Scheduling Flashcards

1
Q

Direct Cost

A

Anything that associated w/ discreet physical part of project
Ex. labor, material, equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Indirect Cost

A

Anything that can’t be associated w/ discreet physical part of project
Ex. Utilities, overhead expenses, salaries

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Total Float (TF)

A

Max. delay of ES without affecting the overall project duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Free Float (FF)

A

Max. delay of ES without affecting ES of any succeeding acitivity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Interfering Float (IF)

A

Delay of acitivity’s ES in the preceeding activity used up

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Critical Path (CP)

A
  • Path w/ the longest duration
  • Defines project duration
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Logical Limit

A

of days to reduce before creating another critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Physical Limit

A

Most # of days to reduce as possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Work breakdown structure (WBS)

A

Identify specific activities of work required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Non-network schedule

A

Gantt Chart
- hard to show effects of delays and changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Network Schedule

A
  1. CPM (Critical Path Method)
    - ex. AOA / AON
  2. PERT (Program Evaluation and Review Technique)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

AOA diagrams

A
  • Arrow = Activities
  • Node = Points in time
  • Dummy arrows
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

AON diagrams

A
  • Arrow = Relationship v activities
  • Node = Activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Why level resources?

A
  • to complete project w/ available resources
  • to avoid crew over allocation + conflict
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Why crash schedule?

A
  • save time and money
  • make up time on project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Cost slope formula

A

(Crash cost - Direct cost) / Crash duration

17
Q

Early Start (ES)

A

Lastest EF of all IPA

18
Q

Early Finish (EF)

A

ES + Dur

19
Q

Late Start (LS)

A

LF - Dur

20
Q

Late Finish (LF)

A

Earliest LS of succeding activity

21
Q

Steps of schedule crashing

A
  1. Forward/Backward pass
  2. Find CP and Critical activities
  3. Find next longest path
  4. Find critical activity w/ the lowest cost slope
  5. Find logical/physical limit
  6. Crash schedule
  7. Recalculate forward/backward pass
  8. Find indirect/direct/total cost
22
Q

What are the steps of resource leveling on MS project

A
  1. Assign available resources/resource limit
  2. Level resources within available slack
  3. If not, level resources outside available slack
23
Q

When levelling resources, which activities have priority?

A

Activities w/ the earliest LS

24
Q

Steps of manual resource leveling

A
  1. Assume there’s no labour limit and calculate project dur.
  2. Determine max. required resource
  3. Find LS
  4. Find resource limit and make resource levelling table