Scheduling Quiz Flashcards

1
Q

Activity

A

A single element or single item of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Activity Duration Time

A

The time required to complete a single activity. It may be expressed in any convenient time unit such as minutes, hours, working days, calendar days etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Bar Chart

A

Form of schedule presentation in which activities and their duration’s are plotted on a horizontal time line. Probably the most frequently used form of schedule in the construction industry.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Calendar Day

A

Any day of the year including working days, weekends or holidays.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cash Flow Projection

A

An analysis of the cash income and cash disbursement requirements for a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Constraint

A

A non-working activity that restricts the start and finish of other activities (arrival of spring weather so that site work may start).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Critical Path

A

The longest (in terms of time) path or sequence of activities from start to finish of a network diagram. An activity is critical if it has zero float, and must start and finish on time in order not to affect the total duration of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Early Finish Time

A

Earliest time an activity may finish without affecting the early start of any following activities. It is equal to the early start time plus the duration of the activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Early Start Time

A

Earliest time an activity may start without interfering with the preceding activity(s). Calculated as the highest total of all times coming into an activity on the “forward pass” through a network diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Free Float

A

The amount of time an activity may be delayed without affecting any following activity(s). It is calculated as the difference between the early finish of an activity and the earliest of the early start of any following activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Late Finish Time

A

Latest time an activity may finish without affecting the late start time of any following activities. It is equal to the late start time plus the duration of an activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Late Start Time

A

Latest time an activity may start and be completed without affecting any subsequent activities. Calculated as the lowest total of all times coming into an activity on the “backward pass” through a network diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Manning Chart

A

A histogram depicting the manpower requirements for a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Network Diagram

A

A diagram used to depict activities and their logical interrelationships. Network diagrams are usually associated with CPM schedules.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Pictorial Schedule

A

Schedule in which the key dates for major operations (floor pours, precast installation) are shown against a pictorial presentation of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Project Schedule

A

A management tool used to plan and control the activities required to construct a project.

17
Q

Resource Histogram

A

A graphical representation of the resource requirements for a project (labour, equipment, money).

18
Q

Resource Leveling

A

A technique used to “balance” the resource requirements for a project by shifting the start time of activities that have either total float or free float.

19
Q

Total Float

A

The amount of time an activity may be delayed without affecting the total project duration or critical path. It is the difference in time between the early start time and late start time of an activity.

20
Q

Total Project Duration

A

Time required to complete the entire project. Equal to the sum of all activity duration’s on the “critical path”

21
Q

Working Day

A

Any day during which a regular amount of work (8 hours) on a project may take place. Usually includes weekdays but not holidays or weekends.