, in this case, the signal is the throughput rate at the constraint. One cannot push a rope; one can only pull it.

Imagine that all WIP inventory is attached to a long rope and that the constraint process is pulling on the rope at the rate needed to match its production, neither faster nor slower.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Market Demand as Constraint

A

There are times when the constraint is not internal, for example, when there is insufficient demand for a company’s product or service—i.e., demand is far below the system’s capacity and the market is constraining the system’s throughput. This is an external market constraint.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Considerations of Market Constraints

A

Considerations of Market Constraints

  • The drum is at shipping and is based on market needs.
  • The rope connects the drum to the material release point (as in conventional DBR).
  • The time buffer is only at shipping. This will result in a small bank of finished goods in front of shipping, which allows for a greater likelihood that the company will meet its order due dates.
  • The S-DBR assumes that all resources have sufficient protective capacity in the event of a higher-than-expected market demand.
  • The workflow needs to be managed to match the slowest area in the workflow.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

The theory of constraints contains a five-step cyclical process, called the five focusing steps.

A

In the theory of constraints, a process to continuously improve organizational profit by evaluating the production system and market mix to determine how to make the most profit using the system constraint.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

five focusing steps

A
  1. Identify the constraint.
    Determine throughput rates and demand rate.
  2. Exploit the constraint. Maximize utilization, partly through buffers.
  3. Subordinate everything else to the constraint. The top priority is effective utilization of the constraint.
  4. Elevate the constraint. Increase the capacity of the constraint.
  5. Once the constraint is relieved, identify the new constraint. There is always a new constraint, so the process repeats.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

How to identify if sales is the constraint?

A

If no work centers are working at full capacity and all orders are being released and completed on time, then sales is the constraint. If

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

How to identify the constraint in a linear process?

A

Identifying the Constraint in a Linear Process is straightforward.

The work center with the lowest production rate is the constraint.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

productive capacity

A

productive capacity as follows: In the theory of constraints, the maximum of the output capabilities of a resource (or series of resources) or the market demand for that output for a given time period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

buffer management as

A

buffer management

In the theory of constraints, a process in which all expediting in a shop is driven by what is scheduled to be in the buffers (constraint, shipping, and assembly buffers).

By expediting this material into the buffers, the system helps avoid idleness at the constraint and missed customer due dates. In addition, the reasons items are missing from the buffer are identified, and the frequency of occurrence is used to prioritize improvement activities.

38
Q

Constraint buffer

A

Constraint buffer. This is often set as the total processing time from when raw materials are released to the gateway operation until they reach the constraint.

39
Q

Assembly buffer

A

Assembly buffer. This duration will often be from the release of raw materials to a process not passing through the constraint but will eventually be combined with materials that did pass through the constraint.

40
Q

Shipping buffer

A

Shipping buffer. This duration will often be from when materials exit the constraint until they reach the shipping location.

41
Q

store

A

store

a storage point located upstream of a work station, intended to make it easier to see customer requirements.

42
Q

Protective capacity

A

Protective capacity

The resource capacity needed to protect system throughput—ensuring that some capacity above the capacity required to exploit the constraint is available to catch up when disruptions inevitably occur.

Nonconstraint resources need protective capacity to rebuild the bank in front of the constraint or capacity-constrained resource (CCR) and/or on the shipping dock before throughput is lost and to empty the space buffer when it fills.

43
Q

Idle capacity

A

Idle capacity

The available capacity that exists on nonconstraint resources beyond the capacity required to support the constraint.

Idle capacity has two components: protective capacity and excess capacity.

44
Q

Throughput accounting

A

Throughput accounting

A management accounting method based on the belief that because every system has a constraint that limits global performance, the most effective way to evaluate the impact that any proposed action will have on the system as a whole is to look at the expected changes in the global measures of throughput, inventory, and operating expense.

45
Q

Theory of constraints (TOC) accounting

A

Theory of constraints (TOC) accounting

A cost and managerial accounting system that accumulates costs and revenues into three areas—

throughput, inventory, and operating expense.

Does not create incentives (through allocation of overhead) to build up inventory. Is considered to provide a truer reflection of actual revenues and costs than traditional cost accounting, and is closer to a cash flow concept of income than is traditional accounting.

46
Q

What is Throughput Accounting’s highest priority?

A

Throughput accounting’s highest priority is to maximize throughput in terms of total monetary value.

47
Q

How is Net Profit calculated?

A

Net Profit = Thoroughput - Operating Expenses

48
Q

How is Thoroughput calculated?

A

Thoroughput = Sales Revenue - True Variable Costs

49
Q

operating expense

A

operating expense as “all the money an organization spends in generating goal units.”

50
Q

Critical chain

A

Critical chain

The longest sequence of dependent events through a project network, considering both technical and resource dependencies in completing the project.

The critical chain is the constraint of a project.

51
Q

Critical chain method

A

Critical chain method

In the theory of constraints, a network planning technique for the analysis of a project’s completion time, used for planning and controlling project activities.

The critical chain, which determines project duration, is based on technological and resource constraints. Strategic buffering of paths and resources is used to increase project completion success.

52
Q

Critical path method (CPM)

A

Critical path method (CPM)

A network planning technique for the analysis of a project’s completion time used for planning and controlling the activities in a project.

By showing each of these activities and their associated times, the critical path, which identifies those elements that actually constrain the total time for the project, can be determined.

53
Q

production activity control (PAC)

A

production activity control (PAC)

The function of routing and dispatching the work to be accomplished through the production facility and of performing supplier control.

PAC encompasses the principles, approaches, and techniques needed to schedule, control, measure, and evaluate the effectiveness of production operations.

54
Q

What are the objectives of PAC?

A

Production activity control has the following objectives:

  • Execute the orders authorized in the master production schedule and the material requirements plan.
  • Optimize the use of resources, including materials, tooling, equipment, staff, and information.
  • Provide availability information to production coordinators so they can ensure the availability of these resources when they are needed.
  • Provide information on work-in-process inventories so planning/operations can maintain the levels set by inventory policy.
  • Maintain customer service at the targeted level.
55
Q

Inputs to PAC

A
  • MRP (shop order qts & due dates)
  • Item Master Files (part #, description, qty)
  • Routing files (operations req’d, sequence of work)
  • Work center Files
  • Shop order files
56
Q

final assembly schedule (FAS)

A

final assembly schedule (FAS) as follows: A schedule of end items to finish the product for specific customers’ orders in a make-to-order or assemble-to-order environment. It is also referred to as the finishing schedule because it may involve operations other than the final assembly; also, it may not involve assembly (e.g., final mixing, cutting, packaging). The FAS is prepared after receipt of a customer order as constrained by the availability of material and capacity, and it schedules the operations required to complete the product from the level where it is stocked (or master scheduled) to the end-item level.

57
Q

job shop scheduling

A

job shop scheduling , which the Dictionary defines as the production planning and control techniques used to sequence and prioritize production quantities across operations in a job shop.

58
Q

Scheduling Objectives

A

Scheduling Objectives Scheduling aims to ensure that delivery dates are met while using manufacturing resources as efficiently and effectively as possible.

59
Q

Scheduling?

A

Scheduling involves establishing the start and completion dates for each operation required to process an order.

60
Q

Backward scheduling

A

Backward scheduling works backward from the due date to find the latest time the operation could start.

Using backward schedules minimizes WIP inventory levels, because orders are completed and resources are committed just when they are needed, but it leaves little room for error.

Because make-to-stock environments already have high inventory costs, backward scheduling is often used to keep inventory and other resource costs as low as possible.

61
Q

forward scheduling

A

forward scheduling

A scheduling technique where the scheduler proceeds from a known start date and computes the completion date for an order, usually proceeding from the first operation to the last.

Dates generated by this technique are generally the earliest start dates for operations.

62
Q

infinite loading

A

infinite loading

calculation of the capacity required at work centers in the time periods required regardless of the capacity available to perform this work.

63
Q

finite loading

A

finite loading

Assigning no more work to a work center than the work center can be expected to execute in a given time period. The specific term usually refers to a computer technique that involves calculating shop priority revisions in order to level load operation by operation.

64
Q

finite forward scheduling

A

finite forward scheduling

An equipment scheduling technique that builds a schedule by proceeding sequentially from the initial period to the final period while observing capacity limits.

A Gantt chart may be used with this technique.

65
Q

overlapped schedule

A

overlapped schedule as follows: A manufacturing schedule that “overlaps” successive operations. Overlapping occurs when the completed portion of an order at one work center is processed at one or more succeeding work centers before the pieces left behind are finished at the preceding work centers.

66
Q

Shop order packet

A

A shop order packet includes the shop order (manufacturing order), which is an authorization for the specified quantity of a specific part number to be made.

67
Q

manufacturing order

A

manufacturing order as a document, group of documents, or schedule conveying authority for the manufacture of specified parts or products

68
Q

work order

A

work order is authorization for equipment maintenance: 1) An order to the machine shop for tool manufacture or equipment maintenance; not to be confused with a manufacturing order. 2) An authorization to start work on an activity (e.g., maintenance) or product.

69
Q

capacity control

A

capacity control as follows: The process of measuring production output and comparing it with the capacity plan, determining if the variance exceeds pre-established limits, and taking corrective action to get back on plan if the limits are exceeded.

70
Q

capacity control objectives

A

The objectives of capacity control include meeting delivery dates and making the best use of resources.

71
Q

Priority control

A

Priority control : The process of communicating start and completion dates to manufacturing departments in order to execute a plan. The dispatch list is the tool normally used to provide these dates and priorities based on the current plan and status of all open orders.

72
Q

Operations sequencing

A

Operations sequencing : A technique for short-term planning of actual jobs to be run in each work center based upon capacity (i.e., existing workforce and machine availability) and priorities. The result is a set of projected completion times for the operations and simulated queue levels for facilities.

73
Q

Dispatching

A

Operations sequencing is the method used to control priorities when it is not necessary to resort to replanning. The process of controlling the priority of orders is called dispatching.

Dispatching

the selecting and sequencing of available jobs to be run at individual workstations and the assignment of those jobs to workers.

74
Q

Dispatching rules

A

Dispatching rules

  • First come, first served (FCFS)
  • Earliest job due date (EDD)
  • Earliest operation due date (ODD)
  • Shortest process time (SPT)
  • Critical ratio (CR
  • Slack time
75
Q

-Critical ratio (CR)

A

If the CR is 0 or negative: Expedite. The order is currently late. If the CR is less than 1.0: Expedite. The order is behind schedule. If the CR is 1.0: The order is on schedule. If the CR is greater than 1.0: The order is ahead of schedule.

76
Q

Criticial Ratio (CR) calculation

A

Critical Ratio =

(Due Date-Present Date)/Lead time remaining

77
Q

Inputs & outputs control what process types?

A

intermittent process types include work center and batch process types. These types can be controlled by monitoring the inputs and outputs of work centers. The

78
Q

input/output control (I/O)

A

input/output control (I/O)

A technique for capacity control where planned and actual inputs and planned and actual outputs of a work center are monitored.

Planned inputs and outputs for each work center are developed by capacity requirements planning and approved by manufacturing management.

Actual input is compared to planned input to identify when work center output might vary from the plan because work is not available at the work center.

Actual output is also compared to planned output to identify problems within the work center.

79
Q

What are the objectives of input/output control?

A

The objectives of input/output control include ensuring that the levels of WIP inventory and queue times at work centers remain at desired levels.

80
Q

What is included in the Input/Output Report?

A

Input/Output Report reports

  • Cumulative Variances
  • Planned Backlog
  • Actual Backlog
81
Q

Cumulative Variance (Inputs) calculation

A

Cumulative Variance (Inputs) = Previous Cumulative Variance + Actual Input - Planned input

82
Q

Cumulative Variance (Outputs) calculation

A

Cumulative Variance (Outputs) = Previous Cumulative Variance + Actual Output- Planned output

83
Q

flow control

A

flow control

A specific production control system that is based primarily on setting production rates and feeding work into production to meet these planned rates, then monitoring and controlling production.

Flow control is used for line and continuous process types as well as in lean production.

84
Q

PAC Feedback & Reporting:

Order status.

A

PAC Feedback & Reporting:
Order status.

Job status, start and completion date variances per work center, input/output variances by work center or department.

85
Q

PAC Feedback & Reporting:

Exception reports.

A

PAC Feedback & Reporting:
Exception reports.

Quantity, scrap, and rework variances; late work orders; material shortages.

86
Q

PAC Feedback & Reporting:

Inventory status.

A

PAC Feedback & Reporting:
Inventory status.

On-hand and on-order balances, changes in WIP and finished goods inventory levels.

87
Q

PAC Feedback & Reporting:

Labor reports.

A

PAC Feedback & Reporting:
Labor reports.

Labor hours used by product, worker hours for payroll.

88
Q

PAC Feedback & Reporting:

Equipment performance.

A

PAC Feedback & Reporting:
Equipment performance.

Equipment utilization and downtime.

89
Q

PAC Feedback & Reporting:

Finance and accounting data.

A

PAC Feedback & Reporting:
Finance and accounting data.

WIP and finished goods completion, labor hours, data for overhead allocation, other costs for cost accounting and financial statement preparation.

90
Q

Planned Backlog

A

Planned Backlog = Previous Planned Backlog + Planned Input - Planned Output