SCRUM definition

A

Scrum is a lightweight framework that helps people, teams and organizations generate value through adaptive solutions for complex problems.
In a nutshell, Scrum requires a Scrum Master to foster an environment where:
1. A Product Owner orders the work for a complex problem into a Product Backlog.
2. The Scrum Team turns a selection of the work into an Increment of value during a Sprint.
3. The Scrum Team and its stakeholders inspect the results and adjust for the next Sprint.
4. Repeat

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The three Scrum pillars

A

transparency, inspection, and adaptation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Scrum Values

A

Commitment, Focus, Openness, Respect, and Courage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

SCRUM team (accountabilities)

A

Scrum Master, one Product Owner, and Developers (several)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Developers

A

Developers are always accountable for:
● Creating a plan for the Sprint, the Sprint Backlog;
● Instilling quality by adhering to a Definition of Done;
● Adapting their plan each day toward the Sprint Goal; and,
● Holding each other accountable as professionals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The Product Owner

A

The Product Owner is also accountable for effective Product Backlog management, which includes:
● Developing and explicitly communicating the Product Goal;
● Creating and clearly communicating Product Backlog items;
● Ordering Product Backlog items; and,
● Ensuring that the Product Backlog is transparent, visible and understood.
The Product Owner may do the above work or may delegate the responsibility to others. Regardless, the Product Owner remains accountable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Scrum Master

A

The Scrum Master is accountable for establishing Scrum as defined in the Scrum Guide. They do this by helping everyone understand Scrum theory and practice, both within the Scrum Team and the organization.
The Scrum Master is accountable for the Scrum Team’s effectiveness. They do this by enabling the Scrum Team to improve its practices, within the Scrum framework.

The Scrum Master serves the Scrum Team in several ways, including:
● Coaching the team members in self-management and cross-functionality;
● Helping the Scrum Team focus on creating high-value Increments that meet the Definition of Done;
● Causing the removal of impediments to the Scrum Team’s progress; and,
● Ensuring that all Scrum events take place and are positive, productive, and kept within the timebox.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Sprints

A

Sprints are the heartbeat of Scrum, where ideas are turned into value.
They are fixed length events of one month or less to create consistency. A new Sprint starts immediately after the conclusion of the previous Sprint.
All the work necessary to achieve the Product Goal, including Sprint Planning, Daily Scrums, Sprint Review, and Sprint Retrospective, happen within Sprints.
During the Sprint:
● No changes are made that would endanger the Sprint Goal;
● Quality does not decrease;
● The Product Backlog is refined as needed; and,
● Scope may be clarified and renegotiated with the Product Owner as more is learned

Sprints enable predictability by ensuring inspection and adaptation of progress toward a Product Goal at least every calendar month. When a Sprint’s horizon is too long the Sprint Goal may become invalid, complexity may rise, and risk may increase. Shorter Sprints can be employed to generate more learning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Sprint Planning

A

Sprint Planning initiates the Sprint by laying out the work to be performed for the Sprint. This resulting plan is created by the collaborative work of the entire Scrum Team.

Sprint Planning addresses the following topics:
Topic One: Why is this Sprint valuable?
The Product Owner proposes how the product could increase its value and utility in the current Sprint. The whole Scrum Team then collaborates to define a Sprint Goal that communicates why the Sprint is valuable to stakeholders. The Sprint Goal must be finalized prior to the end of Sprint Planning.

Topic Two: What can be Done this Sprint?
Through discussion with the Product Owner, the Developers select items from the Product Backlog to include in the current Sprint. The Scrum Team may refine these items during this process, which increases understanding and confidence.
Selecting how much can be completed within a Sprint may be challenging. However, the more the Developers know about their past performance, their upcoming capacity, and their Definition of Done, the more confident they will be in their Sprint forecasts.

Topic Three: How will the chosen work get done?
For each selected Product Backlog item, the Developers plan the work necessary to create an Increment that meets the Definition of Done. This is often done by decomposing Product Backlog items into smaller work items of one day or less. How this is done is at the sole discretion of the Developers. No one else tells them how to turn Product Backlog items into Increments of value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Sprint Backlog

A

The Sprint Goal, the Product Backlog items selected for the Sprint, plus the plan for delivering them are together referred to as the Sprint Backlog.
Sprint Planning is timeboxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Daily Scrum

A

The purpose of the Daily Scrum is to inspect progress toward the Sprint Goal and adapt the Sprint Backlog as necessary, adjusting the upcoming planned work.
The Daily Scrum is a 15-minute event for the Developers of the Scrum Team. To reduce complexity, it is held at the same time and place every working day of the Sprint. If the Product Owner or Scrum Master are actively working on items in the Sprint Backlog, they participate as Developers.
The Developers can select whatever structure and techniques they want, as long as their Daily Scrum focuses on progress toward the Sprint Goal and produces an actionable plan for the next day of work. This creates focus and improves self-management.
Daily Scrums improve communications, identify impediments, promote quick decision-making, and consequently eliminate the need for other meetings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Sprint Review

A

The purpose of the Sprint Review is to inspect the outcome of the Sprint and determine future adaptations. The Scrum Team presents the results of their work to key stakeholders and progress toward the Product Goal is discussed. The Sprint Review is the second to last event of the Sprint and is timeboxed to a maximum of four hours for a one-month Sprint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Sprint Retrospective

A

The purpose of the Sprint Retrospective is to plan ways to increase quality and effectiveness.
The Scrum Team inspects how the last Sprint went with regards to individuals, interactions, processes, tools, and their Definition of Done. Inspected elements often vary with the domain of work. Assumptions that led them astray are identified and their origins explored. The Scrum Team discusses what went well during the Sprint, what problems it encountered, and how those problems were (or were not) solved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Scrum Artifacts

A

Scrum’s artifacts represent work or value. They are designed to maximize transparency of key information. Thus, everyone inspecting them has the same basis for adaptation.
Each artifact contains a commitment to ensure it provides information that enhances transparency and focus against which progress can be measured:
● For the Product Backlog it is the Product Goal.
● For the Sprint Backlog it is the Sprint Goal.
● For the Increment it is the Definition of Done.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Product Backlog

A

The Product Backlog is an emergent, ordered list of what is needed to improve the product. It is the single source of work undertaken by the Scrum Team.
Product Backlog items that can be Done by the Scrum Team within one Sprint are deemed ready for selection in a Sprint Planning event. They usually acquire this degree of transparency after refining activities. Product Backlog refinement is the act of breaking down and further defining Product Backlog items into smaller more precise items. This is an ongoing activity to add details, such as a description, order, and size. Attributes often vary with the domain of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Commitment: Product Goal

A

The Product Goal describes a future state of the product which can serve as a target for the Scrum Team to plan against. The Product Goal is in the Product Backlog. The rest of the Product Backlog emerges to define “what” will fulfill the Product Goal.
A product is a vehicle to deliver value. It has a clear boundary, known stakeholders, well-defined users or customers. A product could be a service, a physical product, or something more abstract.
The Product Goal is the long-term objective for the Scrum Team. They must fulfill (or abandon) one objective before taking on the next.

17
Q

Sprint Backlog

A

The Sprint Backlog is composed of the Sprint Goal (why), the set of Product Backlog items selected for the Sprint (what), as well as an actionable plan for delivering the Increment (how).
The Sprint Backlog is a plan by and for the Developers

18
Q

Commitment: Sprint Goal

A

The Sprint Goal is the single objective for the Sprint. Although the Sprint Goal is a commitment by the Developers, it provides flexibility in terms of the exact work needed to achieve it.
The Sprint Goal is the single objective for the Sprint. Although the Sprint Goal is a commitment by the Developers, it provides flexibility in terms of the exact work needed to achieve it.

19
Q

Increment

A

An Increment is a concrete stepping stone toward the Product Goal. Each Increment is additive to all prior Increments and thoroughly verified, ensuring that all Increments work together. In order to provide value, the Increment must be usable.
12
Multiple Increments may be created within a Sprint. The sum of the Increments is presented at the Sprint Review thus supporting empiricism. However, an Increment may be delivered to stakeholders prior to the end of the Sprint. The Sprint Review should never be considered a gate to releasing value.
Work cannot be considered part of an Increment unless it meets the Definition of Done.

20
Q

Commitment: Definition of Done

A

The Definition of Done is a formal description of the state of the Increment when it meets the quality measures required for the product.
The moment a Product Backlog item meets the Definition of Done, an Increment is born.
The Definition of Done creates transparency by providing everyone a shared understanding of what work was completed as part of the Increment. If a Product Backlog item does not meet the Definition of Done, it cannot be released or even presented at the Sprint Review. Instead, it returns to the Product Backlog for future consideration.