RULE XI - PROTECTION OF PEDESTRIANS DURING CONSTRUCTION OR DEMOLITION Flashcards
Materials to be stored at or near construction sites shall be piled or stacked in an orderly manner to avoid toppling over or being otherwise displaced. No materials shall be piled or stacked higher than ______, except in yards or sheds intended especially for storage. When piles exceed ______ in height, the material shall be so arranged that the sides and ends of the piles taper back.
1.80 meters, 1.20 meters
The mixing of mortar, concrete, or similar materials on public streets is allowed.
False, mixing of mortar, concrete, or similar materials on public streets shall not be allowed.
When the Building Official authorizes a sidewalk to be fenced or closed, or in case there is no sidewalk in front of the building/structure site during construction or demolition, a temporary walkway of not less than ______ shall be provided.
1.20 meters
Such walkway shall be capable of supporting a uniform live load of ______.
650.00 kilogram per sq. meters
Where the sidewalk is permitted by the Building Official to be fully occupied and fenced-off or enclosed, a temporary walkway adjacent to the curb line shall be required. Where the street has no sidewalk, a temporary walkway adjacent to the street line not less than _______ wide shall be provided. Where the RROW is ________ or less, no temporary walkway shall be allowed.
600 millimeters, 5.00 meters
Where only partial occupancy and fencing-off of the sidewalk is necessary, a temporary walkway will not be required provided that a width of at least _______ of the sidewalk with protective railing on road side shall be left open for the use of pedestrians.
600 millimeters
Railings where required, shall be built substantially strong and sturdy and shall not be less than _____ in height.
1.00 meters
Fences shall entirely enclose the construction/demolition site and shall be erected on the building side of sidewalks or walkways and shall be made of approved materials (e.g. G.I. sheet, wooden boards and/or planks, plywood or Lawanit, sawali), not less than ________ in height above the curb line. Fences shall be built solid for its full length except for such openings as may be necessary for proper execution of the work. Such openings shall be provided with doors, which shall be kept closed at all times except when in actual use.
2.40 meters
The protective canopy shall have a clear unobstructed height of _______ above the walkway and shall be made of sufficient strength and stability to sustain safely the weight of materials that may be placed thereon, and to withstand shocks incident to the handling of such materials or their preparation for use, and accidental jars from trucks passing or delivering materials.
2.40 meters
When the canopy is used for the storage of materials or for the performance of work of any kind, substantial railings not less than ______ high and solid toe boards not less than ______ high shall be placed along the street side and ends of the canopy. The canopy shall be capable of safely sustaining a load of______ or the intended load to be placed thereon, whichever is bigger.
1.00 meters, 300 millimeters, 4800 Pascal
The deck flooring of a canopy shall consist of planking not less than ________ in thickness, closely laid. All members of the canopy shall be adequately braced and connected to resist displacement of members or distortion of the framework.
50 millimeters
All entrances/exits to and from the construction/demolition site shall be open at all times except during actual passage of men, materials or equipment.
False, All entrances/exits to and from the construction/demolition site shall be kept closed at all times except during actual passage of men, materials or equipment.
In passageways, stairways and corridors, the average light intensity measured at floor level shall be not less than _______.
200 LUX
At locations where tools and/or machinery are used, the average light intensity measured at floor level shall be not less than _______.
500 LUX
Electrical machinery and equipment to be used for construction work shall be installed and operated in accordance with the ______.
Philippine Electrical Code
Steam boilers used in construction work shall be installed, equipped and maintained in accordance with the _________.
Philippine Mechanical Code