Collecting a representative sample of concrete to be tested is as important as executing the test methods to obtain ___________ ___________
Accurate results
This practice covers sampling from four types of equipment, which are?
- Stationary
- Revolving
- Agitating
- Continuous
The elapsed time between obtaining the first and final portions of a composite sample shall not exceed
15 Minutes
T/F? Portions of a composite sample shall be thoroughly remixed before beginning tests on the sample
True
Start tests for slump, temperature, and air content within ____ minutes after obtaining the final portion of the composite sample
5 minutes
Start molding specimens for strength tests within _______ minutes after fabricating the composite sample
15 minutes
The concrete sample must be protected from contamination and __________________
Evaporation
The minimum size sample for making strength test specimens is ___________
1ft^3
When sampling from a stationary mixer, the batch must be sampled at _________ or more regularly spaced intervals during discharge of the middle portion of the batch.
Two
When sampling from a paving mixer, obtain samples from at least _________ different portions of the pile and combine them into one composite sample for test purposes
5
When sampling from a revolving truck mixer, sample the concrete by collecting _______ or more portions taken at regularly spaced intervals during discharge of the middle portion of the batch
Two
T/F? Concrete samples from a truck mixer must be obtained before any water or admixtures are added to the mixer at the job site
False
When the concrete contains aggregate larger then that permitted for a particular test method, the sample of concrete must be __________ ___________ before making the test
Wet Screened
What must occured before a sample of concrete can be taken from a revolving drum mixer?
All water and admixtures must be added to the mixer
When sampling from a stationary or revolving drum mixer, what is collected and when is it taken during discharge?
In two or more portions of concrete
At regularly spaced intervals
From the middle of the batch