Q

When was it restored

A

1994-96

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What were the aims

A

Water course back to a more natural state, improve water quality, manage bank side vegetation and habitats

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why did they allow flooding here

A

It affected no one here (as they created a more natural channel) because it was away from Coleshill and decreased the chances of flooding downstream in Oxford

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What were the 4 main strategies used

A
  1. Mill Leaf ‘by pass’
  2. Introduction of meanders
  3. Mature willows retained along old course- take up a lot of water and decrease soil erosion
  4. Reedbed formed in existing river