Scope of Work Flashcards
100 Sales Floor
Electrical; Wall finishes; Patch and repair damaged gyp board and paint to ceiling or structure; Install PS7 wainscot and DB5 base; Paint CMU; Paint vertically mounted HVAC grills to match adjacent walls; Floor finishes; Replace ceiling tile; Clean and paint (P8) ceiling grid; Remove any unused electrical drops throughout sales floor; Columns; Replace damaged outlets, non-almond to match existing color, replace almond with white; Replace customer visible almond outlets with white; Replace damaged and customer visible outlet cover plates with brushed stainless steel, including blank plates and columns; Clean or replace damaged diffusers and returns as required; Replace damaged parts of impact doors; Replace all damaged joints; Fire Sprinkler System; 100 Sales Floor Punch List; Z. Final Sign-off - 100 Sales Floor
101 GM Vestibule
Electrical; Walls: Paint brick P209 wainscot to 4’0”, P131 from 4’-0” to 10’-0” AFF; Floor finishes; Replace ceiling tile; Clean and paint ceiling grid; Replace damaged outlets, non-almond to match existing color, replace almond with white; Replace customer visible almond outlets with white; Replace damaged and customer visible outlet cover plates with brushed stainless steel, including blank plates; 101 GM Vestibule Punch List; Z. Final Sign-off - 101 GM Vestibule
105 Courtesy Desk | Customer Service
Floor finishes; Re-laminate front face and side faces of existing casework. Install new wall guard, infill toe kick, and install base; Laminate countertop: Replace countertop with new SS countertop; Replace damaged outlets, non-almond to match existing color, replace almond with white; Replace customer visible almond outlets with white; Replace damaged and customer visible outlet cover plates with brushed stainless steel, including blank plates; Clean or replace damaged diffusers as required; Install monitor support bracket; Install horizontally oriented digital display monitor; Reinstall cart rail at existing location; 105 Courtesy Desk | Customer Service Punch List; Z. Final Sign-off - 105 Courtesy Desk | Customer Service
107 Cash Office
Paint P131 to ceiling; Patch and repair walls; Ceiling: Clean and paint (P131) ceiling grid; Columns; Paint pipe support counter legs P162; Sand and varnish oak on countertop; Z. Final Sign-off - 107 Cash Office
119 AP Office
Electrical; New Walls: Paint P131 to ceiling; Floor; Ceiling; Replace ceiling tile; Clean and paint (P131) ceiling grid; Z. Final Sign-off - 119 AP Office
126 Seasonal Shop
Patch and repair damaged gypsum board walls and paint to ceiling or structure; Install PS7 wainscot and DB5 base; Paint CMU; Floor finishes; Replace ceiling tile; Clean and paint (P131) ceiling grid; Columns; Replace damaged outlets, non-almond to match existing color, replace almond with white; Replace customer visible almond outlets with white; Replace damaged and customer visible outlet cover plates with brushed stainless steel, including blank plates and columns; Clean or replace damaged diffusers and returns as required; Replace damaged parts of impact doors
148 Security
Paint P131 to ceiling; Replace ceiling tile; Clean and paint (P8) ceiling grid; Replace damaged outlets and outlet cover plates; Z. Final Sign-off - 148 Security
151 Breakroom
Demo; Plumbing; Electrical; Wall finishes; Floor; Ceiling; Columns; Millwork; Re-laminate front face and side faces of existing damaged casework; Refurbish SS countertop to like new condition; Replace countertop with SS countertop; Replace damaged outlets, non-almond to match existing color, replace almond with white; Replace damaged cover plates with brushed stainless steel, including blank plates; Clean or replace damaged diffusers and returns as required; 151 Breakroom Punch List; Z. Final Sign-off - 151 Breakroom
153 UPC | Storage
Walls: Paint P131 to ceiling; Replace ceiling tile; Clean and paint (P131) ceiling grid; Columns; Paint pipe support counter legs P162; Sand and varnish oak on countertop; Replace damaged countertop to match existing; Z. Final Sign-off - 153 UPC | Storage
155 Electronics Storage
Paint P131 to ceiling; Replace ceiling tile; Clean and paint (P8) ceiling grid; Replace damaged outlets and outlet cover plates; Z. Final Sign-off - 155 Electronics Storage
157 Hallway
Electrical; Walls ; Columns; Replace damaged outlets and outlet cover plates; Z. Final Sign-off - 157 Hallway
158 Janitor
Wall finishes; FRP on walls; Replace mop sink if broken or cracked; Z. Final Sign-off - 158 Janitor
160 Claims
Walls: Paint P131 to ceiling; Replace ceiling tile; Clean and paint (P131) ceiling grid; Columns; Paint pipe support counter legs P162; Sand and varnish oak on countertop; Replace damaged countertop to match existing; Z. Final Sign-off - 160 Claims
161 Corridor
Walls: Paint P162 wainscot to 4’-0” AFF, and P131 from 4’0” AFF to ceiling; Ceiling: Clean and paint (P131) ceiling grid; Columns; Replace damaged outlets and outlet cover plates; Z. Final Sign-off - 161 Corridor
163 Alcove
Walls; Patch and repair gyp board walls; Paint all walls P209; Install PS7 wainscot and DB5 base; Demising wall on sales floor; Floor finishes; Clean and paint (P8) ceiling grid; Columns; Replace damaged outlets and outlet cover plates; Z. Final Sign-off - 163 Alcove
167 Family Restroom
All water closets and urinals are to be temporarily removed for finish installation and then replaced in the same location; Wall finishes; Floor finishes; Ceiling: Clean and paint (P131) ceiling grid; Plumbing; Electrical; Demo; Replace all outlets with white; Replace all cover plates with brushed stainless steel, including blank plates; Clean or replace damaged diffusers and returns as required; Replace damaged flush valve; Clean and repair water closet or urinal. Replace if unable to restore to like new condition; 167 Family Restroom Punch List; Z. Final Sign-off - 167 Family Restroom
168 Storage
Paint P131 to ceiling; Replace ceiling tile; Clean and paint (P8) ceiling grid; Replace damaged outlets and outlet cover plates; Z. Final Sign-off - 168 Storage
172 Training Room
Wall finishes; Replace ceiling tile; Clean and paint (P131) ceiling grid; Paint pipe support counter legs P162; Replace damaged countertops; Columns; Replace damaged outlets, non-almond to match existing color, replace almond with white; Replace customer visible almond outlets with white; Replace damaged and customer visible outlet cover plates with brushed stainless steel, including blank plates; Clean or replace damaged diffusers and returns as required; Z. Final Sign-off - 172 Training Room
178 GM Receiving
Wall finishes; Ceiling; Replace mop sink if broken/cracked; Z. Final Sign-off - 178 GM Receiving
179 Stockroom
Electrical; Wall finishes; Ceiling; Replace mop sink if broken/cracked; Z. Final Sign-off - 179 Stockroom
180 Mezzanine
Demo; Mechanical; Electrical; Patch and repair gyp board walls; Replace damaged wainscot; Ceiling; Z. Final Sign-off - 180 Mezzanine
183 Management Office
Walls: Paint P131 to ceiling; Replace ceiling tile; Clean and paint (P131) ceiling grid; Columns; Paint pipe support counter legs P162; Sand and varnish oak on countertop; Replace damaged countertop to match existing; Z. Final Sign-off - 183 Management Office
184 Mother’s Room
Walls; Floor finishes; Ceiling; Columns; Fire Sprinkler System; Z. Final Sign-off - 184 Mother’s Room
201 Manager’s Office
Paint P131 to ceiling; Floor; Replace ceiling tile; Clean and paint (P8) ceiling grid; Paint pipe support counter legs P162; Sand and varnish oak on countertop; Replace damaged countertop to match existing; Z. Final Sign-off - 201 Manager’s Office
300 Pharmacy
Demo; Electrical; Mechanical; Plumbing; Fire Sprinkler System; Dust Wall; Paint all walls P131 semigloss. Refinished modular walls.; Install base; Omit new plastic base B9 behind pharmacy racks; Repair damaged walls both interior and exterior; Remove existing carpet, prep surface for new carpet; Install carpet and transition strip; Replace all existing ceiling tile with ACT3; Clean and paint (P131) ceiling grid; Clean existing light lenses, security globes, sprinkler heads and HVAC fixtures to remain; Casework: Install modular millwork; Walls; Paint exterior walls P209; Install new plastic laminate PS7 and plastic base DB5; Interior elevation; Floor finishes; Ceiling finishes; Install digital display monitor; Side Counter Elevation; Interior Elevation; Exterior Elevation; 300 Pharmacy Punch List; Z. Final Sign-off - 300 Pharmacy
301 Pharmacy Toilet
Clean walls; Install new flooring; Install new base; Paint ceiling P131; Clean existing light lenses, sprinkler heads, and HVAC fixtures to remain
303 Health Services Room
Paint all walls P131 semigloss. Refinished modular walls.; Install base; 48’ high wainscot PS7 on all walls; Remove existing finishes and prep surface for new LVT2P; Install transition strips; Ceiling installation; Millwork
501 Garden Center
Electrical; Walls; Floor: Powerwash existing concrete; Ceiling; Install new wind screen; Install shade cloth to match P134E; Repair/replace flashing at metal canopy; 501 Garden Center Punch List; Z. Final Sign-off - 501 Garden Center
700 Optical Sales
Paint all walls P207; Install new base DB5; Match adjacent wall texture for new walls; Remove all PVC flooring; Install transition strips; Replace ceiling tile; Clean and paint (P131) ceiling grid; Millwork
701 Adjustments
Paint all walls P207; Install new base DB5; Remove all PVC flooring and replace with LVT2P; Install transition strips; Replace ceiling tile; Clean and paint ceiling grid; Clean air grilles and diffusers, security globes, and sprinkler heads. Replace any damaged items.; LED light replacement; Millwork
703 Pretest | 705 Exam 1
Paint all walls P207; Replace damaged plastic base; Repair damaged walls; Floor: Install transition strips; Replace ceiling tile; Clean and paint ceiling grid; Clean air grilles and diffusers, security globes, and sprinkler heads. Replace any damaged items.; LED light replacement
946 Pickup Storage
Mechanical; Wall finishes; Floor finishes; Ceiling; Replace ceiling tile; Clean and paint (P131) ceiling grid; 946 Pickup Storage Punch List; Z. Final Sign-off - 946 Pickup Storage
Cart Corrals
Cart corral signage; Install (7) new cart corrals; Remove existing cart corrals; Install trash cans; Z. Final Sign-off - Cart Corrals
Customer Restrooms (Women 166 | Men 165)
All water closets and urinals are to be temporarily removed for finish installation and then replaced in the same location; Wall finishes; Floor finishes; Ceiling: Clean and paint (P131) ceiling grid; Plumbing; Electrical; Demo; Replace all outlets with white; Replace all cover plates with brushed stainless steel, including blank plates; Clean or replace damaged diffusers and returns as required; Replace damaged flush valve; Clean and repair water closet or urinal. Replace if unable to restore to like new condition; Front Restrooms (Women 166 | Men 165) Punch List; Z. Final Sign-off - Front Restrooms (Women 166 | Men 165)
Diamond Plate
Remove existing column wrap; Install diamond plate protection rail; Z. Final Sign-off - Diamond Plate
Exterior Sign
Demo Existing Signage; Install New Signage; Resurface/Paint Surface; Z. Final Sign-off - Exterior Sign
FET
Register Move; Self Checkout BullPen; Grid Wall; Power Poles; Z. Final Sign-off - FET
Fitting Room
Spot, replace, or repair floor as required; Caulk mirrors and seats; Anchor unit to floor; Z. Final Sign-off - Fitting Room
Grab & Go Cases
Electrical; Plumbing Trench; RCU Install; Refrigeration Chase; Refrigeration Piping; Start Up; Z. Final Sign-off - Grab & Go Cases
Miller Zell Signage Install
Phase 1; Phase 2; Z. Final Sign-off - Miller Zell Signage Install
New OGP Door Opening | Stanley
Install air curtain; Stanley door; Electrical; Steel work; Concrete; Security roll down door; Window tint; Z. Final Sign-off - New OGP Door Opening | Stanley
PTE (Paint Exterior)
East Elevation; Gas Line Painting; JibAccess Ladder Painting; North Elevation; South Elevation; West Elevation; PTE (Paint Exterior) Punch List; Z. Final Sign-off
PTI (Paint Interior)
Column Painting; East Interior Elevation; North Interior Elevation; South Interior Elevation; West Interior Elevation; PTI (Paint Interior) Punch List; Z. Final Sign-off
SSM (Stop Signs and Markings)
Parking Lot Directional Signage; Markings; Stop Signs; Z. Final Sign-off - SSM (Stop Signs and Markings)
Site SECP
Paint Bollards; Paint Light Pole Bases; Parking Lot Seal Coating; Parking Lot Striping; Pick-Up Parking; Z. Final Sign-off - Site SECP
VCT Conversion
Pharmacy carpet tile; Restrooms - tile; Lower clean-outs to match elevation of exposed floor; Removal and replacement of refrigerated case protection; Removal and/or replacement of thresholds at automatic sliding doors by vendor; Z. Final Sign-off - VCT Conversion
Vestibule
Repair/infill concrete slab as needed at removal of storefront; Rubber flooring; Mechanical
Vision Center
Fire Sprinkler System; Plumbing; Mechanical; Vision Center Punch List; Z. Final Sign-off - Vision Center