Risk and Issue Management Flashcards

1
Q
  1. Initiation
A

Setting up the process and formulating a risk management plan which will set out a framework for the project manager and project team to ensure risks are managed in a consistent and proactive manner.
Setting up a risk register and deciding risk categories.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. Identification
A

Various techniques are used to identify as many possible risks as possible which are added to the risk register. A combination of the below methods is usually the most effective way to identify all relevant risks.

a. Brainstorming
b. SWOT analysis
c. Assumptions analysis
d. Constraints analysis
e. Using the WBS (work breakdown structure)
f. Interviews

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. Assessment
A

All identified risks must now be assessed and prioritised.
Determining the probability and impact and plotting on a probability and impact grid.
Either on a qualitative scale e.g. very low, low, medium, high, very high or on a quantitative scale e.g 1-5
Exposure, or the risk severity, is calculated by multiplying the impact by the probability.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. Response Planning
A

An appropriate response is planned
There are 5 common strategies for addressing risks or threats:
1. Avoid
2. Transfer
3. Reduce / Mitigate
4. Accept
5. Contingency Plan

Response planning actions:
1. Identify possible responses
2. Evaluate each possible response considering the costs involved and how much it would reduce the risk exposure
3. Identify the most cost effective response
4. Check the effect on the budget against the business plan to ensure the project is still viable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Implement Responses
A

For each risk that has a planned response, the risk owner must monitor and review on a regular basis throughout the project.

The primary tool for managing and monitoring risk is the risk register.