SAMPLE PRACTITIONER QUESTIONS Flashcards
SCENARIO Copy this and have this up on a separate screen
Background
MakeITwell is an IT component manufacturer which is structured into product divisions with centralized administrative functions: Human Resources (HR), Finance, Information Technology (IT) etc. It has traditionally pursued a strategy based on superior quality and reliability. It operates in a highly competitive global market characterized by the following factors:
- New overseas competitors whose products are increasingly matching the functionality and reliability of MakeITwell’s products
- Pressure to respond more quickly to shifts in customer demands and market trends
- Fierce bargaining over prices by the purchasing departments of the major IT hardware suppliers.
Additionally, MakeITwell faces a number of internal challenges as follows:
- Production costs and central overheads exceed those of MakeITwell’s competitors * Production processes and systems do not match the flexibility achieved by competitors. Consequently, it costs MakeITwell more time and money to respond to revised customer requirements
- Until recently change initiatives were led by the relevant divisions. Many suffered from delivery issues (delays and cost escalation) and have failed to realize the benefits intended
- Staff turnover is increasing – of particular concern is the loss of highly skilled engineers.
A review of recently completed initiatives found the following issues:
- Cost and benefits forecasts were highly inaccurate and incomplete – there was evidence of significant benefits being missed at the planning stage
- The strategic contribution was uncertain with many initiatives claiming to deliver the same benefits. There was also confusion as to the drivers of the key elements in the value chain
- Many initiatives were highly complex and the delivery methods applied were not sufficiently flexible to address this complexity
- Unplanned benefits were not being systematically identified and exploited resulting in significant potential benefits not being realized
- Mitigation of dis-benefits was often poorly planned and managed. For example, the Nordic Customer Engagement Initiative (NCEI) that sought to focus attention on the most profitable customers, had not considered the impact on other customers. In the end the position had been recovered without loss of revenue, but this had required significant management effort
- Initiatives had focused on processes and systems change. However, they had failed to obtain the full commitment of staff to the need for cultural change..
The CEO has come to the conclusion that MakeITwell faces a pivotal period in its history – it either adapts to the emerging competitive environment or it will see its competitive position damaged severely.
The CEO has recently persuaded the Corporate Board to approve the establishment of a Transformational Change Portfolio (TCP). This is designed to deliver benefits that contribute to the following portfolio objectives:
- Cost savings that result in reduced overhead expenditure and savings in manufacturing expenditure
- Capacity improvements measured in terms of reduced unit costs
- Greater manufacturing flexibility
- Increased turnover via new product development and more effective marketing.
The TCP includes a range of change initiatives designed to collectively achieve these objectives. This includes initiatives already underway (‘in flight’) and new initiatives including:
* A Business Intelligence (BI) initiative to enable improved management decision-making via more accurate forecasts
* An HR Transformation Programme to improve performance and reduce spend on the central HR function
* A lean manufacturing programme to improve efficiency and reduce production cost * A communications programme to improve communication with staff
* A staff re-engagement programme.
MakeITwell has also adopted best practice methods in project, programme and portfolio management supported by training programmes for all relevant staff.
The CEO has appointed a new Portfolio Director to act as the champion for the TCP. The Portfolio Director has argued strongly that the success of the TCP will depend on ensuring the portfolio adopts a benefits-led approach. Furthermore this requires a constant focus on ensuring benefits are realized and that funding allocations are revised in response to changing business priorities – reflecting the dynamic market conditions and emergent nature of MakeITwell’s strategy. Despite some Board-level uncertainty, the Portfolio Director has, with the CEOs support, gained agreement to the adoption of a Managing Benefits approach.
The progress to date includes the following:
- A first version of MakeITwell’s value chain has been completed and has been used to inform selection of initiatives for inclusion in the TCP
- A Benefits Management Forum has been established to promote more effective Benefits
Management practices across MakeITwell. The forum consists of Project and Programme Management (PPM) representatives and Business Change Managers from across the organization - An approach to benefits mapping has been adopted which includes the following headings: Enabling changes, Business changes, Intermediate benefits, End benefits, Investment objectives, and Strategic drivers
- Initiative and portfolio-level governance structures have been revised. This includes a Portfolio Investment Committee (which approves the benefits management practices and inclusion of initiatives in the TCP) and Portfolio Delivery Committee which monitors benefits realization at a portfolio-level. A Portfolio Benefits Manager has also been appointed to facilitate the development of effective benefits management
- A standard approach to benefits categorization has been agreed. It is being applied to all initiatives in the TCP with benefits being categorized as follows:
◦ Economic benefits – which result in direct budgetary savings
◦ Efficiency benefits – for example staff time savings from changed working practices ◦ Effectiveness benefits – products of a higher quality
Each of the above are sub-divided into cashable and non-cashable sub-categories. - Additionally, benefits are to be classified as ‘mission critical’, ‘highly desirable’ and ‘desirable’ based on the scale of the agreed contribution to the portfolio objectives. This year, cashable benefits have been prioritized as ‘mission critical’ to reflect the urgency of cost reduction and to free up funds to invest in other initiatives. This also reflects the policy adopted by MakeITwell to use as its primary investment decision criterion, the optimization of Net Present Value (subject to any stated constraints) from the available funds. Early payback is a desirable/secondary criterion
- Implementation of standard benefits management documentation to be applied across the portfolio
- The Five Case Business Case (with strategic, economic, financial, commercial and management cases) has been adopted with three iterations at various stages in the business change lifecycle:
◦ Strategic Outline Case (SOC) – prepared to inform the decision as to whether the initiative should be funded and included in the TCP
◦ Outline Business Case (OBC) – prepared to inform the decision as to whether the preferred solution represents value for money and to approve the development through to Full Business Case
◦ Full Business Case (FBC) – prepared to support the decision to go to contract or to commence implementation. By this stage all benefits should be signed off with the relevant benefit owners and ‘booked’ where possible. The FBC should be accompanied by a Benefits Management Strategy, Benefits Realization Plan and Benefit Profiles - Regular stage gate reviews and six monthly portfolio-level reviews have been instigated
- A standard Benefits Dashboard Report has been introduced for all initiatives. This enables consolidation at a portfolio level of progress data on a range of financial and non-financial benefits.
END OF SCENARIO
Question 1A - Principles
Answer the following question about the principles that support the efficient and effective operation of benefits management in MakeITwell.
Column 1 is a list of benefits management actions and techniques being utilized by MakeITwell. For each action/technique in Column 1, select from Column 2 the Managing Benefits Principle that the technique MOST clearly demonstrates. Each selection from Column 2 can be used once, more than once or not at all.
Column 1
1 Establishment of the MakeITwell Benefits Management Forum.
2 Booking the benefits in divisional business plans.
3 Documenting a Portfolio Benefits Management Framework.
4 Applying modular approaches to initiative development.
Column 2
A Align benefits with strategy
B Start with the end in mind
C Utilize successful delivery methods
D Integrate benefits with performance management
E Apply effective governance
F Develop a value culture
Part A
1 A B C D E F
2 A B C D E F
3 A B C D E F
4 A B C D E F
Answer
Part A
1 F
2 D
3 E
4 C
1 Correct [F]: Developing a value culture should be managed as a behavioural change programme with a focus on coordination, commitment and competencies. A Benefits Management Forum can facilitate coordination across the change
portfolio (Section 3.8).
2 Correct [D]: Booking the benefits in business plans, budgets, and performance targets is an aspect of integrating benefits with performance management (Section 3.5).
3 Correct [E]: A key characteristic of effective governance is that it is clear. This includes ensuring everyone understands who is responsible for what and accountable to whom, and what decisions are made where, when, and using what criteria. This is facilitated by documenting a Portfolio Benefits Management Framework (Section 3.7.1).
4 Correct [C]: In a complex and uncertain environment, successful delivery methods include breaking large initiatives down into smaller ones (Section 3.4).
Question 1B - Principles
Using the Scenario, answer the following question about the principles that support the efficient and effective operation of benefits management in MakeITwell.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.
Option Assertion Reason
A True True AND the reason explains the assertion
B True True BUT the reason does not explain the assertion
C True False
D False True
E False False
1
Assertion
Understanding the value chain underpinning MakeITwell’s business model will help determine the strategic contribution of each initiative.
Reason
Benefits represent the measurable improvement from change which contributes to an organizational objective.
2
Assertion
Application of the ‘Start with the end in mind’ principle helps identify the benefits from ‘in flight’ initiatives.
Reason
Benefits should be used to justify the cost of investment in a change initiative.
3
Assertion
Benefits-led change is based on the recognition that benefits realization occurs only after the initiative is completed.
Reason
Benefits realization is often dependent on not only the delivery of project outputs, but also business and behavioural change.
4
Assertion
The application of disciplined delivery methods in MakeITwell should be adapted to the local circumstances.
Reason
If change initiatives are delivered late or don’t achieve the desired outcomes, benefits realization will be adversely affected.
5
Assertion
Clarity about who is accountable for benefits realization is key to the principle: ‘Apply effective governance’.
Reason
Accountability seeks to ensure that MakeITwell knows who to punish when benefits fall below forecast.
6
Assertion
Applying the technique of ‘decision conferencing’ supports the development of a value culture.
Reason
Active engagement of senior management in benefits management practices demonstrates their commitment to a value culture.
Part B
1 A B C D E
2 A B C D E
3 A B C D E
4 A B C D E
5 A B C D E
6 A B C D E
Answer
Part B
1 A True True
2 E False False
3 D False True
4 B True True
5 C True False
6 A True True
1 True: MakeITwell’s strategic objectives are not clearly stated in measurable terms. Addressing this provides a basis for assessing the strategic contribution of
individual initiatives (Section 3.2).
True: Benefits are the measurable improvements which contribute to one or
more organizational objectives. Determining this contribution depends
on an understanding of the organization’s value chain/business
model. Therefore, the answer is A (Section 2.2).
2 False: Application of the ‘Start with the end in mind’ principle means that
identification of the problem to be solved and the benefits of doing so
precede scoping of the initiative (Section 3.3).
False: Initiatives should be established to realize the required benefits rather than
benefits being used to justify the cost of investment in a change initiative (Section 3.1, 3.3).
3 False: Benefits-led change is characterized by impatience for benefits and quick wins (Section 3.3, Table 3.1).
True: Benefits realization doesn’t just happen and is indeed often dependent on
business and behavioural changes (Section 3.4).
4 True: MakeITwell is operating in a dynamic environment characterized by
complexity, ambiguity and uncertainty. In such circumstances, disciplined
delivery methods should be adapted to suit the conditions (Section 3.4).
True: It is true that if change initiatives are delivered late or don’t achieve the
desired outcomes, then benefits realization will be adversely affected.
However, this does not explain why disciplined delivery methods should be
adapted to the local circumstances. Therefore, the answer is B (Section 3.4).
5 True: A key characteristic of effective governance is that there is clarity about
who is responsible for what and accountable to whom (Section 3.7).
False: Effective governance means accountability is based on learning and
continuous improvement rather than a blame culture (Section 3.7).
6 True: Adopting new roles and routines can assist behavioural change. So,
applying the technique of ‘decision conferencing’ whereby managers
actively engage in benefits management, does support the
development of a value culture (Section 3.8).
True: One of the keys to developing a value culture is senior management
commitment. Building this commitment is facilitated by senior managers
adopting new roles and routines including the technique of ‘decision
conferencing’. Therefore, the answer is A (Section 3.8).
Question 2A: Identify & Quantify -
Using the Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about benefits mapping in the Identify & Quantify practice.
Column 1 is a list of entries from the draft benefits map for the HR Transformation Programme. For each entry in Column 1, select from Column 2 the benefits map heading under which that entry should appear. Each selection from Column 2 can be used once, more than once or not at all. All statements in Column 1 are true statements.
Column 1
1 Reduced administration expenditure
2 Reduced headcount required for central HR
3 Cultural change within HR to provide a support rather than a direct delivery role
4 Reduced central HR budget by 20%
5 Implementation of an on-line HR advice facility
6 Increased competitive pressure from on-line and overseas competitors
Column 2
A Strategic drivers
B Investment objectives
C End benefits
D Intermediate benefits
E Business changes
F Enabling changes
Additional Information (Additional Information for part-question 2A)
HR Transformation Programme
HR has a poor reputation among operational managers and consumes a relatively high percentage of Headquarters (HQ) spend. The following issues have been identified:
- Poor employee performance is not being effectively and promptly addressed
- Top performers are not adequately recognized
- Staff turnover among skilled staff is increasing
- Key processes such as recruitment and promotion exercises take an excessive amount of time.
In response, a programme is underway to reduce administration spend, whilst also making the system more responsive. This will be achieved by transferring more HR responsibility to line managers from the central HR function. This programme includes:
- A training programme for line managers
- A cultural change programme within the HR function to support the move to a more supportive role
- Nomination of central HR ‘guides’ to provide a point of contact for specialist advice to help line managers
- The design, development and implementation of a new HR IT system to replace the existing HR intranet resource.
Part A
1 B
2 D
3 E
4 C
5 F
6 A
1 Correct [B]: Investment objectives represent the organizational target for achievement for an initiative in relation to the strategic drivers. In this case, the HR transformation initiative is designed to address the issues of poor performance and HR consuming a relatively high percentage of HQ spend (Section 5.2.2.3)
2 Correct [D]: Intermediate benefits arise from a change initiative and can in turn enable the realization of the end benefits the initiative was designed to realize. In this case, shifting workload results in a reduced headcount requirement. However, the end benefit of a reduced budget will only be realized when the spare staff are taken off budget by being re-allocated to another budget or are released (Section 2.2.5, 5.2.2.3, Glossary).
3 Correct [E]: Business changes represent new ways of working required for benefits to be realized from the enabling changes. They are usually on-going rather than one-off changes. A cultural change programme to enable the full benefits of the enabling changes including the on-line HR advice facility is thus a business change (Section 5.2.2.3).
4 Correct [C]: End benefits are those the initiative is set up to realize and which confirm achievement of the investment objectives. In this case the investment objective is to reduce administration expenditure – this is achieved via reductions in the central HR budget (Section 2.2.5, Glossary).
5 Correct [F]: Enabling changes represent the necessary prerequisites for business change and are usually one-off such as implementation of a new IT system. Implementation of an on-line HR advice facility is therefore an enabling change (Section 5.2.2.3, Glossary).
6 Correct [A]: According to the scenario, a strategic driver for change is the increased competitive pressure from overseas competitors. Strategic drivers exist
independently of any single initiative (Section 5.2.2.3).
Question 2B - Identify & Quantify
Part B
1 A B C D E
2 A B C D E
3 A B C D E
4 A B C D E
Additional Information for part-question 2B
A review of current benefits management practices and performance has identified a number of issues that have undermined the preparation of accurate and reliable benefits forecasts in initiative Business Cases. These issues include the following:
A. Confusing assumptions with knowledge B. Failure to identify all potential benefits
C. Not taking the probability of various potential outcomes into consideration when making the forecast
D. Expectation bias.
The Portfolio Benefits Manager has recently returned from a Managing Benefits training course and has recommended that the following techniques be applied to benefits forecasting as a matter of priority: Technique
- The ‘dog that didn’t bark’ test
- Optimism bias adjustments
- Independent review by a function outside the sponsoring division
- Monte Carlo simulation
- Reference class forecasting
- Requiring all business cases to include evidence both for and against the recommended option.
Part B
1 A B C D E
2 A B C D E
3 A B C D E
4 A B C D E
1 True: Confusing assumptions with knowledge derives in large part from a shared set of beliefs and values. Exposing forecasts to independent review helps
address this bias (Section 5.3.3.2, Appendix D).
True: ‘Groupthink’ refers to the tendency to confuse truth or knowledge with
assumptions. It derives in large part from a shared set of beliefs and values.
Exposing forecasts to independent review helps address this bias.
Therefore, the answer is A (Section 5.3.3.2, Appendix D).
2 True: The ‘dog that didn’t bark’ test asks whether all potential benefits have been
identified. It is therefore relevant to addressing the failure to identify all
potential benefits in the Business Case (Section 7.3, 7.9.1, Glossary).
False: The ‘dog that didn’t bark’ test assesses the benefits included in the Business
Case against the categories specified in the Portfolio Benefits Management
Framework rather than the Benefits Realization Plan (Section 7.3, Appendix B).
3 True: Monte Carlo simulation is used to calculate the probability distribution of
possible outcomes. It is therefore relevant to addressing issue C (Section
5.3.5.3, Glossary).
True: Monte Carlo simulation is indeed facilitated by the use of relevant
software. But this does not explain why this technique is relevant to issue C.
Therefore, the answer is B (Section 5.3.5.3, Glossary).
4 False: Expectation bias refers to the tendency to seek evidence that confirms existing beliefs and assumptions. Optimism bias adjustments are applied to
benefits forecasts and as such do not address this particular bias which is
directly addressed by technique 6 (Section 5.3.3.2, Appendix D).
True: Optimism bias adjustments are indeed used to address the tendency to overestimate the scale of benefits to be realized (Section 5.3.4).
Question 3A - Value & Appraise
Answer the following question about approaches applied to valuing benefits.
Column 1 is a list of benefits from initiatives included within MakeITwell’s Transformational Change Portfolio (TCP). For each benefit in Column 1, select from Column 2 the approach to valuing the benefit that is MOST appropriate. Each selection from Column 2 can be used once, more than once or not at all.
1 Column 1
More efficient processing, thus enabling increased production from the current budgetary provision.
2
3 Reduced risk of potential systems failure with uncertain cost implications.
Reduced time spent on routine data preparation, which can be used for other activities.
Column 2
A Increased revenue
B Reduction in total production cost
C Lower unit costs
D Value of work enabled
E Willingness to pay
Part A
1 A B C D E F
2 A B C D E F
3 A B C D E F
Part A
1 C
2 E
3 D
1 Correct [C]: Efficiency improvements enabling ‘more from the same’ should be measured in terms of reduced unit costs (Section 6.2.2.2).
2 Correct [E]: Reduced risk is a non-financial benefit and as such the most appropriate approach to valuing it is willingness to pay (Section 6.2.2.3).
3 Correct [D]: The value of staff time savings is the value of the use to which the time saved is put (Section 6.2.2.2).
Question 3B - Value & Appraise
Answer the following question about approaches applied to initiative appraisal.
Column 1 is a list of investment rationales for initiatives being considered for inclusion in the TCP. For each entry in Column 1, select from Column 2 the approach to investment appraisal that is MOST appropriate. Each selection from Column 2 can be used once, more than once or not at all.
Column 1
1 IT infrastructure upgrade enabling increased use of current applications, new approved applications, and new applications which are currently at the preapproval stage.
2 Replacement of the stock control system which is essential to maintain business as usual and avoid system failures.
3 New just in time manufacturing system designed to streamline production processes to reduce the cost of production and enable increased throughput.
Column 2
A Cost-benefit analysis
B Real options
analysis
C Cost-effectiveness analysis
D Multi-criteria analysis
Part B
1 A B C D
2 A B C D
3 A B C D
Part B
1 B
2 C
3 A
1 Correct [B]: In this case there is a degree of uncertainty as to the benefits to be derived from unplanned expansion in users and new applications. In such circumstances, real options analysis is relevant as it specifically takes the value of flexibility into consideration (Section 6.3.2, Glossary).
2 Correct [C]: In this case the benefits refer to maintaining Business as Usual. Therefore, cost-effectiveness analysis is most relevant (Section 6.3.3.1).
3 Correct [A]: In this case the benefits are anticipated in terms of reduced costs and lower unit costs. Therefore, cost-benefit analysis is most relevant (Section 6.3.1).
Question 3C: Value & Appraise - Additional Information
Using the Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about the Value & Appraise practice.
1 If there are no limits on funding available, but MakeITwell only has the capacity to manage one initiative from the five available, it should invest in initiative 4.
Is this an appropriate decision for this scenario?
A No, because initiative 2 has the highest NPV and should, therefore, be invested in first.
B No, because initiative 1 has a higher NPV than initiative 4.
C Yes, because initiative 4 has the highest productivity index.
D Yes, because initiative 4 breaks even earlier than the alternative initiatives.
2 If MakeITwell only has £750,000 to invest over five years, it should invest in initiatives 4 and 5. Is this an appropriate decision for this scenario?
A No, because initiative 2 has the highest NPV and should therefore, be invested in first.
B No, because initiatives 1 and 2 have a higher combined NPV.
C Yes, because initiatives 4 and 5 provide the highest possible NPV from the funds available.
D Yes, because investing in more than one initiative helps diversify risk.
3 If MakeITwell has only £1,300,000 to invest over five years in initiatives that pay back in current value terms by the end of year 2, it should invest in initiatives 2, 4 and 5. Is this an appropriate decision for this scenario?
A No, because initiatives 2, 4 and 5 are not affordable.
B No, because initiative 2 does not pay back in current value terms by the end of year 2.
C Yes, because investing in three initiatives helps minimize the risk of failure.
D Yes, because initiatives 2, 4 and 5 have the highest combined NPV from the available investment.
4 MakeITwell has only £1,200,000 to invest over five years in initiatives that pay back in undiscounted terms by the end of year 2. In addition, 10% of benefits from initiative 2 are available to be re-cycled to fund other initiatives. In these circumstances it should invest in initiatives 2, 4 and 5.
Is this an appropriate decision for this scenario?
A No, because the funding available is insufficient for initiatives 2, 4 and 5.
B No, because initiative 2 doesn’t pay back in undiscounted terms by the end of year 2.
C Yes, because this maximizes the NPV from the available funds.
D Yes, because re-cycling benefits enables all initiatives that meet the hurdle rate of return to be funded.
Additional Information for part-question 3C
The following data has been collected for five initiatives in the Transformational Change Portfolio (TCP).
Initiative 1 Year Year Year Year Year Year
5 year cost 600 0 1 2 3 4 5 Totals
PI* 0.388 £,000’s £,000’s £,000’s £,000’s £,000’s £,000’s
Benefits 0 175 250 250 250 175 1100
Costs 600 600
Annual Net Flow -600 175 250 250 250 175 500
Annual NPV
Cumulative net flow -600 -600 159
-425 207
-175 188 75 171 325 109 500 233
Cumulative NPV -600 -441 -234 -46 124 233
Initiative 2 Year Year Year Year Year Year
5 year cost 550 0 1 2 3 4 5 Totals
PI* 0.488 £,000’s £,000’s £,000’s £,000’s £,000’s £,000’s
Benefits 0 200 200 200 200 200 1000
Costs 300 50 50 50 50 50 550
Annual Net Flow -300 150 150 150 150 150 450
Annual NPV
Cumulative net flow -300 -300 136
-150 124 0 113 150 102 300 93
450 269
Cumulative NPV -300 -164 -40 73 175 269
Initiative 3 Year Year Year Year Year Year
5 year cost 275 0 1 2 3 4 5 Totals
PI* -0.063 £,000’s £,000’s £,000’s £,000’s £,000’s £,000’s
Benefits 0 60 60 60 60 60 300
Costs 150 25 25 25 25 25 275
Annual Net Flow -150 35 35 35 35 35 25
Annual NPV
Cumulative net flow -150 -150 32
-115 29
-80 26
-45 24
-10 22 25 -17
Cumulative NPV -150 -118 -89 -63 -39 -17
Initiative 4 Year Year Year Year Year Year
5 year cost 250 0 1 2 3 4 5 Totals
PI* 0.758 £,000’s £,000’s £,000’s £,000’s £,000’s £,000’s
Benefits 0 100 100 100 100 100 500
Costs 0 50 50 50 50 50 250
Annual Net Flow 0 50 50 50 50 50 250
Annual NPV
Cumulative net flow 0 0 45 50 41
100 38
150 34
200 31
250 190
Cumulative NPV 0 45 87 124 158 190
Initiative 5 Year Year Year Year Year Year
Part C
1 A
2 C
3 B
4 C
1 A Correct: If the only constraint is the number of initiatives that can be invested in, MakeITwell should invest in the initiative with the greatest NPV (Section 6.3.1).
B Incorrect: Initiative 1 does have a higher NPV than initiative 4, but initiative 2 has an even higher NPV. If there are no constraints on investment aside from the number of initiatives, then initiative 2 should be funded (Section 6.3.1).
C Incorrect: Initiative 4 does have the highest Productivity Index (PI), but as funding isn’t a constraint, the PI is not relevant (Section 6.3.1).
D Incorrect: Initiative 4 does break even earlier than the other initiatives, but the scenario specifies that MakeITwell has chosen to optimize NPV as its primary investment criterion (Section 6.3.1).
2 A Incorrect: Initiative 1 does have the highest NPV, but initiatives 4 and 5 offer a highercombined NPV from the £750,000 available for funding. Where funding is
constrained the relevant decision rule is to rank initiatives using the Productivity
Index (Section 6.3.1).
B Incorrect: Initiatives 1 and 2 do have a higher combined NPV (£508,000) than initiatives 4 and 5 (£406,000), but they are not affordable – they would cost £1,150,000 whereas only £750,000 is available (Section 6.3.1).
C Correct: NPV is optimized (£406,000) from the £750,000 available for funding by
investing in initiatives 4 and 5 (Section 6.3.1).
D Incorrect: Investing in more than one initiative may or may not diversity risk depending on the characteristics of the initiatives concerned. According to the scenario the decision criterion adopted by MakeITwell is to optimize NPV (Section 6.3.1).
3 A Incorrect: Initiatives 2, 4 and 5 would cost £1,300,000 and are therefore affordable if £1,300,000 is available for investment (Section 6.3.1).
B Correct: Initiative 2 pays back in cash/undiscounted terms by the end of year 2, but not in current value/discounted terms (Section 6.3.1).
C Incorrect: Investing in three initiatives may diversify risk depending on the characteristics of the initiatives concerned. However, the decision criterion adopted by MakeITwell is to optimize NPV subject to any stated constraints (Section 6.3.1).
D Incorrect: Initiatives 2, 4 and 5 do have the highest combined NPV from the available investment of £1,300,000. However, initiative 2 does not pay back in current value terms by the end of year 2 (Section 6.3.1).
4 A Incorrect: The funding available is £1,200,000 plus 10% of the benefits from initiative 2 which is £100,000. So £1,300,000 is available which is sufficient to fund
initiatives 2, 4 and 5 (Section 6.3.1).
B Incorrect: Initiative 2 does pay back in undiscounted terms by the end of year 2 (Section 6.3.1).
C Correct: Investing in initiatives 2, 4 and 5 maximizes the NPV return from the available funds of £1,300,000. Furthermore all three initiatives meet the payback criterion (Section 6.3.1).
D Incorrect: Re-cycling benefits from initiative 2 enables initiatives 2, 4 and 5 to be funded. Initiative 1 also meets the stipulated hurdle rate of return, but funding is
insufficient to also fund this initiative (Section 6.3.1).
Question 4A - Plan
1 Which 2 statements would appear in the Benefits Management Strategy?
A Ramp up of the staff time saving benefit will be 25% in month 1, 50% in month 2, and 100% from month 3.
B Benefits dependency networks will be used to confirm understanding of the enabling and business changes upon which benefits realization depends.
C Current status on benefits realization for efficiency benefits is classified as Amber-Red.
D The total forecast efficiency savings from the initiative are £2,500,000.
E Responsibility for commissioning end of tranche/phase benefit reviews lies with the Senior Responsible Owner (SRO).
2 Which 2 statements would appear in the Benefit Realization Plan?
A The forecast value of programme benefits in the efficiency cashable category totals to £150,000 by month 9.
B Benefits will be reported using the Transformational Change Portfolio categorization system.
C The Benefits Dashboard report will be prepared for the Programme Board for the second Friday each month.
D Efficiency benefits have been assigned to the ‘mission critical’ category.
E Current status on benefits realization for economy benefits is classified as Amber-Green.
3 Which 2 statements would appear in the Economic Case of the Business Case?
A All benefits are required to be validated with benefits owners to help prevent double counting.
B Responsibility for realizing the staff time saving benefit in HR lies with the HR Business Change Manager.
C The highest Net Present Value is provided by option B.
D The forecast Net Present Value of the programme is £450,000 over five years.
E Economic benefits will be re-cycled to address the funding shortfall in year 2.
Part A
1 A B C D E
2 A B C D E
3 A B C D E
Part A
1 B & E
2 A & C
3 C & D
1 A Incorrect: The Benefit Profile contains details of the ramp up of an individual benefit (Appendix B).
B Correct: The Benefits Management Strategy includes the approach to benefits mapping to be applied (Appendix B).
C Incorrect: A statement on benefits realization status would appear in the Benefits
Realization Report (Section 8.4.3.1).
D Incorrect: A statement on the benefits forecast would appear in the Benefits Realization Plan (Appendix B).
E Correct: The Benefits Management Strategy includes a description of the roles,
accountabilities and responsibilities for benefits planning and realization. It also
includes the review and assessment process (Appendix B).
2 A Correct: The Benefits Realization Plan is used as the baseline against which to track benefits realization. Therefore, it will contain a schedule with aggregated
benefits data for each time period (Section 7.9, Appendix B).
B Incorrect: A description of the approach to benefits categorization to be used will be included in the Benefits Management Strategy (Appendix B).
C Correct: The benefits reporting schedule will be included in the Benefits Realization Plan (Appendix B).
D Incorrect: A description of priorities in terms of benefit types sought will be included in the Benefits Management Strategy (Appendix B).
E Incorrect: A statement on benefits realization status would appear in the Benefits
Realization Report (Section 8.4.3.1-2).
3 A Incorrect: Processes to ensure benefits are not double counted are addressed in the Benefits Management Strategy (Appendix B).
B Incorrect: The Benefit Owner for a benefit is recorded on the Benefit Profile (Section 4.5, Appendix B).
C Correct: The Economic Case demonstrates that the preferred option optimizes value for money (Table 7.7).
D Correct: The Economic Case includes a cost-benefit analysis (Table 7.7).
E Incorrect: This entry concerns affordability and therefore appears in the Financial Case of the Business Case (Table 7.7).
Question 4B - Plan
Using the Scenario, answer the following question about initiative-level benefits management roles.
Column 1 is a list of benefits-related functions/actions undertaken on various initiatives within MakeITwell’s Transformational Change Portfolio (TCP). For each statement in Column 1, select from Column 2 the role responsible for undertaking this function/action. Each selection from Column 2 can be used once, more than once or not at all.
Column 1
1 Commissions a benefits review on the Nordic Customer Engagement initiative.
2 Agrees the Benefit Profile for the efficiency savings on the lean programme.
3 Assesses readiness of the Finance Department to adopt the new ways of working prior to implementation of the new Business Intelligence system.
Column 2
A Senior Responsible Owner
B Programme
Manager
C Business Change
Manager
D Benefit Owner
E Benefit Manager
Part B
1 A B C D E
2 A B C D E
3 A B C D E
Part B
1 C
2 D
3 C
1 Correct [C]: According to the scenario the NCEI is one in which the programme has closed. Therefore, responsibility for commissioning benefits reviews will reside with the Business Change Manager (Section 4.5, Appendix C).
2 Correct [D]: The Benefits Owner is responsible for agreeing the Benefit Profile prepared by the BCM (Section 4.5, Appendix C).
3 Correct [C]: The BCM is responsible for assessing readiness for change as part of pretransition (Section 7.5).
Question 4C - Plan
Using the Scenario, answer the following question about the Plan practice.
Lines 1 to4 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.Each option canbe used once, more than once or not at all.
Option Assertion Reason
A True True AND the reason explains the assertion
B True True BUT the reason does not explain the assertion
C True False
D False True
E False False
1
Assertion
Addressing the failure to identify all potential benefits is aided by a Portfolio Benefits Management Framework.
Reason
The Portfolio Benefits Management Framework includes a consistent set of benefits categories against which initiative benefits forecasts can be appraised.
2
Assertion
Addressing the failure to identify emergent benefits is aided by applying the technique of ‘booking the benefits’ early in the initiative lifecycle.
Reason
‘Booking the benefits’ helps align benefits realization with the performance management regime.
3
Assertion
Failing to plan effectively to mitigate dis-benefits on the Customer Engagement
Initiative is an example of value for money failure.
Reason
Value for money failure arises from the effect of optimism bias and strategic misrepresentation on accurate benefits forecasting.
4
Assertion
Confidence in the causes of benefits realization is helped by the identification of a chain of leading and lagging measures.
Reason
Lagging measures help address problems in attributing changes in performance to a particular initiative.
Part C
1 A B C D E
2 A B C D E
3 A B C D E
4 A B C D E
Part C
1 A
2 D
3 E
4 C
1 True: The failure to identify all potential benefits is addressed by the ‘dog that
didn’t bark’ test. This is aided by a Portfolio Benefits Management
Framework (Section 1.5, 7.3).
True: The Portfolio Benefits Management Framework includes a consistent set of
benefits categories against which initiative benefits forecasts can be
appraised – both for forecast benefits and to identify any potential benefits that
have been omitted from the Business Case. Therefore, the answer is A
(Section 7.3, 10.3.1, Appendix B).
2 False: ‘Booking the benefits’ is used to align benefits and performance
management. However, it can only be applied to benefits that have been
identified. Emergent benefits are in contrast unplanned (Section 3.5, 7.7.2,
Glossary).
True: ‘Booking the benefits’ aligns benefits realization with the performance
management regime by ensuring planned improvements are reflected in
organizational KPIs, budgets etc. Responsibility for these improvements is
reflected in individuals’ performance objectives (Section 3.5, 7.3).
3 False: Value for money failure refers to cases where benefits are realized but at
excessive cost. This is not the case with the Customer Engagement
Initiative; according to the scenario the failure to mitigate dis-benefits had no
financial implications (Section 7.7.1).
False: Value for money failure refers to cases where benefits are realized but at
excessive cost. This can be due to the effect of optimism bias and strategic
misrepresentation but on cost rather than benefits forecasting (Section 7.7.1).
4 True: Confidence in benefits realization is helped by the identification of a chain of leading and lagging measures because this helps address the attribution issue (Section 4.3.1, 7.6.5).
False: Leading rather than lagging measures help address problems in attributing
changes in performance to a particular
Question 5A: Realize - Additional Information
Using the Scenario, answer the following question about the Transition Management element of the Realize practice on the HR Transformation Programme.
Column 1 is a list of true statements about activities undertaken as part of a programme. For each activity in Column 1, decide if the activity is part of transition management and select from Column 2 the transition management phase where it is MOST likely to be undertaken.
Column 1
1 Shut down the existing HR intranet resource which is to be replaced by the new HR IT system.
2 The Business Change Manager assesses the capability of the business unit to adopt the new ways of working.
3 The HR Director approves the commencement of the transition stage.
Column 2
A This is NOT part of transition management
B Managing pre-transition
C Managing transition
D Managing post-transition
Part A
1 A B C D
2 A B C D
3 A B C D
Part A
1 D
2 B
3 C
1 Correct [D]: Removing access to legacy systems is a part of the ‘Managing post-transition’ phase of transition management (Section 8.3.2).
2 Correct [B]: Change readiness assessment is part of the ‘Managing pre-transition’ phase (Section 7.5).
3 Correct [C]: SRO approval to commence transition is part of the ‘Managing transition’ phase of transition management (Section 8.3.1).
Question 5B: Realize - Additional Information
Answer the following question about the initiative to improve communications.
Column 1 is a list of communications from the Portfolio Director to Business Case writers. For each communication in Column 1, decide if it is a ‘committed conversation’ and select from Column 2 the type of conversation that it represents. Each selection from Column 2 can be used once, more than once or not at all.
Column 1
1 Will you provide forecasts in accordance with the revised benefits eligibility guidance documented in the Portfolio Benefits Management Framework?
2 Inaccurate and unreliable benefits forecasts compromise our ability to make the best use of available funds. This needs to be addressed in time for the next strategic planning round.
3 We need to significantly improve the accuracy of forecasting.
Column 2
A Not a committed conversation
B Initiative conversation
C Conversation for understanding
D Conversation for performance
E Conversation for closure
Part B
1 A B C D E
2 A B C D E
3 A B C D E
Part B
1 D
2 C
3 B
1 Correct [D]: This is a ‘conversation for performance’ which are a network of requests and promises spoken to produce a specific action and result (Section 8.5.2).
2 Correct [C]: This is a ‘conversation for understanding’ in which people seek to understand the drivers and evidence for initiative conversations and specify the timeline for improvement (Section 8.5.2).
3 Correct [B]: This is an ‘initiative conversation’ which creates a call to action via an assertion, request, promise or declaration (Section 8.5.2).
Question 5C: Realize - Additional Information
Using the Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about which technique is MOST appropriate to address the issues identified.
Lines 1 to4 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.Each option canbe used once, more than once or not at all.
Option Assertion Reason
A True True AND the reason explains the assertion
B True True BUT the reason does not explain the assertion
C True False
D False True
E False False
Assertion
1 From those techniques shown, issue A is MOST effectively addressed by technique 8.
Reason
The ‘Scout and Beacon’ approach ensures that the original business case includes emergent benefits.
Assertion
2 From those techniques shown, issue B is MOST effectively addressed by technique 7.
Reason
‘Narrative leadership’ engages stakeholders at an emotional level.
Assertion
3 From those techniques shown, issue C is MOST effectively addressed by technique 3.
Reason
The ‘one version of the truth’ technique addresses the attribution issue.
Assertion
4 From those techniques shown, issue D is MOST effectively addressed by technique 4.
Reason
Normalized scales can be used with initiative weightings to represent progress at a portfolio level.
Part C
1 A B C D E
2 A B C D E
3 A B C D E
4 A B C D E
Part C
1 C
2 A
3 E
4 B
1 True: Failure to identify unplanned or emergent benefits is addressed by the
‘scout and beacon’ approach (Section 7.7.2).
False: The ‘scout and beacon’ approach helps identify emergent benefits which are
benefits that arise as the initiative is developed, deployed or implemented.
Therefore, they won’t appear in the original Business Case (Section 7.7.2).
2 True: Failure to obtain the full commitment of staff in the need for cultural change is addressed by ‘narrative leadership’ (Section 8.5.6).
True: ‘Narrative leadership’ engages stakeholders at an emotional level and
this explains why it addresses the failure to obtain the full commitment of staff in
the need for cultural change. Therefore, the answer is A (Section 8.5.6).
3 False: ‘One version of the truth’ seeks to ensure an authoritative source of
information for decision-making rather than addressing problems in linking
operational performance improvements to a specific change initiative. This
issue is addressed by using leading measures (Section 8.4.1, 8.4.3.3,
Glossary).
False: The attribution issue is addressed by using leading as well as lagging
measures rather than ‘one version of the truth’ which seeks to ensure an
authoritative source of information for decision-making (Section 8.4.1, 8.4.3.3,
Glossary).
4 True: Normalized scales can be used to combine assessments of progress on
a range of financial and non-financial benefits (Section 8.4.3.1).
True: Weightings can be applied to normalized scales to represent progress
at a portfolio level. However, this does not explain why normalized scales can
be used to represent progress on the initiative Benefits Realization Report.
Therefore, the answer is B (Section 8.4.3.1).
Question 6A: Review - Additional Information
Using the Scenario, answer the following question about the Review practice.
Column 1 is a list of statements made to the team undertaking the post-investment review of the Customer Engagement initiative. For each statement in Column 1, select from Column 2 the cognitive bias that the statement MOST clearly demonstrates. Each selection from Column 2 can be used once, more than once or not at all.
Part A
1 A B C D E
2 A B C D E
3 A B C D E
Part A
1 D
2 B
3 A
1 Correct [D]: The ‘Texas Sharpshooter fallacy’ refers to the tendency to evaluate an initiative in terms of the benefits actually realized, rather than whether the intended benefits were realized (Section 9.5).
2 Correct [B]: The ‘Hindsight bias’ refers to the tendency to see past events as being more predictable than they actually were (Section 9.5).
3 Correct [A]: The ‘Self-serving bias’ refers to the tendency to see successes as being due to our efforts/abilities, but failure is due to external factors or bad luck (Section 9.5).