Risk Response Planning Flashcards
While the risk management team is in the project execution stage, a risk response plan is implemented after predetermined conditions that have been documented occur, indicating the need for a response. A contingency plan proves ineffective. What should the risk management team do NEXT? A. Implement a contingency strategy B. Accept the result C. Develop a new response D. Implement a fallback plan
D. A fallback plan is a planned response that is implemented after all other planned responses prove ineffective. Option A is incorrect since a contingency strategy (response plan) has already been used.
Over past three years, the facility where important project equipment is stored has experienced an increase in theft. One month after the project began, a critical piece of production equipment was stolen and cost the project team $100,000 for replacement. What should have been done to prepare for this risk?
A. Purchased insurance
B. Planned for a reserve to cover replacement costs
C. Installed a security camera
D. Moved the equipment to a safer location
A. It would be a better option to transfer the risk to another organization. Option C only reduces the probability of the theft by an unknown amount and therefore this is not the best solution.
Changing the project schedule to deal with positive risk is an example of which risk response plan? A. Avoid B. Exploit C. Mitigate D. Enhance
B. Exploit is similar to the “avoid” strategy that is to eliminate the uncertainty of a risk. For this case, we are eliminating the uncertainty by altering the project schedule to ensure the positive risk occurs.
A project manager has decided to recommend reducing the impact of a risk in response to a negative risk that could not be eliminated. What is this strategy? A. Avoid B. Enhance C. Passive acceptance D. Mitigate
D. Reducing the impact and / or probability of a risk in response to a negative risk is an example of mitigating it.
Which of the following is an example of exploiting a risk?
A. Starting a joint venture with a production company
B. Adding an experience resource to complete an activity faster
C. Performing additional testing to increase the probability and impact
D. Put aside a reserve fund to manage the risk
B. Adding an experience resource is often a way to expedite an activity or improve the quality. However, this would normally involve higher costs.
A few days before the project execution, the risk management team found a positive risk that could decrease the project costs by 35%. However, making the risk to occur would increase the current project costs by 10%. It would be in the project’s best interest to: A. Share the risk B. Mitigate the risk C. Exploit the risk D. Accept the risk
C. The savings from the positive risk exceeds the cost. Therefore it would be best for the project to ensure the risk happens, which would be the exploit strategy.
Changing the project schedule to deal with negative risk is an example of which risk response plan? A. Transfer B. Mitigate C. Exploit D. Avoid
D. Changing a plan to eliminate a risk is the “avoid” strategy.
Which of the following is NOT used in developing a risk response? A. The contingency strategy B. Documented potential responses C. The risk rating D. Root causes of risk
A. The contingency strategy is used as a technique during the development of a risk response and not an input.
Which of the following is an example of mitigating a risk? A. Purchase insurance B. Develop a partnership C. Build a prototype D. Change the project schedule
C. Build a prototype is mitigating a risk by reducing the probability and / or impact of a risk. Option A is transfer strategy; option B is share strategy; and option D is avoid strategy.
Two months after the execution of a project work had started, a new risk was found. After assessing the risk, it was determined that responding to the risk would be more costly than allowing the risk to follow its own course. A reserve was set aside to deal with the result of the risk, if it were to occur. What strategy was implemented? A. Transfer B. Passive acceptance C. Avoid D. Active acceptance
D. In this scenario, it was decided to accept the risk. However, a reserve is set aside to deal with the risk if it were to occur, which is an active acceptance strategy.
Which of the following is NOT utilized from within the risk management plan for risk responses planning purposes? A. Roles and responsibilities B. Report formats C. Time and budget contingencies D. Risk thresholds
B. After the risk management plan is created, it is used as an input to the remaining five risk management processes. Risk response planning uses all of the options listed except B – reporting formats. In addition, the process also utilizes risk analysis definitions.
All of the following are examples of transfer as a risk response strategy EXCEPT: A. Prototypes B. Guaranties C. Warranties D. Bonds
A. Options B, C, and D are common type of transfer which is also known as purchasing insurance. All these methods are transferring risks to third party.
A project manager of a mid-size project uncovered a risk that, if it were to happen, could shorten the length of the project by 3 months. This is a saving of $120,000 for the project. All the stakeholders agreed that anything within reason should be done to make sure that this risk occurs. What risk responses strategy is the project manager most likely to use? A. Share B. Enhance C. Active acceptance D. Exploit
D. Exploit strategy is used by a project team when the interest is to make sure the risk occurs, as well as increasing the impact of the positive risk.
Which of the following response strategy should a project manager be using to increase the probability that a positive event will occur, and / or to increase the impact of the positive event? A. Mitigate B. Exploit C. Enhance D. Share
C. Enhance is used to in handling positive risks when the project organization wants to increase the probability and / or impact of the risk.
A project manager was told by his team members that the initial planned response for a particular risk had proved ineffective. The stakeholders had given the project manager authority to make decisions regarding risk responses. What should the project manager do NEXT? A. Accept the outcome B. Implement a fallback plan C. Implement the planned response D. Implement a contingency plan
B. Fallback plans are planned responses that are executed when the initial planned response proves not effective.