Section 1 Terms Flashcards

1
Q

Professional services agreement

A

A contract between an owner and consultant for a task or set period of time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Work Breakdown Structure

A

A visual hierarchical deconstruction of all work to be done for a project that shows deliverable tasks and relation to other tasks. Used to create a schedule. Outlines overall work plan including finance/budget, feedback, monitoring, and tasks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

field order

A

change to plans issued by the Landscape Architect that requires no cost or schedule changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

“At risk” construction management

A

CM services are provided as an independent contractor rather than as an owner agent. CM must deliver project that meets GMP requirement or compensate the owner/be penalized

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Post construction evaluation

A

evaluation done after final completion determining if the design meets the needs of the owner and users

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Change Order

A

a change made within the general scope of a contract. Usually means additional pay or time for contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Active interference

A

owner caused problems that prevent the contractor from staying on schedule. For example: not providing drawings on time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Stop Notice

A

an order to stop work until being paid in public projects. Generally not used in private contracts (liens used instead)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

0% Completion

A

item not started (CD Phase)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

25% Completion

A

item started, still in progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

50% Completion

A

drawing started, not labeled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

90% Completion

A

item is complete but has not been reviewed for QC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Punch list

A

List following substantial completion. Largely small items required to reach final completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

GMP

A

Guaranteed Maximum Price. This is the maximum price for a construction project created by the contractor using design documentation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Maximum-not-to-exceed

A

Maximum price for design services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Schedule of values

A

Comprehensive list of items on a project representing the entire project and contract price. Can be used as a basis for submitting and reviewing progress payments. Incidental items are not listed but included in larger elements. For example: re-bar is included in concrete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Record Drawings

A

Final set of drawings created by the architect that include all reported changes that happened during construction. Not considered the same as as-built drawings, which are created by the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Notice of award

A

Given to the contractor as a notice they have been awarded a contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Notice to proceed

A

Notice that a contractor can begin construction process. GC will generally not begin ordering or any other processes until given this notice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Overhead

A

non-labor costs associated with operating an office

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Bid Bond forfeiture

A

GC backs out after being awarded a contract. Must forfeit value of surety bond (5% of contract amount) up to price of the next highest bid to compensate owner. May also be required to forfeit bond value outright

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Contingency

A

Wiggle room allotting extra budget for unforeseen issues. Generally 5-10% when estimated by an LA.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Bid rejection

A

Bid is thrown out & not considered. In public work this can be for lateness, not being a regular bid, or not meeting bond requirements. Private work can reject any and all bids for any reason, but this will create bad relationships between owners & contractors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

opinion of probable cost

A

cost estimate from designer based on takeoffs, details, and specifications. Not intended to be authoritative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Public work: Drawing ownership

A

In public work, drawings generally belong to the owner unless otherwise specified in the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Private work: Drawing ownership

A

In private work, drawings generally belong to the designer unless otherwise specified in the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

“Or equal” & “Or approved equal” specification

A

This is a modification to a proprietary specification. “Approved” equal requires approval from the designer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Specification parts

A

Pt. 1: General; Pt 2. Product; Pt. 3 Execution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

CSI Division 1

A

General Requirements

30
Q

CSI Division 2

A

Existing Conditions

31
Q

CSI Division 3

A

Concrete

32
Q

CSI Division 4

A

Masonry

33
Q

CSI Division 9

A

Finishes

34
Q

CSI Division 31

A

Earthwork

35
Q

CSI Division 32

A

Exterior Improvements

36
Q

CSI Division 12

A

Furnishings

37
Q

Statement of Interest

A

Given in response to a pre-project RFI

38
Q

Errors & Omissions Insurance

A

professional liability insurance purchased to protect a firm from mistakes, claims of negligence, or failure to perform duties

39
Q

Clerk of Works

A

Responsible for verifying quantities of delivered materials & confirming work is carried out properly and safely. Also responsible for ensuring quality of workmanship and safety is proper, and reports back to clients.

40
Q

General Statute of Limitations

A

6-10 years for contracts, less for torts

41
Q

Project work plan

A

Scheduling tool. Organizational framework to plan how and when project will occur

42
Q

Binding arbitration

A

Arbitration that is court-enforceable but does not set legal precedent.

43
Q

Work Plans

A

Plan for completing work put together by contractor before construction

44
Q

Shop drawings

A

Drawings, diagrams, or illustrations clarifying exactly how something will be fabricated. Used for custom items as well.

45
Q

Certificate of occupancy

A

Certificate issued by government building authority confirming a building/project is safe to occupy. Typically occurs around same time as substantial completion, but is not related.

46
Q

Notice of Substantial completion

A

Notice given to contractor after approval from owner that project is largely complete & is followed by a punch list. Owner can no longer assess liquidated damages (lateness) and can only withhold costs for repair or punch list items.

47
Q

Gantt Chart/Bar Chart

A

method of project scheduling for medium sized projects with limited deadlines, deliverables, and consultants

48
Q

Critical Path Method

A

project scheduling process flow diagram superimposed over a timeline with deadlines. Handles large complex projects.

49
Q

Milestone List

A

simplistic scheduling tool often used to convey schedule status without going into major detail

50
Q

Construction Contract Documents

A

contains all documents for a project including correspondence & addendums. Completed when project is closed out, and thereby does not contain bid requirements which are no longer relevant.

51
Q

Project Profit Goal

A

15-20%

52
Q

Project Related Expenses

A

Non-labor costs like printing, messenger services, etc. Charged to client with 10% markup.

53
Q

ALTA Survey

A

American Land Title Association Survey. Detailed land parcel map showing improvements, utilites, and other significant observations

54
Q

Five Project Phases

A

start, planning, design, production, closeout

55
Q

Architects Supplemental Instruction (ASI)

A

Issued by architect to contractor as a response to an RFI. Used to clarify drawings or make corrections to a drawing after it has been issued. Generally does not affect budget or timeline.

56
Q

Request for Information (RFI)

A

Issued by contractor to architect asking for clarification on plans or details

57
Q

Project Manual

A

All project documents except for CD’s. Includes specifications. Basically everything written in text before a project has begun.

58
Q

Bidding Documents

A

All project documents needed for a contractor to create a bid. Does not include project modifications.

59
Q

Alternative Dispute Resolution (ADR)

A

Methods to resolve conflict outside of the legal system. Main methods are arbitration, mediation, & partnering

60
Q

Partnering

A

Method of dispute resolution where two groups solve an issue among themselves

61
Q

Goals

A

Universal principles applied at all projects that do not change

62
Q

Comprehensive General Liability Insurance

A

protects from lawsuits related to injury sustained by the general public, and from third party lawsuits

63
Q

Separate Contracts Method

A

owner contracts all disciplines themselves. Also referred to as Multiple Prime contract method

64
Q

Backcharging

A

provision in a contract allowing one party to recover expenses covering work from another when the other fails to perform. Not to be confused with acceleration.

65
Q

Primary cause of cost overruns

A

Performing work outside of the project scope

66
Q

Site Maintenance plan

A

holistic document taking current and future needs into account for a site. Addresses a variety of resource issues like maintenance budget, energy and water use, and user needs.

67
Q

Submittals

A

written or physical information provided by a responsible contractor submitted to the owner or architect

68
Q

Umbrella Excess Liability Insurance

A

Picks up coverage at the limit of a basic liability policy. Uses liability policy maximum coverage as deductible amount.

69
Q

Contingent Liability

A

an injured third party is able to sue a responsible party regardless of any contracts responsible party may have with anyone else.

70
Q

Construction closeout

A

primary purpose is to ensure the quality of the fully completed project