1
Q

Plan Schedule Management

A
Inputs 
 Project Charter
 Project Management Plan
 Enterprise Environmental Factors
 Organizational Process Assets 
Tools 
 Expert Judgment
 Data Analysis
 Meetings 
Outputs
 Schedule Management Plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define Activities

A
Inputs 
 Project Management Plan
 Enterprise Environmental Factors
 Organizational Process Assets 
Tools 
 Expert Judgment
 Decomposition
 Rolling Wave Planning
 Meetings 
Outputs
 Activity List
 Activity Attributes
 Milestone List
 Change Requests
 Project Management Plan Updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Sequence Activities

A
Inputs 
 Project Management Plan
 Project Documents
 Enterprise Environmental Factors
 Organizational Process Assets 
Tools 
 Precedence Diagramming Method
 Dependency Determination & Integration
 Leads & Lags
 Project Management Information System 
Outputs
 Project Schedule Network Diagrams
 Project Documents Updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Estimate Activity Durations

A
Inputs 
 Project Management Plan
 Project Documents
 Enterprise Environmental Factors
 Organizational Process Assets
Tools 
 Expert Judgment
 Analogous Estimating
 Parametric Estimating
 Three-Point Estimating
 Bottom-Up Estimating
 Data Analysis
 Decision Making
 Meetings 
Outputs
 Duration Estimates
 Basis of Estimates
 Project Documents Updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Develop Schedule

A
Inputs 
 Project Management Plan
 Project Documents
 Agreements
 Enterprise Environmental Factors
 Organizational Process Assets 
Tools 
 Schedule Network Analysis
 Critical Path Method
 Resource Optimization
 Data Analysis
 Leads & Lags
 Schedule Compression
 Project Management Information System
 Agile Release Planning 
Outputs
 Schedule Baseline
 Project Schedule
 Schedule Data
 Project Calendars
 Project Management Plan Updates
 Project Documents Updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Control Schedule

A
Inputs 
 Project Management Plan
 Project Documents
 Work Performance Data
 Organizational Process Assets 
Tools 
 Data Analysis
 Critical Path Method
 Project Management Information System
 Resource Optimization
 Leads & Lags
 Schedule Compression
Outputs
 Work Performance Information
 Schedule Forecasts
 Change Requests
 Project Management Plan Updates
 Project Documents Updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly