Risks and Assumptions Flashcards

1
Q

Risks are

A

key events, actions or decisions

upon which project success depends

which may be subject to delay or which may not materialise.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Risks are not supposed to occur

A

but there is a probability that they might

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Assumptions are

A

external factors

outside the immediate control of the project,

crucial for
the achievement of activities, results and objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The aim of specifying assumptions and preconditions is to

A

ID and assess
potential risks to, dependencies of, the project right from initial stages of the project design,

to support the M of risks during the Imp of the
project

to provide a basis for necessary adjustments.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

It is important to identify the assumptions at

A

each level of the logical framework analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Some assumptions can be identified during the

A

analysis phase as objectives included in the
objective tree

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Those objectives are not achieved by the project but

A

they can be important for achieving the purpose of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

For example

A

a nutrition project may have ‘improved nutritional status of the population’ as its purpose, in a context where this may only be achieved on the condition
that a complementary water project achieves its specific objectives.

One of the assumptions behind the nutritional project therefore may be that this condition is met

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Other examples are:

A

‘access to water will be guaranteed, assuming that there is no sabotage of the transmission line of the water system’,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

other example

A

‘capacity in the region will be improved,

assuming that

the authorities continue to participate in training’,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

other example

A

‘a system can be built in a specific area, assuming that access to the area is guaranteed’.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

There are different levels of assumption depending on

A

Their relevance to the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

If an assumption for success is unlikely

A

Then the project should be redesigned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

If it is sure, or almost sure,that it will occur,

A

Then it is not necessary to include it in the logical framework

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Preconditions
A precondition is a

A

condition that must be satisfied before the project starts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Examples OF Preconditions

A

‘an end to the conflict allows access to the area’

17
Q

Examples of Preconditions

A

‘communities agree to participate
in activity implementation’

18
Q

Examples of Preconditions

A