SE Engine & Life Cycle Reviews Flashcards

1
Q

Purpose of Pre-Phase A: Concept Studies

A

To produce a broad spectrum of ideas and alternatives
for missions from which new programs/projects can be
selected. Determine feasibility of desired system, develop
mission concepts, draft system-level requirements, assess
performance, cost, and schedule feasibility; identify
potential technology needs, and scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Purpose of Phase A: Concept and Technology Development

A

To determine the feasibility and desirability of a suggested
new system and establish an initial baseline compatibility
with NASA’s strategic plans. Develop final mission concept,
system-level requirements, needed system technology
developments, and program/project technical management
plans.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Purpose of Phase B: Preliminary Design and Technology Completion

A

To define the project in enough detail to establish an initial
baseline capable of meeting mission needs. Develop
system structure end product (and enabling product)
requirements and generate a preliminary design for each
system structure end product.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Purpose of Phase C: Final Design and Fabrication

A

To complete the detailed design of the system (and its
associated subsystems, including its operations systems),
fabricate hardware, and code software. Generate final
designs for each system structure end product.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Purpose of Phase D: System Assembly, Integration and Test, Launch

A

To assemble and integrate the system (hardware, software,
and humans), meanwhile developing confidence that it
is able to meet the system requirements. Launch and
prepare for operations. Perform system end product
implementation, assembly, integration and test, and
transition to use.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Purpose of Phase E: Operations and Sustainment

A

To conduct the mission and meet the initially identified
need and maintain support for that need. Implement the
mission operations plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Purpose of Phase F: Closeout

A

To implement the systems decommissioning/disposal plan
developed in Phase E and perform analyses of the returned
data and any returned samples.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Outcome of Pre-Phase A: Concept studies

A

Feasible system concepts in the form of simulations, analysis, study reports, models, and mock-ups

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Outcomes of Phase A: Concept and Technology Development

A
System concept definition
in the form of simulations,
analysis, engineering models
and mock-ups, and trade
study definition
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Outcomes of Phase B: Preliminary Design and Technology Completion

A

End products in the form of
mock-ups, trade study results,
specification and interface
documents, and prototypes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Outcomes of Phase C: Final Design and Fabrication

A

End product detailed designs,
end product component
fabrication, and software
development

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Outcomes of Phase D: System Assembly, Integration and Test, Launch

A

Operations-ready system
end product with supporting
related enabling products

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Outcomes of Phase E: Operations and Sustainment

A

Desired system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Outcomes of Phase F: Closeout

A

Product closeout

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Key Decision Points

A

KDPs are the events at which the decision authority determines the readiness of a program/project to progress to the next phase of the life cycle (or to the next KDP). Phase boundaries are defined so that they provide natural points for“go” or “no-go” decisions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Give 5 examples of key decision points

A
17
Q

Mission Concept

Review (MCR)

A

The MCR will affirm the mission
need and evaluates the proposed
objectives and the concept for
meeting those objectives.

18
Q

System
Requirements
Review (SRR)

A
The SRR evaluates the functional
and performance requirements
defined for the system and
the preliminary program or
project plan and ensures that
the requirements and selected
concept will satisfy the mission.
19
Q

System
Definition
Review (SDR)

A
This review
evaluates whether the proposed
architecture is responsive to
the functional and performance
requirements and that the
requirements have been allocated
to all functional elements of the
mission/system.
20
Q

Preliminary
Design Review
(PDR)

A
The PDR demonstrates that
the preliminary design meets
all system requirements with
acceptable risk and within the
cost and schedule constraints
and establishes the basis for
proceeding with detailed design.
It shows that the correct design
options have been selected,
interfaces have been identified,
and verification methods have been
described. The PDR should address
and resolve critical, system-wide
issues and show that work can
begin on detailed design.
21
Q

Critical Design

Review (CDR)

A
The CDR demonstrates that
the maturity of the design
is appropriate to support
proceeding with full scale
fabrication, assembly,
integration, and test. CDR
determines if the technical
effort is on track to complete
the system development,
meeting mission performance
requirements within the identified
cost and schedule constraints.
22
Q

Production
Readiness
Review (PRR)

A
A PRR is held for projects
developing or acquiring multiple
or similar systems greater than
three or as determined by the
project. The PRR determines
the readiness of the system
developers to efficiently produce
the required number of systems.
It ensures that the production
plans; fabrication, assembly, and
integration-enabling products;
and personnel are in place and
ready to begin production.
23
Q

System
Integration
Review (SIR)

A
An SIR ensures segments,
components, and subsystems
are on schedule to be
integrated into the system.
Integration facilities, support
personnel, and integration plans
and procedures are on schedule
to support integration.
24
Q

System
Acceptance
Review (SAR)

A
The SAR verifies the
completeness of the specific
end products in relation to
their expected maturity level
and assesses compliance to
stakeholder expectations. It also
ensures that the system has
sufficient technical maturity to
authorize its shipment to the
designated operational facility or
launch site.