rnav Flashcards
To use FINAL APP how many FMS needs to be operative and in what condition?
1 x FMS
GPS PRIMARY
The minimum equipment required to start RNP APCH operations is?
One FMGC
One GPS
Two IRS
One MCDU
One FD
One PFD on the PF side
Two NDs (the temporary display of ND information via the PFD/ND switch is permitted on PM side)
Two FCU channels.
Difference allowed between F-PLAN A page and plates?
0.1 degree for vertical path
1 degree for lateral track
PM Calls if lateral or vertical limits exceeded during approach?
“X-Track” > 0.1nm
“V-Dev” > 1/2 Dot
Vertical path. Height for 1 dot and 1/2 dot
1 Dot = 100ft
1/2 Dot = 50ft
If you lose GPS Primary what do you do?
Continue with remaining AP/FD
If you have NAV ACCUR DOWNGRAD on 1 x ND what do you do?
Continue with remaining AP/FD
Which systems require you to discontinue the approach if you have no visual references?
- GPS Primary lost on both NDs
- X-Track > 1/2 RNP
- NAV/FM GPS POS DISAGREE
- NAV ACCUR DOWNGRADE on both ND’s
If you are doing RNAV (LNAV) and vertical guidance no good, what can you do?
Use NAV/FPA
If you are doing RNAV (VNAV), at what vertical deviation do you discontinue approach?
75ft (V/Dev > 3/4 Dot)