Section E Flashcards
What are the key aspects of Contract Administration?
- Progress reporting
- Programme
- Budget/Cost
- Quality
- Compliance
- Issue resolution
- Variations
- Document Management
- Occupation & Handover
- Health & Safety
What should you be wary of when inspecting shop drawings?
- Do not use terms “check”,”approve”, verify correctness etc. GREATER LIABILITY. Use Review as per NZIA recommendation.
- From an architectural perspective only - do not indicate approval other than in conforming with design concept and in principle with the specification + drawings.
What might be a valid reason for an Extension of Time under 3910?
- Effect of any variation
- Weather
- Strike, lockout or industrial action
- Loss or damage to the Construction Works or Materials
- Flood, volcanic or seismic events
- Circumstances not reasonably foreseeable at the time of tendering and not due to contractors fault
- Default by the Principal, or Persons who Principal responsible, which is not a Variation.
What is the timing for a Payment Claim under the SCC?
5 + 10
Architect issues provisional schedule: 5 working days
Principal review: 3 working days (8 working days)
Replacement schedule: 2 working days (10 working days)
Payment: 17 working days from receiving of claim
What is the timing for a Payment Claim under 3910?
7 + 12
Engineer 7 working days
Principal review: 3 working days (10 working days)
Replacement schedule: (12 working days)
Payment: 17 working days from receiving claim
What is the percentage for retentions released at practical completion under the SCC and 3910?
SCC: 40% at PC
3910: 50% at PC
What is the timing for the final payment claim under SCC?
Act and SCC no stated period for submission of final claim.
Arch issue final payment schedule: 20 working days
Principal review: +10 working days (30 working days)
Replacement Schedule: +5 working days (35 working days)
Principal pay: +10 working days (45 working days)
What must payment claims include for them to be valid under the CCA?
- Identify the construction contract, construction work and period the payment relates to,
- Clearly state a claimed amount and date payment is due,
- Explain how the claimed amount was calculated,
- State that request for payment is made under CCA,
- Includes Form 1 Notice (explains process for responding to the claim, and the consequences of not responding to the claim or paying the claimed or scheduled amount in full)
How would you assess off site goods?
Inspect the materials to verify they are:
- Separated
- Identified
- Labelled
- Secure
- Of quantity claimed
What is a Provisional Sum?
A work or item monetary allowance, for carrying out specific part of the Contract Work, includes contractors expenses & margins.
Examples: Joinery supply + install
Telecommunications, data and audio visual cabling
Security system
What is a Prime Cost sum?
A material related monetary allowance, provides for purchase and supply. Does not include install. Sum includes net purchase price and allowance for contractors expenses & margin.
What is one effect of Extensions of Time?
Insurance - ensure all insurances cover the period to the new date
How long does the contractor have to claim an EoT?
SCC - 5 working days, or as soon as practicable, after the delay begins.
3910 - As soon as practicable or 20 working days after circumstances arise
Must be in writing
What might be a valid reason for an Extension of Time under SCC?
- Consent or approval not obtained
- Unforeseeable physical conditions
- Contract Works are suspended in a way allowed under the Contract
- Loss or damage to any part of the Contract Works
- Variations
- Weather that interferes with progress
- Strike, lockout or industrial action
- Arch does not give a Direction within a reasonable time after being asked by the Contractor in writing to do so,
- Principal does not supply, work or services on time,
- A seperate contractors act or omission,
- Something else of significance beyond the Contractors control
What is the dispute resolution steps & timing under NZIA SCC (general condition 17)?
- Refer Contract
- Arch 10 WD from date of receipt of dispute formal written decision
- 30 WD after arch formal decision - notice to mediation
- 30 WD after mediation, appoint arbitrator within 15 WD
- Arbitrators award is final and binding. Entitled to court proceedings for some items - refer contract.
How should you address defects in relation to practical completion?
Major defects should be rectified before PC - or could become Deferred Works.
Minor defects can be listed prior to PC - but money cannot be withheld.