SAP PS Interview Questions For Freshers Flashcards

1
Q

1a. What is SAP PS?

A

A project management tool of SAP ERP that organizations use to plan and schedule their project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

1b. What are PS ‘s key features?

A

Project planning
Project controlling
Resource allocation
Project execution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. What is a WBS in SAP PS?
A

It is a structured hierarchy that describes the work to be done on a project. It’s used to help divide the project into smaller easier to manage tasks. It also defines the project deliverables goals and milestones.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. What project types can PS handle?
A

Capital
R&D
Engineering & construction
Marketing
Manufacturing
Plant maintenance
IT Project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. How do u create a project in SAP PS?
A

Use CJ20N
Projects—>copy—>Project
Enter:
Project description
Project definition
Start/End dates
Project profile
Press enter pass message if different proj profl
Assign WBS elements
Assign resources
Assign milestones
Set budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. How do you track project progress in SAP PS?
A

Project status reports
EVA earned value analysis
Network diagram
Progress tracking
Cost report
Resource utilization report

SAP gives you many ways to determine status you way depends on your needs and project requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. What are the parameters of PS?
A

Org
Time
Financial
Network
Material
Resource
Information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the 4 types of currency in PS

A

Controlling area, obj, project, transaction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Where are the time profiles defined

A

SPRIO—>IMG—>project systems—> dates —> define time profiles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Where can u view the Gantt chart?

A

CJ20N & CN20N

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How do u calculate WIP in ECC 6?

A

CJ20N
CJ20N
Costs—>WIP—>WBS elements selection tab
Select WBS to b calculated
Select multiple WBS and enter proj def
Execute
Display report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do u assign resources to a project in SAP PS?

A

CJ20N
Go to WBS
Click on activities tab
Click on resource assignment
Enter resource name and hours or units
Save

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the organizational parameters?

A

Project definition, profile, type and WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the time parameters?

A

Project start/finish, scheduling options and phases that constitute the project schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the financial parameters?

A

Cost center, cost element, currency that defines the project budget, costing and accounting techniques

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the network parameters?

A

Network type, Activity type, predecessor/successor linkages

17
Q

What are the material parameters?

A

Material master, material type, stock availability that characterizes the projects materials

18
Q

What are Resource parameters

A

Resource type, master record and availability

19
Q

What is the information parameter?

A

Project status, progress reporting, and documentation

20
Q

Finish to start FS

A

Activity can’t start till activity b4 finishes

21
Q

Start to finish ST

A

Next Activity can’t finish till activity b4 it starts