SCS/SCPS - key conditions Flashcards

1
Q

What is the default completion date

A

20 WD after date of contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the default completion time?

A

2pm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How many days does a party have to complete once a notice to complete is served?

A

Within 10 WD after NTC is served. Time starts day after served

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What can an innocent seller claim if NTC is served? (4)

A

They may rescind the contract and in doing so:

  1. keep deposit
  2. interest for each day of delay on full purchase price (minus deposit)
  3. resell property
  4. contractual compensation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What can an innocent seller claim if NTC is served and completion does not take place at all? What happens to any interest paid for delay?

A

Damages

Any interest paid for delay is deducted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What may an innocent buyer claim if NTC is served? (4)

A

They may rescind the contract and in doing so:

  1. claim deposit back
  2. claim interest for each day of delay on full purchase price
  3. contractual compensation
  4. specific performance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How is contractual compensation calculated? (amount and time period)

A

it is a % as stated under the contract on the full purchase price (minus deposit if a buyer)

Period between completion date and actual completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When is VAT payable? (2)

A
  1. property less than 3 years old
  2. seller has opted in to tax
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How much VAT is payable on commercial properties?

A

20% of purchase price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly