Scrum Artifacts Flashcards
Who has the final say on the order of the Product Backlog?
1. Scrum Master
2. Product Owner
3. The Developers
4. The CEO
5. The Stakeholders
2
For the purpose of transparency, when does Scrum say a new increment must be available?
1. When the PO asks to create one
2. After the AC testing phase
3. Every 3 Sprints
4. Before the release Sprint
5. At the end of every Sprint
5
What are the characteristics of a Product Backlog Item that is “Ready” for selection in a Sprint Planning? Select three.
1. Can be implemented within one Sprint and tested in the next Sprint
2. Can be “Done” within one Sprint.
3. Somewhere at the bottom of the Product Backlog
4. Well-refined
5. Somewhere at the top of the Product Backlog
6. Has less detail
2,4 & 5
During the Sprint, if work is required, the Devs can add it to the current Sprint Backlog
True
False
True
Who must ensure the new increments meet the Definition of Done?
1. Scrum Master
2. Product Owner
3. Devs
4. Scrum Team
5. QA Specialists
3
When is it most appropriate for Devs to change the Definition of Done?
1. During the Sprint Retro
2. During Sprint Planning
3. Prior to starting a new Sprint
4. Prior to starting a new Project
1
A scrum Team crafts the following Sprint Goal: “All the Sprint code should have passed 100% automated unit tests”.
1. Not an appropriate goal, since the Sprint Goal should be about the expected business value
2. It is a well-formed Sprint Goal
3. It is incorrect, since the Product Owner formulates the goal and not the Scrum Team
1
Which of the following are NOT Scrum Artifacts? Select all applicable answers.
1. The list of removed impediments
2. Product Backlog
3. Sprint Goal
4. Increment
5. Sprint Backlog
1 & 3
Scrum’s artifacts represent work or value to provide transparency and opportunities for inspection and adaptation. Artifacts defined by Scrum are specifically designed to maximize transparency of key information so that everybody has the same understanding of the artifact.
The Scrum artifacts are Product Backlog, Sprint Backlog and Increment.
Scrum’s artifacts are designed to maximize the Developers’ velocity.
* True
* False
False
Scrum’s artifacts represent work or value. They are designed to maximize transparency of key information. Thus, everyone inspecting them has the same basis for adaptation.
Each artifact contains a commitment to ensure it provides information that enhances transparency and focus against which progress can be measured:
● For the Product Backlog it is the Product Goal.
● For the Sprint Backlog it is the Sprint Goal.
● For the Increment it is the Definition of Done.
These commitments exist to reinforce empiricism and the Scrum values for the Scrum Team and their stakeholders.
Which of the following is not a Scrum Artifact?
1. User Stories
2. Sprint Backlog
3. Product Backlog
4. Software Increment
1
How should items in the Product Backlog be ordered?
1. Alpha first and then by list order in the Product Backlog
2. Grouped by business features first and the chronologically by date of the original business request
3. Prioritized by business importance. The items that result in the biggest ROI must be prioritized first.
4. Chronologically by date of the original business request and then by list order in the Product Backlog.
3
H
Under what circumstances should the Product Backlog by reprioritized?
1. The Scrum Master should reprioritize the Product Backlog only at the end of a Sprint
2. The Scrum Master should reprioritize the Product Backlog only at the start of a new Sprint.
3. The Team should reprioritize the Product Backlog only at the end of a Sprint.
4. The PO should reprioritize the Product Backlog whenever new information is learned.
4
The individual, detailed pieces of work that are needed to convert a product backlog item into a working software component or solution are called:
1. User Stories
2. Use Cases
3. Line Items
4. Tasks
4
Which of the following Statements best describes the Product Backlog items?
1. Undefined or poorly defined items should be placed in the Product Backlog with a low priority
2. All Product Backlog items are the result of a(n) analysis, requirements and/or design phase(s).
3. Undefined or poorly defined items should be kept out of the Product Backlog until sufficient details is available.
4. Every Product Backlog item, low or high priority, should possess sufficient detail for the Team to complete in a Sprint.
3
What Artifact shows actual versus planned work?
1. Work Flow
2. Burn down Chart
3. Task Breakdown
4. Stakeholders
2