Section 1 Flashcards

1
Q

Collecting a representative sample of concrete to be tested is as important as executing the test methods to obtain ___________ ___________

A

Accurate results

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

This practice covers sampling from four types of equipment, which are?

A
  1. Stationary
  2. Revolving
  3. Agitating
  4. Continuous
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The elapsed time between obtaining the first and final portions of a composite sample shall not exceed

A

15 Minutes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

T/F? Portions of a composite sample shall be thoroughly remixed before beginning tests on the sample

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Start tests for slump, temperature, and air content within ____ minutes after obtaining the final portion of the composite sample

A

5 minutes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Start molding specimens for strength tests within _______ minutes after fabricating the composite sample

A

15 minutes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The concrete sample must be protected from contamination and __________________

A

Evaporation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The minimum size sample for making strength test specimens is ___________

A

1ft^3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When sampling from a stationary mixer, the batch must be sampled at _________ or more regularly spaced intervals during discharge of the middle portion of the batch.

A

Two

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When sampling from a paving mixer, obtain samples from at least _________ different portions of the pile and combine them into one composite sample for test purposes

A

5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When sampling from a revolving truck mixer, sample the concrete by collecting _______ or more portions taken at regularly spaced intervals during discharge of the middle portion of the batch

A

Two

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

T/F? Concrete samples from a truck mixer must be obtained before any water or admixtures are added to the mixer at the job site

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When the concrete contains aggregate larger then that permitted for a particular test method, the sample of concrete must be __________ ___________ before making the test

A

Wet Screened

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What must occured before a sample of concrete can be taken from a revolving drum mixer?

A

All water and admixtures must be added to the mixer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When sampling from a stationary or revolving drum mixer, what is collected and when is it taken during discharge?

A

In two or more portions of concrete
At regularly spaced intervals
From the middle of the batch

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How are the sample portions obtained from the discharge stream of a stationary or revolving drum mixer?

A

Repeatedly pass a receptacle through the entire discharge stream

Completely divert the discharge stream into a sampler container

17
Q

Describe the procedure for collecting a sample from a paving mixer

A

Discharge the contents of the paving mixer

Obtain samples from at least 5 different portions of the pile

18
Q

What is the minimum size for a sample when strength test specimens are to be molded?

A

1ft^3
One cubic foot

19
Q

What is the maximum allowable time between obtaining the first and final portions of the composite sample?

A

15 minutes

20
Q

What action is required after the individual concrete samples have been transported to the place where tests are to be performed?

A

Combine and remix with a shovel. (Wheelbarrow)

21
Q

What should be done if the concrete contains aggregate larger than is appropriate for the size of the molds or equipment being used?

A

Wet sieving (screening)

22
Q

Start the tests for slump, temperature, and air content within how many minutes after obtaining the final portion of the composite sample?

A

5 minutes

23
Q

Start molding specimens for the strength tests within how many minutes after fabricating the composite sample?

A

15 minutes

24
Q

From what must the concrete sample be protected?

A

Sun, wind, and rapid evaporation

Contamination