Schedule Management Flashcards

1
Q

What is the primary goal of project schedule management?

A

To ensure timely completion of a project

This involves a series of processes including planning, defining activities, and controlling the schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

List the processes involved in project schedule management.

A
  • Planning schedule management
  • Defining activities
  • Sequencing activities
  • Estimating activity resources
  • Estimating activity durations
  • Developing the schedule
  • Controlling the schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why is delivering projects on time considered a major challenge?

A

Time has the least amount of flexibility; it passes regardless of project circumstances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a milestone in project management?

A

A significant event that normally has no duration

Milestones are useful for setting schedule goals and monitoring progress.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Define mandatory dependencies.

A

Dependencies inherent in the nature of the work being performed on a project, sometimes referred to as hard logic.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are discretionary dependencies?

A

Dependencies defined by the project team, sometimes referred to as soft logic.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the purpose of network diagrams in project management?

A

To show activity sequencing and the logical relationships among project activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What does the arrow diagramming method (ADM) represent?

A

Activities are represented by arrows, with nodes indicating the start and end points.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the precedence diagramming method (PDM)?

A

A network diagramming technique where boxes represent activities and show types of dependencies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Fill in the blank: Duration includes the actual amount of time worked on an activity plus _______.

A

elapsed time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a three-point estimate?

A

An estimate that includes optimistic, most likely, and pessimistic estimates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the main goal when developing a project schedule?

A

To create a realistic project schedule that serves as a basis for monitoring project progress.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does a Gantt chart display?

A

Project activities along with their corresponding start and finish dates in a calendar format.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What do black diamonds represent on a Gantt chart?

A

Milestones.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the critical path in project management?

A

The series of activities that determine the earliest time by which the project can be completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

True or False: The critical path can change as the project progresses.

A

True.

17
Q

What is free slack or free float?

A

The amount of time an activity can be delayed without delaying the early start of any immediately following activities.

18
Q

What does the forward pass determine in project scheduling?

A

The early start and finish dates.

19
Q

What is total slack or total float?

A

The amount of time an activity may be delayed from its early start without delaying the planned project finish date.

20
Q

What is free slack or free float?

A

Amount of time an activity can be delayed without delaying the early start of any immediately following activities

Example: Installation of electrical wiring can be delayed by 3 days without affecting subsequent tasks.

21
Q

What is total slack or total float?

A

Amount of time an activity may be delayed from its early start without delaying the planned project finish date

Example: Software testing can be delayed by 5 days without extending the project’s finish date.

22
Q

What does the forward pass determine in project scheduling?

A

The early start and finish dates for project activities

Example: Foundation pouring can start on day 10 and finish on day 16.

23
Q

What does the backward pass determine in project scheduling?

A

The late start and finish dates for project activities

Example: Testing and validation must start no later than day 32.

24
Q

What are the main techniques for shortening project schedules?

A
  • Shortening durations of critical activities/tasks
  • Crashing activities
  • Fast tracking activities

Crashing involves obtaining the greatest amount of schedule compression for the least incremental cost.

25
Q

What is Critical Chain Scheduling?

A

A method that considers limited resources when creating a project schedule and includes buffers to protect the project completion date

It uses the Theory of Constraints to minimize multitasking.

26
Q

What is a project buffer in Critical Chain Scheduling?

A

Additional time added before the project’s due date

Helps protect against delays and uncertainties.

27
Q

What is Murphy’s Law in the context of project management?

A

If something can go wrong, it will

Highlights the importance of planning for risks.

28
Q

What is Parkinson’s Law?

A

Work expands to fill the time allowed

Suggests that tasks may take longer if not tightly scheduled.

29
Q

What is the Program Evaluation and Review Technique (PERT)?

A

Network analysis technique used to estimate project duration when there is a high degree of uncertainty about individual activity durations

Uses probabilistic time estimates.

30
Q

What are the goals of schedule control?

A
  • Know the status of the schedule
  • Influence factors that cause schedule changes
  • Determine if the schedule has changed
  • Manage changes when they occur
31
Q

What is the importance of reviewing the draft schedule?

A

To ensure the schedule is realistic and followed

It helps identify potential issues early.

32
Q

In Agile projects, is estimating activity durations crucial?

A

False

Overall project completion time may not be important in Agile environments.

33
Q

What is the significance of controlling the schedule in project management?

A

To maintain alignment with project goals and timelines

Involves managing changes and ensuring the project stays on track.

34
Q

What are the main processes in project time management?

A
  • Plan schedule management
  • Define activities
  • Sequence activities
  • Estimate activity resources
  • Estimate activity durations
  • Develop schedule
  • Control schedule